2019‐2023 Capital Projects
Presented on June 11th by Public Works Staff
2019 2023 Capital Projects Presented on June 11 th by Public Works - - PowerPoint PPT Presentation
2019 2023 Capital Projects Presented on June 11 th by Public Works Staff Priority and Structure in the CMIP Capital Projects Maintenance activities Legal mandates (ADA, and EPA) Grants, Economic Development, or Special
Presented on June 11th by Public Works Staff
and EPA)
Development, or Special Assessment Funds
Involvement
– Contractor working on storm drainage and curb and gutter currently – Project ahead of schedule to be completed before Sept. 2019.
– Initial plans to be reviewed to KDOT by end of May – Project to Bid in Sept. 2020
prior to bidding
combination of Federal Grant and Matching Local Funds. (debt)
– Phase I ‐ $13.3 Million – Phase II ‐ $9.0 Million (est.)
Total Project Value: $4,975,000
– $3,000,000 Debt – $1,975,000 Dedicated Sales Tax
Intersection (2020‐2022)
– Est. $7.0M
Intersection (2020)
– Est. $350,000
– 36th St. and Ohio Ave. – Est. $700,000
Improvements (2019‐2020)
– Est. $600,000
Phase I
– Est. $4.0 Million – Begin in 2021
Reconstruction
– Est. $2.0 Million – Begin in 2022
improvements
– Partner with KDOT, local cities, and counties
– Total Est. $3.3 Million
– Possibility of getting a portion or all covered as well
Intersection (2022)
–
(2021)
– NW Middle and Caruthers Elem. – Est. $2.3 Million
Improvements (2022)
– Parallel Pkwy. to Leavenworth Rd. – Est. $7.0 Million
(2020)
– 6th St. to 7th St. – Est. $1.3 Million
Minnesota Ave.
– Federal Grant (MARC)
– Matching Local Funds (Debt)
– Design: 2021 – Construct: 2022
Modernization
Reconstruction
Metropolitan Ave. to Merriam Ln.
Leavenworth Rd
Turner Diagonal
Improvements
115th St
115th St. to 123rd St.
St.
Intersection Improvements (2022)
Interstate 70 and Turner Diag. Interchange Reconstruction
– Federal ‐ $17 Million – State ‐ $8.5 Million – Local/Development ‐ $8.5 Million
– Total Est. $70.5 Million
– Total Est. $9.5 Million
– Total Est. $5.0 Million
– Total Est. $1.0 Million
– Total Est. $1.5 Million
Wolcott Treatment Plan Expansion
Million
Kaw Point BioSolids
– Possible revenue source for the future.
– Joint Project with KVDD, USACE, KCMO, and BNSF Rail. – Local Share ‐ $6.0 Million (debt)
– Joint Project with BNSF Rail, USACE, and KCMO – UG Portion ‐ $4.5 Million (debt)
– Project Timeline ‐ Decades – Total Cost $365 Million
Plan will focus on individual watersheds and identify current issues for future projects
Juvenile Justice Center
New Parking
Juvenile Justice Center
June 2018
– Begin: Sept. 2018 – Complete: 2019
Piper Fire Station
– In Progress
– Late 2018, Early 2019
Courthouse Roof and Masonry Repairs
– Work to begin in late 2018 and completed in 2019.
Memorial Hall Window and HVAC Projects
– Windows to be completed in 2018 – HVAC to be completed by 2019