A pion beam line option for LBNF - nuPIL Outline Introduction - - PowerPoint PPT Presentation
A pion beam line option for LBNF - nuPIL Outline Introduction - - PowerPoint PPT Presentation
A pion beam line option for LBNF - nuPIL Outline Introduction Updated design overview Neutrino flux comparison Physics comparison Details of design Engineering considerations Conclusions and moving forward July 21, 2016
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
Outline
- Introduction
- Updated design overview
- Neutrino flux comparison
- Physics comparison
- Details of design
- Engineering considerations
- Conclusions and moving forward
July 21, 2016 2
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
Credits
Jean-Baptiste Lagrange Jaroslaw Pasternak Imperial College London AB Pilar Coloma Ao Liu David Neuffer Milorad Popovic (working on independent concept) Fermilab Terry Hart University of Mississippi Elizabeth Worcester BNL
July 21, 2016 3
Total effort is only ~ 1.5 FTE
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
Introduction
- The basic concept is to design a sign-selected,
large acceptance (transverse and in momentum) pion beam line.
– neutrinos from a pion beam line: nuPIL
- Send only pions in desired momentum range
towards DUNE detector (40kT LAr assumed in what follows.
– Of course, protons/kaons/muons in the same momentum band will follow along
- Ideal configuration: have a 5.8o bend matched
into a straight transport beam line (~200m)
- Basic design evolved from the pion injection
beam line for nuSTORM.
July 21, 2016 4
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
nuPIL advantages I
Beam systematics
- Beam systematics concerns for conventional horn-focused ν beam
line:
– Secondary particle production
- Particle types, flux and energy distribution
– Proton beam targeting stability – Target degradation/change – Horn stability – Target/Horn module mass uncertainty
- Water, supports, etc.
- Since the pion flux is measured in situ by the beam line
instrumentation (flux, momentum distribution, emittance), the above are largely factored out.
– Some R&D on instrumentation is needed, but work began and vendor contacts have been initiated. – Can also include commissioning/calibration runs that utilize destructive (for the beam) instrumentation
- In addition the ν background in the anti-ν beam (& vice versa) is
significantly reduced
– Some issues with new bend lattice
July 21, 2016 5
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
Beam systematics II Diagnostics
Quantity Detector(s) Comments
Beam Intensity Beam current transformers <1% resolution obtainable Beam Position BPMs 1 cm resolution Beam profile Scintillating screens, etc Destructive Energy Polarimeter <1% resolution Energy spread Profile measurement in bend Beam loss Conventional Timing Conventional Pion/proton separation
- Beam can be fully characterized, including
destructive methods during a commissioning phase
- Magnet currents can be monitored and
controlled with precision
- all magnets are DC
Instrumentation for the beam line (straight)
Parameter Uncertainty Intensity 0.3% Divergence 0.6% Energy spread 0.1% Total ≤ 1%
nuSTORM study
July 21, 2016 6
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
Update since May CM
- New bend with wider momentum acceptance
- Horn optimization for this bend
– 4 λ long C target
- Match into straight beam line
- Transport (~200 m) in beam line
July 21, 2016 7
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
nuPIL ν flux comparison May CM & now
July 21, 2016 8
This represents a 42% increase in flux
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
nuPIL Lattice13-Hybrid vs. LBNF/DUNE 3-Horn Opt
July 21, 2016 9
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
CP violation sensitivity from Elizabeth W.
July 21, 2016 10
π /
CP
δ
- 1 -0.8 -0.6 -0.4 -0.2
0.2 0.4 0.6 0.8 1
2
χ ∆ = σ 1 2 3 4 5 6 7 8
CP Violation Sensitivity
π /
CP
δ
- 1 -0.8 -0.6 -0.4 -0.2
0.2 0.4 0.6 0.8 1
2
χ ∆ = σ 1 2 3 4 5 6 7 8
DUNE Sensitivity Normal Hierarchy years ν + ν 3.5+3.5 = 0.085
13
θ 2
2
sin = 0.45
23
θ
2
sin
σ 3
σ 5
CDR Optimized Design 3-horn Optimized Design nuPIL Design
CP Violation Sensitivity
- Sensitivity calculations
produced by Elizabeth Worcester
- Flux for LBNF beams
produced by Laura Fields
- Flux for nuPIL beam provided
by Ao Liu
- Unless otherwise noted, all
configurations (GLoBES code,
- scillation parameters,
systematic selection efficiencies, etc) are identical to those used in the CDR
- LBNF optimized: identical to
“optimized design” in CDR, but with 204 m DP
- LBNF 3-horn optimized:
updated LBNF optimized design with improvements including, but not limited to moving to 3-horn design.
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
Hierarchy
July 21, 2016 11
π /
CP
δ
- 1 -0.8 -0.6 -0.4 -0.2
0.2 0.4 0.6 0.8 1
2
χ ∆ 5 10 15 20 25
Mass Hierarchy Sensitivity
π /
CP
δ
- 1 -0.8 -0.6 -0.4 -0.2
0.2 0.4 0.6 0.8 1
2
χ ∆ 5 10 15 20 25
CDR Optimized Design 3-horn Optimized Design nuPIL Design
DUNE Sensitivity Normal Hierarchy years ν + ν 3.5+3.5 = 0.085
13
θ 2
2
sin = 0.45
23
θ
2
sin Mass Hierarchy Sensitivity
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
3σ coverage over 75%
- f δ range (Pilar Coloma)
July 21, 2016 12
NuPIL - Latt.13 DUNE CDR
0.0 0.2 0.4 0.6 0.8 1.0 1 2 3 4 5 6
δ
σ
3.5 + 3.5 years
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
Normalization uncertainties
- I also asked Elizabeth to plot a case with the
current estimates for the normalization uncertainties for LBNF/DUNE and nuPIL/ DUNE
– LBNF/DUNE: Taken from the case made in the CDR = 5⊕2 – nuPIL: With beam line instrumentation and from studies done for nuSTORM: 4.5⊕1.5
- This was done for a large exposure
– 10.4 + 10.4 years
July 21, 2016 13
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
CP Violation sensitivity
July 21, 2016 14
π /
CP
δ
- 1 -0.8 -0.6 -0.4 -0.2
0.2 0.4 0.6 0.8 1
2
χ ∆ = σ 2 4 6 8 10 12
CP Violation Sensitivity
π /
CP
δ
- 1 -0.8 -0.6 -0.4 -0.2
0.2 0.4 0.6 0.8 1
2
χ ∆ = σ 2 4 6 8 10 12
DUNE Sensitivity Normal Hierarchy years ν + ν 10.4+10.4 = 0.085
13
θ 2
2
sin = 0.45
23
θ
2
sin
σ 3 σ 5
CDR Optimized Design 3-horn Optimized Design nuPIL Design CDR norm. unc.
- Est. nuPIL norm. unc.
CP Violation Sensitivity
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
EW’s plot shown at CM
July 21, 2016 15
- The take away from this
plot is that if, for some reason, your normalization uncertainties are larger than anticipated, the precision of this measurement will degrade quickly
- Starting off with
anticipated smaller normalization errors leaves more room.
- A well controlled
measured beam line as in nuPIL has the potential to be a great advantage
Configuration Details
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
Schematic
Section view
- Target Hall complex at MI depth (could raise to surface level)
- “Conventional” target+horn(single) + 5.8° bend + production straight
(204m)
- Bend: sign and momentum selection
– With 2.4MW on target there is now ~ 145 kW in the beam
- Production straight: transport of beam to end of decay straight.
- ~110 kW pions + ~30 kW protons at beginning
- ~35 kW + ~17 kW = ~42 kW at end & into absorber (+ ~25 kW in muon)
July 21, 2016 17
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
“Waste power” mitigation
- “Waste power” is kept at MI depth.
– Less problematic than dealing with underground (cheaper)
- Since no line-of-sight from target to production straight,
unwanted charged particles and neutrons can be absorbed at/near surface level in the target hall complex.
– Will show preliminary MARS results. – Power going underground limited to ~ 145 kW (2.4MW on target)
67 kW 145 kW 2.4 MW
Primary absorber
Plan (TOP) view schematic One concept for Absorber hall
July 21, 2016 18
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
nuPIL
Current status
- FFAG 5.8o bend
– Double achromat Bend: 4 FDF triplets (12 magnets)
- 3 Quad match into beam line straight
- Quad triplet (FDF) straight beam line
- This is a hybrid system: FFAG - Quad
July 21, 2016 19
Note: Aperture stops for wrong-sign π only introduced after magnets 11 & 12 at present
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
Beam propagation through the bend
π+ decay off
After horn After dispersion creator After bend cell 1 After bend cell 2 (end) At end of decay pipe
July 21, 2016 20
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
ν production straight
- The π decay beam line channel (production
straight, formally known as a Decay Pipe) is a 200 meters long straight beam line consisting
- f a total of 27 quadrupole magnets. The first
three quads match the optics after the FFAG steering bend to the periodic cell optics, which is defined by a triplet cell (FDF).
July 21, 2016 21
G4Beamline visualization: Red vertical bands are quads
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
Tunability
- General nuPIL tuning:
– Horn current can be adjusted (within certain margins) for input matching – Ratio of B field in the F and D (focusing/de-focusing) magnets allows for the adjustment of non-bending plane optics – Bending plane tuning of magnets will allow one to adjust bending plane trajectory – Non-bending plane correctors (one per cell) should be enough for non-bending trajectory adjustment
- Example (LowE tune for Lattice 13):
July 21, 2016 22
Trajectories for 0.85 GeV/c, 1.75 GeV/c and 3.6 GeV/c pions in “tuned” Lattice 13. High_E (tau) work in progress.
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
Lattice 13 Beam Power Loss
- Yes, this is a problem
– ~40 kW of useful pions + ~12 kW protons
- Note: 35 kW of pion power produces the Lattice 13 ν flux
- Approach:
– Optimize match and Quad lattice, run GA, repeat – What can’t be made “useful” (transported to end) – absorb (apertures) in bend (TS)
July 21, 2016 23
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
Engineering considerations
- The nuPIL configuration does add active
components in the target station.
- Can they survive?
- A MARS simulation of a “parameterized” TS
has been performed.
- Magnets simulated with cylindrical symmetry
with 80 cm bore and 1m Fe annulus outside bore as return yoke.
- Uniform (dipole) magnetic filed in bore
July 21, 2016 24
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
MARS model
July 21, 2016 25
White: Vacuum Red: Iron Grey: Concrete Purple: Poly
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
MARS – 5 GeV/c pions
July 21, 2016 26
C target set to vacuum
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
MARS: 80 GeV protons on C
July 21, 2016 27
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
MARS: Energy deposition
July 21, 2016 28
- Largest dose is in magnet 1
bore (coils)
– Note: Magnet 3 is acting as primary proton beam stop in this model. (Not good engineering practice)
- This dose ~2 X 10-6 GeV/g-
- POT. The technology we
envision using here are MgO insulated magnets as developed in Japan and used at J-PARC. Lifetime of 1011 Gy
– Hirose et al., IEEE
TRANSACTIONS ON APPLIED SUPERCONDUCTIVITY, VOL. 22,
- NO. 3, JUNE 2012
- This would correspond to 20
years of running at 2.4 MW.
- Also, very little radiation
dribbling out of back of TS
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
Target station design
- The baseline design for LBNF follows the
design for NuMI
– To a large extend, it is the NuMI TS at surface
- This configuration does not accommodate the
nuPIL components very easily
- TS design the NF Study 1
– ORNL/TM-2001/124 “Support Facility for a Mercury-Jet Target Neutrino Factory”, September, 2001.
July 21, 2016 29
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
NF TS Design
July 21, 2016 30
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
NF TS Design II
July 21, 2016 31
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
NF TS Design III
July 21, 2016 32
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
NF TS Design IV
July 21, 2016 33
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
Conclusion
- Using a pion beam line after a high-power target/
horn module presents an exciting possibility for producing a νµ beam for long-baseline ν oscillation experiments
– Comparable physics performance. – Much higher beam quality w/r to beam purity
- Lattice 13 “wrong-sign” bkg reduction - work in progress
– Beam systematics uncertainties reduced
- Neutrino beam flux determined directly from parent
particles, not induced from other experiments or MC.
- Uncertainties reduced by possibly a large factor due to the
beam line instrumentation
– Underground radiological issues essentially removed
- At this stage of the analysis, the nuPIL concept is
cost neutral
July 21, 2016 34
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
Moving forward
- Continued work
– We are still on a sharp rising curve w/r to further
- ptimization.
- Improved flux by ~40% since CM
- Expect further significant improvement.
– Things to study:
- Look at 60 GeV protons
- Target/Horn design
– Our horn efficiency is only ~40% compared to 70% (NuMI)
- Match & Beam line lattice optimization
– May include iteration on the bend too
- Apertures in bend
– Losses in production straight
- Address Eν tuning to both lower and higher Eν
– Which is more important first?
July 21, 2016 35
Backup
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
Pion Instrumented Line (nuPIL)
X X X
Eliminate µ storage capability
X
1300 km Residual high energy protons bend down 2.9° bend down 2.9° π d e c a y i n t h e s t r a i g h t
Target Station
nuSTORM
π + → µ+ +νµ µ+ → e+ +νe +ν µ David Neuffer, Ao Liu 2 km Ao Liu, JB Lagrange Kill the STORM part
July 21, 2016 37
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
FFAG “C” magnet (bend)
July 21, 2016 38
Alan Bross | DUNE Accelerator and Beam Interface Group Meeting
nuPIL Horn sketch
July 21, 2016 39
500 1000 1500 2000 2500 3000 3500 4000
Z (mm)
50 100 150 200 250 300 350 400
Y (mm) Optimized horn for lattice 11/13, with 160 cm Carbon target
195397.38
X: 3991 Y: 76.68