A pion beam line option for LBNF - nuPIL Outline Introduction - - PowerPoint PPT Presentation

a pion beam line option for lbnf nupil outline
SMART_READER_LITE
LIVE PREVIEW

A pion beam line option for LBNF - nuPIL Outline Introduction - - PowerPoint PPT Presentation

A pion beam line option for LBNF - nuPIL Outline Introduction Updated design overview Neutrino flux comparison Physics comparison Details of design Engineering considerations Conclusions and moving forward July 21, 2016


slide-1
SLIDE 1

A pion beam line option for LBNF - nuPIL

slide-2
SLIDE 2

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

Outline

  • Introduction
  • Updated design overview
  • Neutrino flux comparison
  • Physics comparison
  • Details of design
  • Engineering considerations
  • Conclusions and moving forward

July 21, 2016 2

slide-3
SLIDE 3

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

Credits

Jean-Baptiste Lagrange Jaroslaw Pasternak Imperial College London AB Pilar Coloma Ao Liu David Neuffer Milorad Popovic (working on independent concept) Fermilab Terry Hart University of Mississippi Elizabeth Worcester BNL

July 21, 2016 3

Total effort is only ~ 1.5 FTE

slide-4
SLIDE 4

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

Introduction

  • The basic concept is to design a sign-selected,

large acceptance (transverse and in momentum) pion beam line.

– neutrinos from a pion beam line: nuPIL

  • Send only pions in desired momentum range

towards DUNE detector (40kT LAr assumed in what follows.

– Of course, protons/kaons/muons in the same momentum band will follow along

  • Ideal configuration: have a 5.8o bend matched

into a straight transport beam line (~200m)

  • Basic design evolved from the pion injection

beam line for nuSTORM.

July 21, 2016 4

slide-5
SLIDE 5

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

nuPIL advantages I

Beam systematics

  • Beam systematics concerns for conventional horn-focused ν beam

line:

– Secondary particle production

  • Particle types, flux and energy distribution

– Proton beam targeting stability – Target degradation/change – Horn stability – Target/Horn module mass uncertainty

  • Water, supports, etc.
  • Since the pion flux is measured in situ by the beam line

instrumentation (flux, momentum distribution, emittance), the above are largely factored out.

– Some R&D on instrumentation is needed, but work began and vendor contacts have been initiated. – Can also include commissioning/calibration runs that utilize destructive (for the beam) instrumentation

  • In addition the ν background in the anti-ν beam (& vice versa) is

significantly reduced

– Some issues with new bend lattice

July 21, 2016 5

slide-6
SLIDE 6

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

Beam systematics II Diagnostics

Quantity Detector(s) Comments

Beam Intensity Beam current transformers <1% resolution obtainable Beam Position BPMs 1 cm resolution Beam profile Scintillating screens, etc Destructive Energy Polarimeter <1% resolution Energy spread Profile measurement in bend Beam loss Conventional Timing Conventional Pion/proton separation

  • Beam can be fully characterized, including

destructive methods during a commissioning phase

  • Magnet currents can be monitored and

controlled with precision

  • all magnets are DC

Instrumentation for the beam line (straight)

Parameter Uncertainty Intensity 0.3% Divergence 0.6% Energy spread 0.1% Total ≤ 1%

nuSTORM study

July 21, 2016 6

slide-7
SLIDE 7

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

Update since May CM

  • New bend with wider momentum acceptance
  • Horn optimization for this bend

– 4 λ long C target

  • Match into straight beam line
  • Transport (~200 m) in beam line

July 21, 2016 7

slide-8
SLIDE 8

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

nuPIL ν flux comparison May CM & now

July 21, 2016 8

This represents a 42% increase in flux

slide-9
SLIDE 9

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

nuPIL Lattice13-Hybrid vs. LBNF/DUNE 3-Horn Opt

July 21, 2016 9

slide-10
SLIDE 10

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

CP violation sensitivity from Elizabeth W.

July 21, 2016 10

π /

CP

δ

  • 1 -0.8 -0.6 -0.4 -0.2

0.2 0.4 0.6 0.8 1

2

χ ∆ = σ 1 2 3 4 5 6 7 8

CP Violation Sensitivity

π /

CP

δ

  • 1 -0.8 -0.6 -0.4 -0.2

0.2 0.4 0.6 0.8 1

2

χ ∆ = σ 1 2 3 4 5 6 7 8

DUNE Sensitivity Normal Hierarchy years ν + ν 3.5+3.5 = 0.085

13

θ 2

2

sin = 0.45

23

θ

2

sin

σ 3

σ 5

CDR Optimized Design 3-horn Optimized Design nuPIL Design

CP Violation Sensitivity

  • Sensitivity calculations

produced by Elizabeth Worcester

  • Flux for LBNF beams

produced by Laura Fields

  • Flux for nuPIL beam provided

by Ao Liu

  • Unless otherwise noted, all

configurations (GLoBES code,

  • scillation parameters,

systematic selection efficiencies, etc) are identical to those used in the CDR

  • LBNF optimized: identical to

“optimized design” in CDR, but with 204 m DP

  • LBNF 3-horn optimized:

updated LBNF optimized design with improvements including, but not limited to moving to 3-horn design.

slide-11
SLIDE 11

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

Hierarchy

July 21, 2016 11

π /

CP

δ

  • 1 -0.8 -0.6 -0.4 -0.2

0.2 0.4 0.6 0.8 1

2

χ ∆ 5 10 15 20 25

Mass Hierarchy Sensitivity

π /

CP

δ

  • 1 -0.8 -0.6 -0.4 -0.2

0.2 0.4 0.6 0.8 1

2

χ ∆ 5 10 15 20 25

CDR Optimized Design 3-horn Optimized Design nuPIL Design

DUNE Sensitivity Normal Hierarchy years ν + ν 3.5+3.5 = 0.085

13

θ 2

2

sin = 0.45

23

θ

2

sin Mass Hierarchy Sensitivity

slide-12
SLIDE 12

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

3σ coverage over 75%

  • f δ range (Pilar Coloma)

July 21, 2016 12

NuPIL - Latt.13 DUNE CDR

0.0 0.2 0.4 0.6 0.8 1.0 1 2 3 4 5 6

δ

σ

3.5 + 3.5 years

slide-13
SLIDE 13

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

Normalization uncertainties

  • I also asked Elizabeth to plot a case with the

current estimates for the normalization uncertainties for LBNF/DUNE and nuPIL/ DUNE

– LBNF/DUNE: Taken from the case made in the CDR = 5⊕2 – nuPIL: With beam line instrumentation and from studies done for nuSTORM: 4.5⊕1.5

  • This was done for a large exposure

– 10.4 + 10.4 years

July 21, 2016 13

slide-14
SLIDE 14

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

CP Violation sensitivity

July 21, 2016 14

π /

CP

δ

  • 1 -0.8 -0.6 -0.4 -0.2

0.2 0.4 0.6 0.8 1

2

χ ∆ = σ 2 4 6 8 10 12

CP Violation Sensitivity

π /

CP

δ

  • 1 -0.8 -0.6 -0.4 -0.2

0.2 0.4 0.6 0.8 1

2

χ ∆ = σ 2 4 6 8 10 12

DUNE Sensitivity Normal Hierarchy years ν + ν 10.4+10.4 = 0.085

13

θ 2

2

sin = 0.45

23

θ

2

sin

σ 3 σ 5

CDR Optimized Design 3-horn Optimized Design nuPIL Design CDR norm. unc.

  • Est. nuPIL norm. unc.

CP Violation Sensitivity

slide-15
SLIDE 15

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

EW’s plot shown at CM

July 21, 2016 15

  • The take away from this

plot is that if, for some reason, your normalization uncertainties are larger than anticipated, the precision of this measurement will degrade quickly

  • Starting off with

anticipated smaller normalization errors leaves more room.

  • A well controlled

measured beam line as in nuPIL has the potential to be a great advantage

slide-16
SLIDE 16

Configuration Details

slide-17
SLIDE 17

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

Schematic

Section view

  • Target Hall complex at MI depth (could raise to surface level)
  • “Conventional” target+horn(single) + 5.8° bend + production straight

(204m)

  • Bend: sign and momentum selection

– With 2.4MW on target there is now ~ 145 kW in the beam

  • Production straight: transport of beam to end of decay straight.
  • ~110 kW pions + ~30 kW protons at beginning
  • ~35 kW + ~17 kW = ~42 kW at end & into absorber (+ ~25 kW in muon)

July 21, 2016 17

slide-18
SLIDE 18

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

“Waste power” mitigation

  • “Waste power” is kept at MI depth.

– Less problematic than dealing with underground (cheaper)

  • Since no line-of-sight from target to production straight,

unwanted charged particles and neutrons can be absorbed at/near surface level in the target hall complex.

– Will show preliminary MARS results. – Power going underground limited to ~ 145 kW (2.4MW on target)

67 kW 145 kW 2.4 MW

Primary absorber

Plan (TOP) view schematic One concept for Absorber hall

July 21, 2016 18

slide-19
SLIDE 19

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

nuPIL

Current status

  • FFAG 5.8o bend

– Double achromat Bend: 4 FDF triplets (12 magnets)

  • 3 Quad match into beam line straight
  • Quad triplet (FDF) straight beam line
  • This is a hybrid system: FFAG - Quad

July 21, 2016 19

Note: Aperture stops for wrong-sign π only introduced after magnets 11 & 12 at present

slide-20
SLIDE 20

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

Beam propagation through the bend

π+ decay off

After horn After dispersion creator After bend cell 1 After bend cell 2 (end) At end of decay pipe

July 21, 2016 20

slide-21
SLIDE 21

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

ν production straight

  • The π decay beam line channel (production

straight, formally known as a Decay Pipe) is a 200 meters long straight beam line consisting

  • f a total of 27 quadrupole magnets. The first

three quads match the optics after the FFAG steering bend to the periodic cell optics, which is defined by a triplet cell (FDF).

July 21, 2016 21

G4Beamline visualization: Red vertical bands are quads

slide-22
SLIDE 22

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

Tunability

  • General nuPIL tuning:

– Horn current can be adjusted (within certain margins) for input matching – Ratio of B field in the F and D (focusing/de-focusing) magnets allows for the adjustment of non-bending plane optics – Bending plane tuning of magnets will allow one to adjust bending plane trajectory – Non-bending plane correctors (one per cell) should be enough for non-bending trajectory adjustment

  • Example (LowE tune for Lattice 13):

July 21, 2016 22

Trajectories for 0.85 GeV/c, 1.75 GeV/c and 3.6 GeV/c pions in “tuned” Lattice 13. High_E (tau) work in progress.

slide-23
SLIDE 23

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

Lattice 13 Beam Power Loss

  • Yes, this is a problem

– ~40 kW of useful pions + ~12 kW protons

  • Note: 35 kW of pion power produces the Lattice 13 ν flux
  • Approach:

– Optimize match and Quad lattice, run GA, repeat – What can’t be made “useful” (transported to end) – absorb (apertures) in bend (TS)

July 21, 2016 23

slide-24
SLIDE 24

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

Engineering considerations

  • The nuPIL configuration does add active

components in the target station.

  • Can they survive?
  • A MARS simulation of a “parameterized” TS

has been performed.

  • Magnets simulated with cylindrical symmetry

with 80 cm bore and 1m Fe annulus outside bore as return yoke.

  • Uniform (dipole) magnetic filed in bore

July 21, 2016 24

slide-25
SLIDE 25

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

MARS model

July 21, 2016 25

White: Vacuum Red: Iron Grey: Concrete Purple: Poly

slide-26
SLIDE 26

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

MARS – 5 GeV/c pions

July 21, 2016 26

C target set to vacuum

slide-27
SLIDE 27

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

MARS: 80 GeV protons on C

July 21, 2016 27

slide-28
SLIDE 28

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

MARS: Energy deposition

July 21, 2016 28

  • Largest dose is in magnet 1

bore (coils)

– Note: Magnet 3 is acting as primary proton beam stop in this model. (Not good engineering practice)

  • This dose ~2 X 10-6 GeV/g-
  • POT. The technology we

envision using here are MgO insulated magnets as developed in Japan and used at J-PARC. Lifetime of 1011 Gy

– Hirose et al., IEEE

TRANSACTIONS ON APPLIED SUPERCONDUCTIVITY, VOL. 22,

  • NO. 3, JUNE 2012
  • This would correspond to 20

years of running at 2.4 MW.

  • Also, very little radiation

dribbling out of back of TS

slide-29
SLIDE 29

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

Target station design

  • The baseline design for LBNF follows the

design for NuMI

– To a large extend, it is the NuMI TS at surface

  • This configuration does not accommodate the

nuPIL components very easily

  • TS design the NF Study 1

– ORNL/TM-2001/124 “Support Facility for a Mercury-Jet Target Neutrino Factory”, September, 2001.

July 21, 2016 29

slide-30
SLIDE 30

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

NF TS Design

July 21, 2016 30

slide-31
SLIDE 31

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

NF TS Design II

July 21, 2016 31

slide-32
SLIDE 32

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

NF TS Design III

July 21, 2016 32

slide-33
SLIDE 33

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

NF TS Design IV

July 21, 2016 33

slide-34
SLIDE 34

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

Conclusion

  • Using a pion beam line after a high-power target/

horn module presents an exciting possibility for producing a νµ beam for long-baseline ν oscillation experiments

– Comparable physics performance. – Much higher beam quality w/r to beam purity

  • Lattice 13 “wrong-sign” bkg reduction - work in progress

– Beam systematics uncertainties reduced

  • Neutrino beam flux determined directly from parent

particles, not induced from other experiments or MC.

  • Uncertainties reduced by possibly a large factor due to the

beam line instrumentation

– Underground radiological issues essentially removed

  • At this stage of the analysis, the nuPIL concept is

cost neutral

July 21, 2016 34

slide-35
SLIDE 35

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

Moving forward

  • Continued work

– We are still on a sharp rising curve w/r to further

  • ptimization.
  • Improved flux by ~40% since CM
  • Expect further significant improvement.

– Things to study:

  • Look at 60 GeV protons
  • Target/Horn design

– Our horn efficiency is only ~40% compared to 70% (NuMI)

  • Match & Beam line lattice optimization

– May include iteration on the bend too

  • Apertures in bend

– Losses in production straight

  • Address Eν tuning to both lower and higher Eν

– Which is more important first?

July 21, 2016 35

slide-36
SLIDE 36

Backup

slide-37
SLIDE 37

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

Pion Instrumented Line (nuPIL)

X X X

Eliminate µ storage capability

X

1300 km Residual high energy protons bend down 2.9° bend down 2.9° π d e c a y i n t h e s t r a i g h t

Target Station

nuSTORM

π + → µ+ +νµ µ+ → e+ +νe +ν µ David Neuffer, Ao Liu 2 km Ao Liu, JB Lagrange Kill the STORM part

July 21, 2016 37

slide-38
SLIDE 38

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

FFAG “C” magnet (bend)

July 21, 2016 38

slide-39
SLIDE 39

Alan Bross | DUNE Accelerator and Beam Interface Group Meeting

nuPIL Horn sketch

July 21, 2016 39

500 1000 1500 2000 2500 3000 3500 4000

Z (mm)

50 100 150 200 250 300 350 400

Y (mm) Optimized horn for lattice 11/13, with 160 cm Carbon target

195397.38

X: 3991 Y: 76.68