A sustainable solution replacing an active and inefficient Dual - - PowerPoint PPT Presentation

a sustainable solution replacing an active and
SMART_READER_LITE
LIVE PREVIEW

A sustainable solution replacing an active and inefficient Dual - - PowerPoint PPT Presentation

A sustainable solution replacing an active and inefficient Dual Phase Extraction System Joyce Cruz - Project Geologist joyce.cruz@ch2m.com Joo Marcellino Project Manager joao.marcellino@ch2m.com Olivier Maurer Senior


slide-1
SLIDE 1

Joyce Cruz - Project Geologist – joyce.cruz@ch2m.com João Marcellino – Project Manager – joao.marcellino@ch2m.com Olivier Maurer – Senior Technologist – olivier.maurer@ch2m.com Christian Nogueira – Senior Reviewer – christian.nogueira@ch2m.com Renata Moura – Petrom Contract Manager - renata.moura@petrom.com.br

A sustainable solution replacing an active and inefficient Dual Phase Extraction System

slide-2
SLIDE 2

2

Schedule

  • Introduction
  • NAPL distribution model
  • Conceptual approach
  • Construction
  • Conclusions
slide-3
SLIDE 3

3

A sustainable solution replacing an active and inefficient Dual Phase Extraction System

slide-4
SLIDE 4

4

Introduction

We ¡will ¡present ¡the ¡main ¡steps ¡of ¡a ¡Permeable ¡Adsorp5ve ¡Barrier ¡system ¡at ¡the ¡ a ¡chemical ¡facility ¡near ¡São ¡Paulo ¡Brazil ¡(Petrom, ¡Mogi ¡das ¡Cruzes). ¡: ¡

  • ­‑ to ¡design ¡
  • ­‑ construct, ¡ ¡
  • ­‑ and ¡operate ¡
  • Dual-­‑Phase ¡ Extrac5on ¡ System ¡ in ¡ opera5on ¡ since ¡ 2007 ¡ to ¡ treat ¡ LNAPL, ¡ not ¡

sufficient ¡enough ¡and ¡not ¡sustainable. ¡ ¡ ¡

  • APer ¡revising ¡the ¡Site ¡Conceptual ¡Model ¡(CSM) ¡a ¡Passive ¡Barrier ¡System ¡was ¡

viewed ¡as ¡a ¡more ¡sustainable ¡solu5on ¡to ¡prevent ¡poten5al ¡light ¡non-­‑aqueous ¡ phase ¡ liquid ¡ (LNAPL) ¡ (di(2-­‑ethylhexyl)phthalate ¡ (DEHP) ¡ and ¡ di-­‑n-­‑butyl ¡ phthalate ¡ (DBP)) ¡ from ¡ entering ¡ a ¡ channelized ¡ water ¡ stream ¡ crossing ¡ the ¡ facility, ¡the ¡main ¡environmental ¡receptor. ¡ ¡

slide-5
SLIDE 5

5

The image cannot be displayed. Your computer may not have enough memory to open the image, or the image may have been corrupted. Restart your computer, and then open the file again. If the red x still appears, you may have to delete the image and then insert it again.

Localization

slide-6
SLIDE 6

6

New Conceptual Site Model (CSM)

  • Provided the necessary support for the technical team to propose a

modification on the remedial approach to CETESB, with the replacement

  • f the existing MPE system for a permeable reactive barrier (PAB wall).

Lost on MPE System efficiency Significant long term expenditures, without knowing the closure plan Company was looking for a consulting firm with exp. on Sustainable Remediation Main receptor of concern, not yet impacted.

slide-7
SLIDE 7

7

Petrom Study Case

  • 2013 – first steps, select a more sustainable solution and gain support from authorities

– Review and revision of existing conceptual site model (CSM) and Human Health Risk Assessment, – Presentation to CETESB of new remedial concept and approval

  • 2014 – Barrier Construction
  • 2015 – Cetesb presentation
  • 2015 – Dual system evaluation

Suggested that the free product plume was relatively stable with low mobility Narrow Valley NAPL containing di(2- ethylhexyl)phthalate (DEHP) and di-n-butyl phthalate (DBP)

slide-8
SLIDE 8

8

MPE System Loss of Efficiency

2000 4000 6000 8000 10000 12000 500 1000 1500 2000 2500 3000 3500 4000 4500 Acumulated(Liters) Volume (Liters)

Volume of Extract Product

Product removed from1999 to sept/2006: 54.717L Clear lost on efficiency Heavy O&M scope, costs and energy consumption

slide-9
SLIDE 9

9 Presentation Title

NAPL Distribution Model

slide-10
SLIDE 10

10

Bis[2-ethylhexyl]phtalate Soil Plume

Figure 1 Bis [2-ethylhexyl] phthalate Soil Plume Petrom Mogi Das Cruzes, Brazil

Barrier Wall

slide-11
SLIDE 11

11

0,1 % NAPL Saturation Plume

Figure 2a 0.1% LNAPL Saturation Plume Petrom Mogi Das Cruzes, Brazil

Barrier Wall Culverted Stream

slide-12
SLIDE 12

12

0,5 % NAPL Saturation Plume

Figure 2b 0.5% LNAPL Saturation Plume Petrom Mogi Das Cruzes, Brazil

Barrier Wall

slide-13
SLIDE 13

13

1,0 % NAPL Saturation Plume

Figure 2c 1.0% LNAPL Saturation Plume Petrom Mogi Das Cruzes, Brazil

Barrier Wall

slide-14
SLIDE 14

14

2,0 % NAPL Saturation Plume

Figure 2d 2.0% LNAPL Saturation Plume Petrom Mogi Das Cruzes, Brazil

Barrier Wall

slide-15
SLIDE 15

15 Presentation Title

Conceptual Approach

slide-16
SLIDE 16

16

New Remedial System (PAB)

  • Passive Adsorptive Barrier, using the natural GW flow to protect the

primary receptor as well as collecting the free phase and treating the dissolved phase

Added collection trench associated with 2 sumps and skimmers PMs to monitor and control the system performance

slide-17
SLIDE 17

17 Presentation Title

Construction

slide-18
SLIDE 18

18

The Barrier System

  • 4 ¡main ¡components: ¡

1. LNAPL ¡interceptor ¡and ¡a ¡recovery ¡trench; ¡ 2. Situated ¡immediately ¡upgradient ¡of ¡the ¡PAB; ¡ 3. Cement-­‑bentonite ¡(CB) ¡slurry ¡wall ¡sec5ons; ¡ ¡ 4. Sumps ¡ to ¡ recover ¡ and ¡ prevent ¡ LNAPL ¡ from ¡ accumula5ng ¡ at ¡ the ¡ upgradient ¡ faces ¡of ¡both ¡wall ¡sec5ons. ¡

  • Design: ¡

– Based ¡on ¡nature ¡and ¡es5mated ¡quan55es ¡of ¡LNAPL ¡ ¡ – Three ¡key ¡issues ¡: ¡ ¡

  • 1. ¡Preven5ng ¡migra5on ¡of ¡the ¡LNAPL ¡through ¡the ¡PAB ¡wall; ¡ ¡
  • 2. ¡Clogging ¡of ¡the ¡PAB ¡wall ¡by ¡LNAPL; ¡and, ¡
  • 3. ¡Preven5ng ¡migra5on ¡of ¡dissolved ¡COCs ¡through ¡the ¡PAB ¡wall. ¡ ¡
slide-19
SLIDE 19

19

Layout

slide-20
SLIDE 20

20

Cement-bentonite Barrier

  • Two ¡cement-­‑bentonite ¡barriers ¡were ¡built ¡in ¡order ¡to ¡drive ¡groundwater ¡flow ¡

to ¡the ¡Drainage ¡Barriers ¡to ¡the ¡Adsorp5ve ¡Permeable ¡Sec5on; ¡

  • First ¡ barrier: ¡ 68 ¡ meters ¡ in ¡ length, ¡ depth ¡ of ¡ 4 ¡ meters ¡ and ¡ average ¡ width ¡ of ¡

0.70 ¡meters; ¡

  • Second ¡barrier: ¡25 ¡meters ¡long, ¡depth ¡of ¡4 ¡meters ¡and ¡0.70 ¡meters ¡width; ¡
  • Preven5ng ¡that ¡the ¡supernatant ¡free ¡phase ¡contact ¡the ¡Tributary ¡of ¡Oropó ¡
  • Stream. ¡
slide-21
SLIDE 21

21

Cement-bentonite Barrier

slide-22
SLIDE 22

22

Gravel Trench

Draining ¡Barrier ¡

  • The ¡Draining ¡Barrier ¡was ¡built ¡about ¡30 ¡meters, ¡average ¡width ¡of ¡0.80 ¡meters ¡

and ¡depth ¡of ¡2.70 ¡meters; ¡

  • ¡Lined ¡with ¡geotex5le ¡(Bidim) ¡and ¡filled ¡with ¡graded ¡gravel ¡(#2); ¡
  • Two ¡wells ¡to ¡extract ¡product ¡(with ¡skimmers); ¡
  • To ¡ focus ¡ the ¡ groundwater ¡ flow ¡ (and ¡ free ¡ phase ¡ product), ¡ direct ¡ it ¡ to ¡ the ¡

collec5on ¡wells. ¡

slide-23
SLIDE 23

23

Gravel Trench

slide-24
SLIDE 24

24

Permeable Adsorptive Barrier (PAB)

Filtering ¡Barrier ¡or ¡Permeable ¡Adsorp5ve ¡Barrier ¡(PAB) ¡ Excavated ¡with ¡dimensions ¡of ¡4.6x3.50 ¡meters ¡with ¡depth ¡of ¡4 ¡meters, ¡forming ¡ a ¡filter ¡box, ¡"enveloped" ¡by ¡a ¡permeable ¡geosynthe5c.

slide-25
SLIDE 25

25

Barriers Section

slide-26
SLIDE 26

26 Presentation Title

Conclusions

slide-27
SLIDE 27

27

Conclusions

  • The system has collected more than 10,000 liters of product.
  • Less O&M
  • Energy consumption
  • Carbon footprint,
  • Innovation in Brazil
  • Favorizing operation by local resources
slide-28
SLIDE 28

Thanks