Airly Mine Airly Mine Community Consultative Committee (CCC) Presentation Airly Mine 5 th September 2017 www.centennialcoal.com.au 1. Introduction Reporting Period: May - Sep 2017 Site Name/Location: Airly Mine, Capertee, NSW Summary of


slide-1
SLIDE 1

www.centennialcoal.com.au

Airly Mine

Airly Mine

Community Consultative Committee (CCC) Presentation Airly Mine 5th September 2017

slide-2
SLIDE 2
  • 1. Introduction

Reporting Period: May - Sep 2017 Site Name/Location: Airly Mine, Capertee, NSW Summary of Consents and Licences: Airly Mine Contact Details:

2

Any Change? SSD_5581 No ML1331 No EPL12374 No A232 No EPBC 2013/7606 Approval granted on 18 May 2017 Position Key Contact Contact Details Mine Manager Bob Miller (02) 6359 2101 Email: bob.miller@centennialcoal.com.au Environment and Community Coordinator Sam Price Office: (02) 6359 2108 Mobile: 0427 647 657 Email: sam.price@centennialcoal.com.au

slide-3
SLIDE 3
  • 2. Operations Summary

Material Approved Limit (and source) This Reporting Period since previous CCC (May – Aug 2017) Year to Date Annual Forecast Waste Rock/ Overburden

N/A N/A N/A N/A

ROM Coal

1.8MT/annum 259kt 522kt 850kt

Reject

N/A N/A N/A N/A

Saleable Product

N/A 190kt 263kt 850kt

Railing

224kt 464kt 840kt

3

slide-4
SLIDE 4

4

Current & Projected Workings

slide-5
SLIDE 5

5

Current & Projected Workings

slide-6
SLIDE 6

Overview of Operations 2017 YTD

  • Nil environmental “non compliances” recorded
  • Production and productivity levels exceeded both budget and

forecast

  • Successful trial of gate road ‘single unit’ development completed at

increased depth under Airly Mesa

  • ‘Super unit’ development extended into shallow workings on

western fringe of Genowlan Mesa

  • Permanent employment numbers increased from 78 to 82 persons
  • Continued to supply domestic customers (Eraring and Delta) and

export customers through Port Waratah Coal Services.

  • Undertook major upgrade of underground ventilation infrastructure
  • Commitment resources to continuous miner rebuild program,

underground ventilation and conveyor upgrade

  • Developed environmental management plans under SSD_5581

6

slide-7
SLIDE 7

Projections for 2017 Operating Context

  • Maintain bord and pillar first working operations

employing ‘super unit’ methods in 206 Panel and 207 Panel under Genowlan Mesa

  • Undertake gate road development program under Airly

Mesa employing “single unit” methods.

  • Gain regulatory approval for conditions contained in the

consent granted for the Airly Extension Project..

  • Finalise feasibility report for Phase 2 Mining including:
  • Option study on equipment selection near finalisation
  • Capital project funding documentation prepared
  • Rebuild program commenced for continuous miners

7

slide-8
SLIDE 8
  • 3. Environmental Performance

8

slide-9
SLIDE 9

Airly Mine – Noise Monitoring

  • Airly Mine has no specific noise monitoring requirements or noise criteria in either

the Project Approval (DA 162/91) or EPL12374.

  • Airly Mine is currently preparing a Noise Management Plan (NMP) in accordance

with SSD_5581.

  • 2017 noise monitoring is scheduled for October.

9

Airly Mine Adopted Noise Monitoring Criteria Location Day/Evening/Night Criteria. LAeq, 15minute Night Criteria. LA1,1minute Location A N/A N/A Location B 35 45 Location C N/A N/A Location D N/A N/A Location E N/A N/A Location F N/A N/A

slide-10
SLIDE 10

Airly Mine – Noise Monitoring Results

Location Compliant? Location A IA <30 IA N/A Yes Location B IA IA IA 35 Yes Location C <30 35 <20 N/A Yes Location D IA IA IA N/A Yes Location E IA <25 IA N/A Yes Location F IA <30 <30 N/A Yes

10

  • LAeq,15minute noise monitoring was conducted at Airly Mine on 13th & 14th

November 2016 for locations A, B and D; and on 20th and 21st November 2016 for locations C, E and F.

IA = Inaudible

slide-11
SLIDE 11

Airly Mine – Air Quality Monitoring Results

11

Location Air Quality (g/m2/month) Dust Deposition Gauge Results

Jan 2017 Feb 2017 Mar 2017 Apr 2017 May 2017 Jun 2017 Jul 2017 Aug 2017

DM1

0.8 0.4 2.4 0.6 0.4 0.8 0.1 0.3

DM2

1 4.2* 0.6 0.3 0.2 0.1 0.2 0.3

DM3

0.4 1.2 0.7 2.6 0.7 0.3 0.5 0.3

DM4

2.2 1.5 0.5 0.3 0.3 0.1 0.2 0.2

Non-compliance Compliance

  • *Sample contaminated by external factors such as bird droppings.
  • Airly Mine has four depositional dust gauges located across site. These gauges are

monitored monthly for compliance.

  • Depositional dust monitoring results for YTD 2017 are provided below.
slide-12
SLIDE 12

Airly Mine – Air Quality Monitoring Results

12

slide-13
SLIDE 13

Airly Mine - Meteorological Monitoring

13

Month Total Rainfall (mm) Minimum Temperature (

  • C)

Maximum Temperature (

  • C)

January – 2017 37.4 11.7 38.3 February – 2017 20.8 5.4 41.4 March – 2017 130.6 8 30 April – 2017 21.8 1.6 22.3 May – 2017 28.4

  • 3.7

19.7 June – 2017 16.6

  • 2.4

16.8 July – 2017 8

  • 5.5

20.7 August – 2017 Month not complete at the time of the report.

slide-14
SLIDE 14

Airly Mine - Meteorological Monitoring

14

slide-15
SLIDE 15

Airly Mine – Water Monitoring Results

15

Discharge water quality

pH Total Suspended Solids (mg/L) Electrical Conductivity (μS/cm) Oil & Grease (mg/L)

January 2015 – August 2017 LDP1 No discharge LDP2 No discharge LDP3 No discharge Non-compliance Compliance

slide-16
SLIDE 16

Airly Mine – Subsidence Monitoring

  • The subsidence monitoring line over the 121 Panel was

installed during February 2017.

  • Pillar monitoring in 121 Panel under the subsidence line

was also during February 2017

  • Extraction in this area will be later in 2017
  • Quotes are being sourced for photogrammetry survey

16

slide-17
SLIDE 17

Subsidence Monitoring Line

17

slide-18
SLIDE 18

2016 Groundwater Monitoring Bores

18

Monitoring Location Monitoring Type Final Depth Completion Date

ARP11 Lithgow Seam water level & quality 15.29m 13/10/16 ARP12 Grotto surface/ alluvial water level & quality 2.6m 13/10/16 ARP13 Shoalhaven Group (120m bgl) & Devonian strata (280m bgl) water level & quality 310m 9/12/16 ARP13 SP Lithgow Seam water level & quality 80m 25/11/16 ARP14 Oasis surface/ alluvial water level & quality 2.29m 13/10/16 ARP15 Lithgow Seam (125m bgl), Shoalhaven Group (200m bgl), Devonian strata (365m bgl) water level & quality 375m 12/1/17 ARP15 SP Narrabeen sandstone water level & quality 22.2m 17/1/2017

slide-19
SLIDE 19

Airly Mine – Groundwater Monitoring Locations

19

slide-20
SLIDE 20
  • 4. Environmental Management

20

slide-21
SLIDE 21

Airly Mine – Cultural Heritage

21

Historically: Five (5) sites have been undermined: 45-1-2746 (Artefact Scatter) - Dec 2010 45-1-2763 (Artefact Scatter) – Mar 2011 45-1-2761 (Shelter) – Jul 2011 45-1-2762 (Artefact Scatter) – Sep 2015 45-1-2748 (Isolated Find) – May 2017

  • No mining related disturbance to any site.

Previous 6 Months: One site (45-1-2748) was undermined; monitoring inspections were carried out as per the ACHMP Upcoming 6 Months: Nil Low level subsidence and tilt as a result of mining, does not pose a risk of harm to these sites Fencing activities completed to help mitigate against potential harm

slide-22
SLIDE 22

Airly Mine – Cultural Heritage

22

  • A pre-mining inspection of site 45-

1-2748 was completed on 28 March 2017.

  • No mining induced impacts to

the site were evident during the pre-mining inspection

  • A post-mining inspection of site 45-

1-2748 was carried out on 17 August 2017.

  • No mining related disturbance

were evident during the

  • inspection. All RAPs were

satisfied with the condition of the site.

slide-23
SLIDE 23

Airly Mine – Rehabilitation & Land Management

  • Airly Mine does not currently have any land available or subject to rehabilitation
  • works. This is not likely to change until mine closure.
  • Updated rehabilitation cost estimate was sent to DRE on 31 March 2017.
  • A revised MOP/RMP has been developed and has been submitted for consultation

and approval.

  • Spring/Summer 2017-18 weed spraying program will recommence in October.
  • Surrounding Mine owned land continues to be leased out for agricultural purposes.
  • Riparian restoration of Airly Creek on-going. Tube stock scheduled for Spring.
  • Tree screen maintenance conducted as required.

23

slide-24
SLIDE 24

Airly Mine – Flora, Fauna & Aquatic Ecology Monitoring

24

  • Flora and fauna monitoring activities are

conducted by RPS in spring and summer.

  • Aquatic ecology monitoring activities were

conducted in May 2017. And are scheduled again for October 2017.

  • Stygofauna monitoring was conducted in

August 2017. No stygofauna present.

Glossy-black Cockatoos Leaf-tailed Gecko

slide-25
SLIDE 25
  • 5. Summary of Incidents / Non-compliances

(CCC Period: Feb - Apr 2017)

Were all conditions of the relevant approval(s) complied with?

DA162/91 YES ML1331 YES EPL12374 YES A232 YES

25

Statement of Compliance:

Relevant Approval Condition # Condition summary Compliance Status Comment / Description Nil

Non-compliance Summary: Incident Summary:

Nature of Incident Detail of Incident Detail of Mitigation / Remediation

Nil

slide-26
SLIDE 26
  • 6. Community Engagement
  • Airly Mine representatives attended and provided updates at the Capertee Valley

Progress Association (CVPA) Monthly Meetings;

  • Airly Mine manned the BBQ again for the Train Day Market on Sunday 21 May

2017.

26

Sponsorship/Donations:

  • Kandos/Rylstone Show;
  • Rylstone Street Feast;
  • Capertee Public School;
  • Capertee Hall.
  • Cudgegong Country Ball
  • Rylstone Rural Fire Brigade
slide-27
SLIDE 27
  • 7. Community Complaints
  • One community complaint was received on 10 March 2017 in relation to vibration.
  • Airly Mine Community Complaints Register is publically available on the Centennial

Coal website.

27

Community Complaints Register 2017.

Jan

  • 17

Feb

  • 17

Mar

  • 17

Apr

  • 17

May

  • 17

Jun

  • 17

Jul- 17 Aug

  • 17

Sep

  • 17

Oct

  • 17

Nov

  • 17

Dec

  • 17

Jan

  • 18

Total

Air Water Noise Other

1

Subsidence Waste Visual 1

slide-28
SLIDE 28
  • 8. Activities proposed for the Next Period

 Environment

  • Scheduled monitoring and reporting

 Systems

  • Continue to prepare environmental management plans.
  • Implementation of compliance database.

 Water

  • Routine monitoring and reporting

 Rehabilitation and Mine Closure

  • Nil

 Biodiversity

  • Routine monitoring and reporting

 Approvals

  • Awaiting approval of submitted environmental management plans as

required under SSD_5581

  • Submit Extraction Plan for First Workings in the Cliff Zone

28

slide-29
SLIDE 29

AIRLY MINE

THANK YOU