Beechworth Sewer Project Update Presented by Misty Howard 7 - - PowerPoint PPT Presentation

beechworth sewer project update
SMART_READER_LITE
LIVE PREVIEW

Beechworth Sewer Project Update Presented by Misty Howard 7 - - PowerPoint PPT Presentation

Beechworth Sewer Project Update Presented by Misty Howard 7 October 2019 Agenda for tonights meeting Introductions Recap of the problem being solved New sewer main (pipeline) recap and where we are up to Final al align


slide-1
SLIDE 1

Beechworth Sewer Project Update

Presented by Misty Howard 7 October 2019

slide-2
SLIDE 2

Agenda for tonight’s meeting

  • Introductions
  • Recap of the problem being solved
  • New sewer main (pipeline) – recap and where we are up to
  • Final

al align gnment in detai ail

  • Questions
  • Wastewater Treatment Plant Upgrade
  • Next Steps
  • Questions

2

slide-3
SLIDE 3

Beechworth Sewer Project Background

  • The

The Problem? Infiltration results in sewer overflow and spill into Beechworth Historic Park.

  • Wh

What are we doing? g? Increasing capacity of the sewer system to address environmental risks and provide for growth of the town.

  • How?

w? › Increasing the size of the sewer main (pipeline) that transfers sewage to the WWTP; and › Upgrading the WWTP to treat the increased flows and load.

3

slide-4
SLIDE 4

Pipeline

slide-5
SLIDE 5

Pipeline background

  • Beechworth’s sewer main runs through the Historic

Park (constructed 1967)

  • Heavy rain events in 2016 led to a number of sewer

spills at the Church Street inlet

  • EPA issued a Pollution Abatement Notice to North

East Water, requiring capital works solution

  • Two preliminary options were identified – a large tank

at top of the Park or a new, larger pipeline

  • North East Water commenced discussions with

stakeholders in late 2016

5

slide-6
SLIDE 6

The Stakeholder Process

6

DELWP

NEW

Parks Vic

EPA

Beechw hworth h Communit ity

IEAC Indigo Council ACTIO TION

DELW LWP: Department of Environment, Land, Water & Planning EPA PA: Environment Protection Authority IEAC AC: Indigo Environment Advisory Committee

Cons nsul ult Inform rm Ad Advise se

slide-7
SLIDE 7

Our engagement journey

7

Nov 2016 4 April 2017

1st

st Comm

mmunity Meet eeting:

  • Community values

identified

  • 2 prelim options
  • T

ank least preferred 2nd

nd Communit

ity M y Meetin ing:

  • Community values

workshopped

  • 3 pipeline options

20 April 2017

3rd

rd Community M

y Meet eeting:

  • Review criteria &

weightings for MCA

  • Met with IEAC

Door K

  • r Knoc
  • ck – Old

d Chilt iltern R Rd:

  • Update residents
  • Clarify

miscommunications

Sept 2017

4th

th Communit

ity M y Meetin ing:

  • Results of MCA
  • Old Chiltern Rd

preferred option

  • Flora & fauna

presentation by Biosis

Oct 2017 March 2018

Old ld C Chil iltern Rd Rd Walk T Thru:

  • Walked the proposed

alignment with residents

  • Construction methods

discussed

September 2019

Regular email updates as project progressed Detailed design complete & ready to present to community

Oct/Nov 2019

Submit Planning Permit application to Council

slide-8
SLIDE 8

Options presented to community

8

OPT PTIO ION DESCRIPTIO ION MULTI-CRITERIA ASSE SSESSM SSMENT RANK NKING ING

Malakoff Road & Historic Park

  • New gravity-fed pipeline
  • Additional pump stations
  • Built mainly along Malakoff Rd
  • Route partially through Park

2

Old Chi hiltern Ro Road

  • New

ew p pip ipel elin ine

  • Thro

rough town n and nd O Old Chi hiltern Rd Rd

  • Ro

Rout ute i is s along f fring nge of the he Park

  • New p

pump ump st station r requi uired

1 1

Historic Park

  • New gravity-fed pipeline
  • No additional pump stations

3

T ank at Church Street

  • New tank (3.5 million litre capacity)
  • Below existing site in Church St
  • In Historic Park

4

slide-9
SLIDE 9

Final Alignment

9

slide-10
SLIDE 10

What have we done since we last met?

Since March 2018, we have:

  • Consulted with regulatory stakeholders – Indigo Shire Council, DELWP

, Parks Vic, EPA

  • Completed preliminary designs
  • Gained Board endorsement for final alignment
  • Engaged external consultant to provide detailed design of pump station and pipeline
  • Internal review of detailed design
  • Commenced discussions with WWTP neighbours

10 10

slide-11
SLIDE 11

Detailed Design

  • Difficulties overlaying an aerial photograph on to a flat map – pipeline alignment on crown land not

not private property

  • Churc

rch Stre reet – new pump station within existing site, open trench

  • Last Street – open trench and backfill along road reserve
  • Sydne

dney y Road – under bore

  • Old Chilt

ltern n Road: › Under bore › Follow utilities corridor and power lines

  • Pine Trac

ack: › Under bore › Follow Parks Vic Management track › Avoid sharp bends

11 11

slide-12
SLIDE 12

Next Steps

  • Liaise with approval authorities (EPA, DELWP

, Parks Vic, Council)

  • Submit Planning Permit to Council
  • Construction of Church St pump station February

2020

  • Commence pipeline construction mid 2020
  • Continue to inform the community and residents as

project progresses

12 12

slide-13
SLIDE 13

Questions?

13 13

slide-14
SLIDE 14

Wastewater Treatment Plant Upgrade

slide-15
SLIDE 15

Background

  • Built in 1960s
  • Located on McFeeters Road, 3.5km north-

west of Beechworth

  • Consists of 3-step treatment process:

– primary anaerobic treatment lagoon – series of secondary lagoons – Final polishing prior to discharge

15 15

slide-16
SLIDE 16

Purpose of Upgrade

  • Increase capacity:

– Additional flows due to new sewer main capturing stormwater infiltration – Accommodate town growth

  • Reduce risk of odours
  • Minimise noise
  • Maximise effluent reuse

16 16

slide-17
SLIDE 17

Upgrade design process

  • Design addresses environmental and growth needs of community
  • Informed by regular meetings and discussions with neighbours for past 12 months
  • 2 independent consultant peer reviews of design
  • Will include:

– New inlet structure – New treatment process – new lagoons and aerators – Wet weather buffering

17 17

slide-18
SLIDE 18

18 18

slide-19
SLIDE 19

Next Steps

  • Consultant has been engaged to develop a preliminary design
  • EPA Works Approval application November 2019
  • Upgrades expected to commence in 2020
  • Will continue to meet with neighbours on-site

19 19

slide-20
SLIDE 20

Questions

20 20