BULK and CLUSTERED METERS 17 September 2014 City of Mandaluyong - - PowerPoint PPT Presentation

Presentation on BULK and CLUSTERED METERS 17 September 2014 City of Mandaluyong Outline of Presentation Objectives Different Types of Metering Scheme Issues Related to Bulk and Clustered Metered Problems Encountered Hindering


slide-1
SLIDE 1

Presentation

  • n

BULK and CLUSTERED METERS

17 September 2014 City of Mandaluyong

slide-2
SLIDE 2

Outline of Presentation

  • Objectives

Metropolitan Waterworks and Sewerage Systems

Regulatory Office

  • Problems Encountered Hindering Individualization
  • Procedures / Process for Application of Water Service

Connections

  • Measures Undertaken
  • Issues and Concern Agency
  • Different Types of Metering Scheme
  • Issues Related to Bulk and Clustered Metered
  • Disadvantages of Bulk Meter Scheme
slide-3
SLIDE 3

Objectives

  • Convert Bulk Meter to Individual Connections
  • Raise the level of awareness of customers under

Bulk metering, educate customers and solicit feedback

  • To come up with appropriate policies and

guidelines for communities covered by Bulk Meter arrangements or enhance existing Implementing Rules and Regulations

Metropolitan Waterworks and Sewerage Systems

Regulatory Office

slide-4
SLIDE 4

Individual Meter

Metropolitan Waterworks and Sewerage Systems

Regulatory Office

slide-5
SLIDE 5

Clustered Meters

* Applies for Depressed Area

Metropolitan Waterworks and Sewerage Systems

Regulatory Office

slide-6
SLIDE 6

Bulk Meters

Metropolitan Waterworks and Sewerage Systems

Regulatory Office

slide-7
SLIDE 7

Public Faucets

Metropolitan Waterworks and Sewerage Systems

Regulatory Office

slide-8
SLIDE 8

Issues Related to Bulk and Clustered Meters

Spaghetti Connections

Metropolitan Waterworks and Sewerage Systems

Regulatory Office

slide-9
SLIDE 9

Issues Related to Bulk and Clustered Meters

Unsanitary Pipe Installation

Metropolitan Waterworks and Sewerage Systems

Regulatory Office

slide-10
SLIDE 10

Problems Encountered Hindering Individualization

  • Land Disputes (Ownership)
  • Right-of-Way
  • Decision of Homeowners / Community /

Water Operator

Metropolitan Waterworks and Sewerage Systems

Regulatory Office

slide-11
SLIDE 11

Disadvantages of Bulk MeterScheme

  • Unregulated Tariff Rate of Private Operator
  • Residents share in the Overhead Expenses and

Maintenance Cost

  • Residents pay for the Non-Revenue Water
  • All Residents, including those who are updated in

their payments, suffer the consequences of disconnection, if the People’s Organization or

  • perator fails to pay the bill

Metropolitan Waterworks and Sewerage Systems

Regulatory Office

slide-12
SLIDE 12

Measures Undertaken

IRR No. 2008-06 Implementing Rules and Regulations for Additional Meter and Clustered Connection Charges for Open/Depressed Communities

Metropolitan Waterworks and Sewerage Systems

Regulatory Office

slide-13
SLIDE 13

IRR No. 2008-06 The service connection charge shall be based

  • n a 1/3:2/3 cost sharing scheme whereby

1/3 shall be borne by the consumers and 2/3 shall be borne by the concessionaires

Measures Undertaken

*Applies only for Clustered Metered in a Depressed Area

Metropolitan Waterworks and Sewerage Systems

Regulatory Office

slide-14
SLIDE 14

CSR 001-05 Policy Guideline on Providing Water Services to Customers in Open Communities and Depressed Areas

Measures Undertaken

Metropolitan Waterworks and Sewerage Systems

Regulatory Office

slide-15
SLIDE 15

CSR 001-05 Billing Computation – the official meter shall be billed at the Average Residential Rate (AVERES) of the consumption block.

Measures Undertaken

*Applies only for Bulk Meter

Metropolitan Waterworks and Sewerage Systems

Regulatory Office

slide-16
SLIDE 16

Click to edit Master title style

Metropolitan Waterworks and Sewerage Systems

Regulatory Office

IMPACT ON WATER BILL

Manila Water Company, Inc. Billing Scheme: Average Residential (for 100% Residential Occupancy) Given: Actual Consumption of Master Meter (ACM) = 281 m3 Number of Active Units (NAU) = 17 Actual Average Consumption (ACM/NAU) = 16.53 m3/active unit Bill Computation: Based on the 2010 Residential Rates Basic Charge for 16.53 m3 1st 10 m3 (10 m3) = 81.74 (Per Active Unit) Next 10 m3 (6.53 m3 * 9.97) = 65.10 Total = 146.84 Total Basic Charge for Master Meter (TBC)

=

Basic Charge for 16.53 x NAU

=

146.84 x 17 = 2,496.28 Other charges:

FCDA

= 1.58% of TBC = 39.44 EC = 16% of (TBC + FCDA) = 405.72 MSC = meter size 50 mm = 1.50 VAT = 12% of All Charges = 353.15 TOTAL = Charge for 281 m3 = 3,296.09 Cost / m3 = 11.73

slide-17
SLIDE 17

Click to edit Master title style

Metropolitan Waterworks and Sewerage Systems

Regulatory Office Total Number of Active Units : 17 Master Meter Consumption : 281 m3 Actual Average Consumption : 281 m3 / 17 = 16.53 m3 Old Scheme Based on CSR 001-05 Rate Class / Billing Scheme Residential/ Master Meter cons Average Residential Total Cost P 10,956.10 P 3,296.09 Cost / m3 P 38.99 P 11.73 % Reduction = 70%

IMPACT ON WATER BILL

slide-18
SLIDE 18

Lifeline Discount (Residential and Depressed Area)

Low-Income Household Consuming 10 cu.m. or less P 60.61/connection P 101.01/connection Not within the Low-Income Household Consuming 10 cu.m. or less

Measures Undertaken

Metropolitan Waterworks and Sewerage Systems

Regulatory Office

slide-19
SLIDE 19

Customers Eligible for a Lifeline Discount

Measures Undertaken

Metropolitan Waterworks and Sewerage Systems

Regulatory Office

  • Low-Income Domestic Accounts / Customers

Requirements:

  • Tax Exemption Certificate from the BIR
  • Any Government-issued Certification
slide-20
SLIDE 20

Procedures for Application of Water Service Connections

Metropolitan Waterworks and Sewerage Systems

Regulatory Office

slide-21
SLIDE 21

Procedures:

Applicant Bulk Meter Land or Right of Way Issue? NO Clustered Metered Submit Requirements

Open Community

Approved MOA / Application Depressed Area Individual Connections YES YES NO YES

Metropolitan Waterworks and Sewerage Systems

Regulatory Office

slide-22
SLIDE 22

Issues and Concern Agency

  • High Tariff - NWRB
  • Land Ownerships - LGU
  • Executive Order 465 - NHA
  • Cooperative Problems - CDA

Metropolitan Waterworks and Sewerage Systems

Regulatory Office

slide-23
SLIDE 23

End of Presentation

Metropolitan Waterworks and Sewerage Systems

Regulatory Office

slide-24
SLIDE 24

Executive Order 465

FURTHER AMENDING EXECUTIVE ORDER 70 DATED FEBRUARY 11, 2002 AS AMENDED BY EXECUTIVE ORDER 216 DATED JUNE 9, 2003 ENTITLED “DECLARING PORTIONS OF THE PROPERTY OF THE BASES CONVERSION AND DEVELOPMENT AUTHORITY LOCATED IN FORT BONIFACIO AND ITS ENVIRONS AS SOCIALIZED HOUSING SITES AND PROVIDING FOR THE DISPOSITION THEREOF TO QUALIFIED OCCUPANTS AND BENEFICIARIES”, CLARIFYING THE TRANSFER OF OWNERSHIP; AND ADMINISTRATION, AND DEFINING THE DUTIES AND ROLES OF THE IMPLEMENTING AGENCIES