Certain information contained in this presentation constitutes - - PowerPoint PPT Presentation
Certain information contained in this presentation constitutes - - PowerPoint PPT Presentation
Certain information contained in this presentation constitutes forward looking information. This information may relate to future events or the Companys future performance. All information other than information of historical fact is forward
Certain information contained in this presentation constitutes forward looking information. This information may relate to future events or the Company’s future performance. All information other than information of historical fact is forward looking information. The use of any of the words “anticipate”, “plan”, “continue”, “estimate”, “expect”, “may”, “will”, “project”, “should”, “believe”, “predict” and “potential” and similar expressions are intended to identify forward looking information. This information involves known and unknown risks, uncertainties and other factors that may cause actual results or events to differ materially from those anticipated in such forward looking information. No assurance can be given that this information will prove to be correct and such forward looking information included in this presentation should not be unduly relied upon. This information speaks only as of the date of this presentation. Such forward looking statements include, among other things, statements or information relating to: the Company’s New Liberty gold project in Liberia (the “New Liberty Gold Project”)(including the quantity and quality of mineral resource and mineral reserve estimates), the potential to upgrade inferred mineral resources, opportunities to optimize the New Liberty Gold Project, the ability of the Company to develop the New Liberty Gold Project into a mine and the proposed plans relating thereto regarding operations and mine design, estimates relating to tonnage, grades, waste ratios, recovery rates and future gold production, life-of-mine estimates, assay results, gravity concentration test results, expectations regarding throughput gold production, mill treatment and plant feed, estimates of capital and operating costs and start-up costs, anticipated sources of funding, expectations regarding staffing requirements and the engagement of external contractors, estimates of revenues and pay-back periods, estimates of net present values and internal rates of return, expectations regarding operating parameters, plans regarding
- ptimization work (including the timing thereof), construction activities, power supply and infrastructure development, plans regarding relocations, community development and water management, transportation
methods, plans regarding the diversion of the Marvoe Creek, the proposed budget for the work program at the New Liberty Gold Project, asset retirement obligations and decommissioning requirements, plans for further exploration work, including drilling and metallurgical test work, expectations regarding the potential direct and indirect environmental and socio-economic impacts of the New Liberty Project, as well as the other forecasts, estimates and expectations relating to the New Liberty Gold Project included in this presentation; the future market price of commodities; strategic plans; production targets; timetables; the continued listing of the common shares of the Company on the Toronto Stock Exchange (the “TSX”) and the AIM market operated by the London Stock Exchange (“AIM”); financing plans and alternatives; proposed plans and exploration activities on the Company’s other target areas (including the proximal targets of Weaju, Ndablama, Leopard Rock, Gondoja, Yambesei, Archean West, Mabong and Mafa West) and the timing related thereto; and targets, goals, objectives and plans associated therewith; the Company’s expectation that all licences/permits will be able to be obtained, when required and the Company’s intentions regarding employee training. With respect to forward looking information contained in this presentation, assumptions have been made regarding, among other things: general business, economic and mining industry conditions; interest rates and foreign exchange rates; mineral resource and reserve estimates; geological and metallurgical assumptions (including with respect to the size, grade and recoverability of mineral resources and reserves) and cost estimates on which the mineral resource and reserve estimates are based; the parameters and assumptions employed in the technical report dated July 3, 2013 and entitled “New Liberty Gold Project, Liberia, West Africa, Updated Technical Report” (the “New Liberty Technical Report”), (including but not limited to, those relating to construction, future mining and operating costs, processing and recovery rates, net present values and internal rates of return, timing for the commencement of production, tax and royalty rates, future gold prices, metallurgical rates, pit design, operations and management, grades, the base case analysis and the proposed budget for further exploration plans and objectives); the supply and demand for commodities and precious and base metals and the level and volatility of the prices of gold; market competition; the ability of the Company to raise sufficient funds from capital markets and/or debt to meet its future obligations and planned activities; the business of the Company including the continued exploration of its properties; the political environments and legal and regulatory frameworks in Liberia and Cameroon with respect to, among other things, the ability of the Company to obtain, maintain, renew and/or extend required permits, licences, authorizations and/or approvals from the appropriate regulatory authorities and the ability of the Company to continue to obtain qualified staff and equipment in a timely and cost-efficient manner to meet its demand. Actual results could differ materially from those anticipated in the forward looking information contained in this presentation as a result of the risk factors, including: risks normally incidental to exploration and development of mineral properties; the inability of the Company to obtain required financing when needs and/or on acceptable terms or at all; risks related to operating in West Africa; health risks associated with the mining workforce in West Africa; risks related to the Company’s title to its mineral properties; adverse changes in commodity prices; risks related to current global financial conditions; risks that the Company’s exploration for and development of mineral deposits may not be successful; risks normally incidental to exploration and development of mineral properties; the inability of the Company to obtain, maintain, renew and/or extend required licences, permits, authorizations and/or approvals from the appropriate regulatory authorities and other risks relating to the legal and regulatory frameworks in Liberia and Cameroon, including adverse changes in applicable laws; competitive conditions in the mineral exploration and mining industry; risks related to obtaining insurance or adequate levels of insurance for the Company’s operations; uncertainty of mineral resource and reserve estimates; the inability of the Company to delineate additional mineral resources; risks related to environmental regulations; uncertainties in the interpretation of results from drilling; uncertainties in the estimates and assumptions used, and risks in the methodologies employed, in the New Liberty Technical Report and that the completion of additional work at the New Liberty Gold Project could result in changes to the forecasts, estimates and expectations contained in the New Liberty Technical Report; risks related to the legal systems in Liberia and Cameroon; risks related to the tax residency of the Company; the possibility that future exploration, development or mining results will not be consistent with expectations; delays in construction; inflation; changes in exchange and interest rates; risks related to the activities of artisanal miners; actions of third parties that the Company is reliant upon; lack of availability at a reasonable cost or at all, of plants, equipment or labour; the inability to attract and retain key management and personnel; political risks; the inability to enforce judgments against the Company’s directors and officers; and future unforeseen liabilities and other factors. Information relating to “resources” and “reserves” is deemed to be forward looking information as it involves the implied assessment based on certain estimates and assumptions that the resource and reserves can be profitable in the future. Such estimates are expressions of judgment based on knowledge, mining experience, analysis of drilling results and industry practices. Valid estimates made at a given time may significantly change when new information becomes available. By their nature, mineral resource and reserve estimates are imprecise and depend, to a certain extent, upon statistical inferences which may ultimately prove unreliable. If such mineral resource estimates are inaccurate or are reduced in the future, this could have a material adverse impact on the Company. Accordingly, investors should not place undue reliance on forward looking information. Mineral resources that are not mineral reserves do not have demonstrated economic viability. Due to the uncertainty that may be attached to inferred mineral resources, it cannot be assumed that all or any part of an inferred mineral resource will be upgraded to an indicated or measured mineral resource as a result of continued exploration. The forward looking information included in this presentation is expressly qualified by this cautionary statement and is made as of the date of this presentation. The Company does not undertake any obligation to publicly update or revise any forward looking information except as required by applicable securities laws.
New Liberty, rty, Liberia ria
- The most advanced gold mine under construction in West Africa – 1st gold pour due Q1
2015 High Grade Open Pit t Low
- w Cost
t Opera rati tion
- n
- High grade reserve of 8.5m tonnes at 3.4 g/t
- All in Sustaining Cash Costs US$850/oz
- Free cash (after debt repayment) of US$206m at US$1,250/oz gold
Fully ly Financ anced d Through ugh To Produc
- ducti
tion
- n and Beyon
yond
- Plant construction on track c. 60% complete
- Pre-strip mining commenced August 2014
- Poised for a developer to producer valuation re-rating
Signif ifica icant t Explora lorati tion Pote tenti tial al
- 1,470km2 exploration portfolio on major gold bearing structures
- Potential for a second project at Ndablama
Cataly alysts ts
- Q4 2014 – Ndablama upgraded resource estimate and PEA
- Q1 2015 – First gold pour at New Liberty
3
2000 4000 6000 8000 10000 12000 5 10 15 20 25 30 35 40 45 50 Sep13 Nov13 Jan14 Mar14 May14 Jul14 Sep14 Volume (000) Price (GBp) Daily Volume (RHS) Price (LHS)
4
Capit itali lisa satio ion n Summary ry at September ber 01, 2014
AIM / TSX Ticker AUE LN / CN Shares in Issue 310.6 Warrants 40.1 Options 15.0 Fully Diluted 350.7 Market Cap US$ 120million Balance Sheet at June 30, 2014 14 (in millions ns) Cash US$ 48.61 Debt US$ 54.0
1Does not include US$11m IFC investment completed in July 2014
Share re Price e – Last Twelve lve Months
Source: Bloomberg
Major r Shareho rehold lders ers
BlackRock 9.7% Baker Steel 5.6% IFC 7.9% Genesis 4.9% Blakeney 7.2% GCIC 3.9% Mackenzie 7.0% Macquarie 3.2% RBC AM 6.3% Investec 3.0% JP Morgan 5.7% Wells Capital 2.5%
- No reported or suspected cases of Ebola to date across our operations or in close
proximity to anywhere the Company operates
- Construction at New Liberty continues with key contractors and staff remaining on
site
- Established and implemented precautionary measures and contingency plans to
ensure the Company, its employees, contractors and visitors are not placed under unnecessary risks including;
5
– Enhanced security and access controls to our
- perations
– Daily temperature screening for all employees and contractors – Heightened medical provisions & assistance at the New Liberty medical clinic – Travel restrictions for employees and contractors – No non-essential staff or visitors on site – Education and collaboration with employees, local villages and village elders
6
New Liberty is the only gold mine under construction in West Africa
7
Tarmac Road from Monrovia to Sierra Leone New Laterite Road (20km) Ball Mill En Route To New Liberty Via Tarmac Road from Monrovia to Sierra Leone
8
- CapEx of US$152 million*
- First gold pour on track for March 2015
- 8 year mine life on current reserves
- Average annual production of c.120Koz
for first 6 years
- Plant throughput of 1.1 Mtpa
- Conventional Gravity & CIL processing
(93% Recovery)
- LOM production of 859Koz
- All in Sustaining Cash Cost of
US$850/oz**
*DFS capex of US$150 million, including US$14 million contingency plus US$2 million additional contingency post bank technical due diligence **World Gold Council definition
Classif ifica ication ion Tonnes es Gold (g/t /t) Gold (koz) Proven 700,000 4.4 99 Probable 7,800,000 3.3 825 Total Reser erve 8,500,00 ,000 3.4 924 924
LOM Production and Grade
0.5 1 1.5 2 2.5 3 3.5 4 4.5 20 40 60 80 100 120 140 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8
Production + Inferred (koz) Production (koz) - LHS Head Grade (g/t) - RHS Head Grade + Inferred (g/t)
Larjor
- r
Latif iff Kinjor Marvoe rvoe
Stage 3 Stage 2 Stage 1 Stage 4 Stage 5 Stage 6
9
E W
500m 0m
Pit Design gn Total Tonnes (Mt) 140 Ore Tonnes (Mt) 8.5 Waste Tonnes (Mt) 132 Ore Grade (g/t) 3.38 Strip Ratio 15.4 Contained Au (koz) 924 Recovered Au (koz) 859
10
- Aureus have partnered with MonuRent to engage in owner mining with a fleet rental
agreement
- MonuRent has purchased and will maintain a new mining fleet, matched to the mining
schedule
- Dozers, Excavators and ADTs are already operational and working on the top soil
removal and pre-strip mining
- Four 100 tonne dump trucks and one 120 tonne excavator are due for delivery to
site in early October
- MonuRent guarantees fleet availability at a minimum of 85%
- Mining cost of US$3.01 per tonne, priced on a detailed bottom up basis
MonuRent nt Excava vators
- rs Comm
mmenc ncing ng Top Soil Remov
- val
al and Pre-St Stri rip Mining
11
- Final mine schedule and mine plan due for completion in November 2014
- Currently assessing options for two concurrent starter pits
- Optimise haul profiles and ramp designs
- Maintain haul road surfaces to a high standard to focus on tyre life in wet conditions
- Improving equipment utilisation by practicing ‘hot seat changeover’ and 12 hour shifts
- Maximise productivity by matching truck allocation to shovels and minimising idle times
- Minimise equipment damage by using experienced operator trainers and supervisors
- Optimise drilling patterns and blast designs (fragmentation)
- Minimise ore dilution and avoid ore loss (RC Drilling in progress)
- Manage Drainage – using experienced dewatering crews
W E 2 Km
12
- 60% of EPCM mine build completed and on budget
Milestone Completion Date Status
Commenced Marvoe Creek Diversion Channel Excavations, Process Plant Bush Clearing, TSF Bush Clearing, RAP Village Bush Clearing. December 2012
Plant Earthworks Complete September 2013
First Concrete Pour October 2013
Bush Clearing Completed November 2013
Civil Works Commenced December 2013
Steel Work Erection Commenced, Store and Workshop Civil Work Commenced February 2014
Ball Mill Foundations Poured March 2014
CIL Tank Bases Completed April 2014
Upgrade Work on Daniels Town Road Completed May 2014
Steel Work Erection for Primary Crusher, Screening & Gold Room Commenced May 2014
Ball Mill Arrives at New Liberty June 2014
All families successfully relocated to New Kinjor Township August 2014
13
14 0% 0% 20% 20% 40% 40% 60% 60% 80% 80% 100% 100%
Process Plant Commissioning & First Gold Pour Ball Mill Fabrication & Transportation to Site Process Plant Steel Erection CIL Tank Bases and Erection Process Plant Civil Construction Camp David Accommodation Construction Upgrade Work on Daniels Town Road TSF Dam Wall Construction TSF Bush Clearing MCDC Dam 1 & 2 Construction MCDC Spillway Construction Project Earthworks
0% 0% 100% 100% 50% 50% 38% 38% 60% 60% 98% 98% 100% 100% 98% 98% 100% 100% 82% 82% 89% 89% 95% 95%
Comple letion ion
EPCM CM Contr ntract ct 60% Com
- mplete*
plete*
* As at August 20th 2014
Q2 2014
Ball Mill Arrives on Site Complete MCDC Dam Walls and Spillway
Q3 2014 2014
Complete TSF Dam Walls Commence Pre-Strip & Grade Control Drilling
Q1 2015
Start Open Pit Mining Operations Plant Commissioning First Gold Pour
Q2 2015
Ramp up process plant Achieve Steady State Production
15
Q4 2014
Complete Mill Installation Complete Plant Civil Construction Complete Kinjor Village Relocation
- Cash:
sh: – 30th June 2014 Balance Sheet of US$48.6 million1
- Fundin
ding: g: – US$15 million private placement closed in April 2014 – Drawn down US$60 million from US$100 million project debt facility – US$11 million IFC investment completed July2014
- Fully
ly funded nded beyond yond produ
- duct
ction: ion: – Approximately US$85 million expended on Project CapEx to date – Required equity spend on Project CapEx has been fully contributed – Debt facilities to fund all remaining Project CapEx – Existing cash and recent investment proceeds available for non-CapEx activities
1Does not include US$11m IFC investment completed in July 2014
16
Revenue venues - US$1.1 .1 billion lion
- Average 120,000 oz. p.a. for first 6 years for a total LoM of 859,000 oz at
US$1,250 per oz over 8 year LoM Low cash costs
- US$850/oz. all in sustaining cash costs*
Cash Flow
- Generates free cash over 8 year LoM after debt repayment and interest of;
– US$206 million @ US$1,250 / oz – US$300 million @ US$1,400 / oz
* World Gold Council definition 17
Ball Mill On Site At New Liberty rty
18
- All families have been successfully relocated to New Kinjor Township
- Old village site has been cleared allowing the pre-strip to commence
- The community is 100% involved the completion of the the New Kinjor Township housing
- 318 permanent houses, 265 temporary houses
- Houses and land will be owned by the local community
- Township includes a community centre, market, mosque, church, school buildings, police
station, water-wells and ablution facilities
- Hydraform brick making machines will be handed over to a community cooperative
RAP Village – New Housing ng Units
19 New Liberty M&I 9,796 1,143 3.6 1.0 New Liberty Inferred 5,730 593 3.2 1.0 Ndablama Inferred 6,829 451 2.1 0.5 Weaju Inferred 2,680 178 2.1 1.0
A B
E W
2km 2km 500 00m
20
Resou
- urc
rce:
- Measured: 651,
1,000t 00t at 4.8 8 g/t (for 100,000 ounces)1
- Indicated: 9,145,
145,000t 000t at 3.6 6 g/t (for 1,043,000
- unces)1
- Total M & I: 1.14
14 Moz at 3.63g 63g/t;
- Inferred: 5,730,
730,000 000t at 3.2 2 g/t (for 593,000 ounces)1
Note 1: Resource Cut off grade = 1.0 g/t, Reserve reported at a cut-off grade of 0.8g/t Au and ore grading between 0.8 & 1.0 g/t cut-off is stockpiled for processing towards the end of the mine life Note 2: A dilution skin of 0.5m added and minimum width of 2.5m applied Note 3: A gold price of US$ 1,300 was used for pit optimisation
21
¹
- Holes drilled to test the down
dip extension of the mineralised shoots have intersected good grades at depths of up to 500m
- Inferred resources below the
pit floor have the potential for being mined through underground methods
22
23
Magnetics RTP 1VD Radiometrics Total Count Yilgarn Block, Western Australia, Magnetics
Kanow
- wna
na Belle Kalgoorli
- rlie
Padding ngton
- n
Lady Bount ntiful Kundana ana East st Banduli Broad ad Arrow
- w
24
¹ ¹
- Soil geochemistry, radiometrics and
geophysics defines 13km gold corridor
- Reconnaissance drilling and trenching
confirms in-situ bedrock mineralisation
- Maiden resource defined at Ndablama
Central, mineralisation remains open
25
¹
25
- Pressure shadow zone extends over
5km between Ndablama North and Leopard Rock South
- Ndablama Phase 1-3 drilling program
completed for 54 drill holes (c.8,300m)
- Inferred Resource of 451Koz grading
2.1g/t calculated from Phases 1-3 drilling
- Metallurgical test work returned overall
recoveries of c.94%.
- 70% recovery though gravity processes
- Further drilling undertaken at Leopard
Rock confirms mineralisation continuity to the South
- Trenching at Ndablama North also
intersected mineralisation and will be drill tested in 2015
1,300m
26
- Phase 4 drilling programme completed
for 100 holes (61 x DDH: 13,000m, 39 x RC: 5,800m)
- Results announced from 51 holes
(11,200m) with results pending for 49 holes (7,600m)
- RC drilling targeted the infill areas
between previously drilled holes
- Diamond holes tested down dip & strike
extensions
- Latest results extend the continuity of the
mineralisation
- Resource upgrade underway, expected
completion due early Q4 2014
- Preliminary Economic Assessment
expected end of Q4 2014
27
¹
140m 120m
28
Gondoja Gbalidee Koinja
Koinja Gondoja Gbalidee Ndablama
- SZ geological mapping
- Koinja, Gbalidee and
Gondoja detailed mapping and interpretation
- Target drilling (next season)
Trench: 22 m @ 3.4 g/t Trenches: 6 m @ 2.2 g/t 18 m @ 0.9 g/t Trenches: 7 m @ 13.1 g/t 38 m @ 1.2 g/t DDH: 30 m @ 3.9 g/t 3 m @ 14.8 g/t 4.3 m @ 3.6 g/t
29
¹
- 1470km2 contiguous licence portfolio
- Shear Zones represent extensive conceptual
targets extending for an overall 150 km over the licence area
- Regional mapping has highlighted new targets,
mainly Welinkua, Diabobo and Mabong
- Current BLEG coverage on new licenses to
deliver stream anomalies to generate targets
20 km Mabong License Archaen West License Yambesei License Mafa West License Archean Gold Diabobo Welinkua
29
30 1,0 ,000 1,2 ,200 1,4 ,400 1,6 ,600 1,8 ,800 2,0 ,000 Apri ril 2011 Aug ugus ust 2 t 2011 Decemb mber r 2011 Apri ril 2012 Aug ugus ust 2 t 2012 Decemb mber r 2012 Apri ril 2013 Aug ugus ust 2 t 2013 Decemb mber r 2013 Apri ril 2014
Gold d Price ce US$/o $/oz
Listed on TSX & AIM Raised US$40m First Drawdown
- n US$100m
project finance facilities Rasied US$26m M&I Resource increased to 2.4Moz @ 2.9g/t Resource of 1.7Moz @ 3.6g/t declared Raised US$80m from equity
- ffering
DFS Completed Reserves of 924koz @ 3.4g/t declared US$100m debt financing & credit approval secured Raised US$16m from equity
- ffering
New Liberty Feasibility Study completed Maiden Reserve of 873Koz @ 3.1g/t declared Feasibility drilling completed 13Km gold corridor
- utlined
Earthworks & early construction commence
- n site
RAP & CDP approved for New Liberty Nedbank & RMB mandated for project financing Mill foundations completed & steel work commenced
31
BFS DFS FS FS PFS PEA Stag age of Project:
New Liberty (Aureus, 2013) Karma (True Gold, 2014) Singuida (Shanta, 2011) Tri-K (Avocet, 2013) Banfora (Gryphon, 2013) Obotan (Asanko, 2012) Hounde (Endeavour, 2013) Esaase (Asanko, 2013) Fekola (Papillion, 2013) Kiaka (B2Gold, 2012) Banfora (Gryphon, 2014) Bombore (Orezone, 2014) Dugbe (Hummingbird, 2013) Natougou (Orbis, 2013) Yaoure (Amara, 2014) Bombore (Orezone, 2011) Yanfolila (Hummingbird, 2014)
100 100 200 200 300 300 400 400 500 500 600 600 700 700 0.0 .0 1.0 .0 2.0 .0 3.0 .0 4.0 .0 5.0 .0 6.0 .0
Proje ject CapEx Ex (US$m $m) Averag age Gold Grade Mined (g/t)
32
- The only fully financed gold project under construction in West Africa
- First gold pour due Q1 2015
- Project provides real investment value
- Undervalued relative to other fully financed developers
- Sufficient cash resources available post construction
- Project fully derisked following BFS + bank due diligence
- Project endorsed by the lending banks, IFC, shareholders and Government of Liberia
- Further upside around New Liberty and resource expansion underway at Ndablama
New Liberty rty Plant Site Overview
Thank you
www.a .aureu ureus-mining ining.com .com
34
New Liberty rty Plant Site
35
Ball Mill & Vertimi mill Foundat ations ns
36
Ball Mill Arri rival al at New Liberty rty
37
Rom Tip & Prima mary ry Crus ushi hing ng Struct ructure ure Stoc
- ckpile Tunnel
38
Tailings Stora
- rage Facility
39
MCDC Spillway ay Marvoe Creek Diversion
- n Chann
nnel Re-vegetat ation
- n
40
Camp David Mine Personne nnel Accommodati
- mmodation
- n
Camp David Mine Personne nnel Accommodati
- mmodation
- n
41
Completed RAP Houses RAP Village – New Schoo hool Buildings
Debar ar Allen en– General Man anager ger - Mon
- nrovia
- via
- MBA & 17 years experience with US based
companies; managed private construction company since returning to Liberia in 2003
- Vice Chairman of the Board of Directors for the
Liberian Maritime Authority David d Readin ding – CEO and d Director tor
- 35 years experience in global mining: exploration,
feasibility, project development and production
- Former CEO, European Goldfields. Former GM
Exploration, RRL. MSc Econ. Geology David d Nether erway – Chai airma man and d Director tor
- Mining engineer with >35 years of experience.
Former CEO of Shield Mining
- Involved in development & construction of Iduapriem,
Siguiri & Kiniero gold mines in West Africa Adrian an Reynolds ds – Non
- n-exec
executive Directo tor
- At RRL, compiled feasibility studies at Morila, Loulo
and Tongon gold mines in West Africa
- 30 years experience in the industry. MSc Geology &
GDE in Mining Engineering Lui uis da Silva – Non
- n-exec
executi utive e Directo tor
- CEO of GB Minerals. Former CEO of Afferro Mining &
- f African Aura pre split. Continuity with New Liberty
- Graduate Mining Engineer and MBA. Extensive
international experience with Lafarge & Blue Circle Lou
- udon
don Owen – Non
- n-exec
executi utive e Directo tor
- Successful international business man and lawyer,
founder of McLean Watson Capital
- Extensive public and private company board
experience, including Kilo Gold Mines Jean an-Guy uy Mar artin tin – Non-ex executiv tive e Director tor
- Extensive experience advising multinationals looking
to complete acquisitions & divestitures
- 35 years experience financial reporting. Former
partner of PwC Canada
42
Thinus us Strydom dom – GM Con
- nstructio
uction & Mine e Operati ation
- n
- Mining engineer with >16 years of experience in the
design, construction, development & operation of mines
- Experience includes key roles at Loulo for RRL and at
Bisha for Nevsun Resources Paul ul Thoms
- mson – CFO
- Chartered Accountant with 20 years global
experience in the energy and mining industries
- Formerly with Ernst & Young and Kazakhmys PLC
Germai main Cresti estin – VP Explora
- ration
- 20 years experience for RRL in Burkina Faso & Mali,
European Goldfields & Eldorado in Turkey, Greece & SE Europe.
- Chief Geologist in Mali when 7Moz Yalea gold deposit
was discovered
43
Depo posit sit Catego tegory Tonna nnage ge (Kt Kt) Gold d (Koz
- z)
Grade de (g/t) g/t) Above ve Cut-Off ff (g/t) g/t) New Liberty M&I 9,796 1,143 3.6 1.0 New Liberty Inferred 5,730 593 3.2 1.0 Ndablama Inferred 6,829 451 2.1 0.5 Weaju Inferred 2,680 178 2.1 1.0 Depo posit sit Catego tegory Tonna nnage ge (Kt Kt) Gold d (Koz
- z)
Grade de (g/t) g/t) Above ve Cut-Off ff (g/t) g/t) New Liberty Proven 700 99 4.4 0.8 New Liberty Probable 7,800 825 3.3 0.8 New w Libert erty Tota tal l Reser serve ve 8,50 500 924 24 3.4 0.8
Miner eral l Resource ces Miner eral l Reserve erves
Note 1: Mineral Resources for the New Liberty & Weaju deposits are reported to a cut-off grade of 1.0 g/t Au. The Ndablama deposit is reported at a cut-off grade of 0.5 g/t Au Note 2: The effective date of the Ndablama & Weaju gold deposits mineral resource estimates is 11 November 2013. Note 3: The effective date of the New Liberty gold deposit mineral resource estimate is 1 October 2012 and the mineral reserve estimate is 20 May 2013. Note 4: Canadian Institute or Mining, Metallurgy and Petroleum (CIM) definitions were used for both mineral resources and reserves Note 5: Mineral resources, which are not mineral reserves, do not have demonstrated economic viability. The estimate of mineral resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues. Note 6: Totals and average grades are subject to rounding to the appropriate precision
44
10 10 20 20 30 30 40 40 50 50 60 60
- 1
1 2 2 3 3 4 4 5 5 6 6 7 7 Year 0 r 0 Year 1 r 1 Year 2 r 2 Year 3 r 3 Year 4 r 4 Year 5 r 5 Year 6 r 6 Year 7 r 7 Year 8 r 8
Conatin ined ed Gold d (Koz) Mined Tonnes es (Mt)
Mater eria ial Moveme ment nt by Stage e & AU Oz Mined ed
LATKIN STAGE1 LATKIN STAGE2 LARJOR STAGE3 LATKIN STAGE4 MARVOE STAGE6 MARVOE STAGE5 CONTAINED GOLD
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Oct-12 Dec-12 Feb-13 Apr-13 Jun-13 Aug-13 Oct-13 Dec-13 Feb-14 Apr-14 Jun-14 Aug-14 Oct-14 Dec-14 Feb-15 Apr-15 Jun-15 Aug-15
Overall all Progress ress Status tus date - 15 Augus ust t 2014
Current Date First Gold Actual Early Start Curve Late Start Curve 1st Gold Target - 31 March 2015
45
- First Gensets arrived and commissioned on site
- Mining fleet supply and maintenance contracted
- Mining fleet currently mobilising to site
- Ball mill on site and currently being installed
46