A DJACENT C ONSTRUCTION P ROGRAM O VERVIEW Chicago Transit Authority Steven Mascheri General Manager, Capital Construction November 18, 2015 A GENDA Explanation of Adjacent Requirements Types of Partnerships Planning Work


slide-1
SLIDE 1

ADJACENT CONSTRUCTION PROGRAM OVERVIEW

November 18, 2015

Chicago Transit Authority

Steven Mascheri General Manager, Capital Construction

slide-2
SLIDE 2

AGENDA

2

  • Explanation of Adjacent Requirements
  • Types of Partnerships
  • Planning Work
  • Performing Work
  • Additional Information
slide-3
SLIDE 3

ADJACENT CONSTRUCTION

3

Explanation of Adjacent Requirements

  • Safe Working Conditions
  • Coordination to minimize service disruptions
  • Notification to riders and general public
slide-4
SLIDE 4

PARTNERSHIPS

4

slide-5
SLIDE 5

PARTNERSHIPS

5

PRIVATE PARTIES

  • High Rise Construction
  • Utility Relocation
  • Building Maintenance
  • Emergency Repairs
  • Planning
slide-6
SLIDE 6

6

PARTNERSHIPS

slide-7
SLIDE 7

7

PARTNERSHIPS

slide-8
SLIDE 8

8

  • Working within 50’ of CTA Infrastructure
  • Track Structure
  • Rail Stations
  • Bus Garages
  • Rail Yards
  • Subway Tubes
  • Other Infrastructure

Within 50’ of CTA’s Right-of-Way

PLANNING WORK AROUND CTA

slide-9
SLIDE 9
  • Permit Process
  • Department of Buildings
  • Office of Underground Coordination
  • Advance Notification
  • Meet With Construction, Safety and

Operations Groups

PLANNING WORK AROUND CTA

slide-10
SLIDE 10
  • Flagging Slow Zone
  • Bus Reroute
  • Vibration Monitoring
  • Settlement Monitoring

TYPES OF IMPACTS PERFORMING WORK

slide-11
SLIDE 11
  • Rail Single Track
  • Train reroute

TYPES OF IMPACTS PERFORMING WORK

slide-12
SLIDE 12
  • Process Plans
  • Insurance Requirements
  • Rail Safety Training
  • Estimate for Support Costs
  • Flagging, Track Access
  • Inspections
  • CTA Capital Projects
  • Other Adjacent Construction
  • Restricted Dates (Holidays, festivals, etc)

PERFORMING WORK COORDINATION

slide-13
SLIDE 13

CTA Website: http://www.transitchicago.com/adjacentconstruction

ADDITIONAL INFORMATION