City of Rehoboth Beach Ocean Outfall Project Town Hall Q&A - PowerPoint PPT Presentation
City of Rehoboth Beach Ocean Outfall Project Town Hall Q&A Workshop September 16, 2017 City of Rehoboth Beach Town Hall Workshop September 16, 2017 Agenda Projects Overview Force Main Construction Force Main Alignment
City of Rehoboth Beach Ocean Outfall Project Town Hall Q&A Workshop September 16, 2017 City of Rehoboth Beach Town Hall Workshop – September 16, 2017
Agenda • Projects Overview • Force Main Construction • Force Main Alignment • Construction Plan / Impacts • Deauville Beach • Questions City of Rehoboth Beach Town Hall Workshop – September 16, 2017
Ocean Outfall Projects Outfall Pipe & Diffuser • 24-inch outfall pipe from the staging area to the outfall diffuser, 6,000 ft away • Located at end of outfall pipe, 6,000 ft offshore Force Main • Force main from the RBWWTP to the outfall staging area (approximately 11,400 ft) Pump Station • New pump station located at the RBWWTP WWTP Reliability Upgrades • Various upgrades at the Rehoboth WWTP City of Rehoboth Beach Town Hall Workshop – September 16, 2017
Force Main Proposed Force Main Alignment • 11,400 linear feet long, 24- inch diameter PVC pipe. • Will predominately follow existing utilities and right of ways Construction Methods • Combination of open cut excavation and jack and bore City of Rehoboth Beach Town Hall Workshop – September 16, 2017
WWTP / Roosevelt Street o City of Rehoboth Beach Town Hall Workshop – September 16, 2017
State Road / Canal Street o City of Rehoboth Beach Town Hall Workshop – September 16, 2017
Canal Street / Rehoboth Avenue City of Rehoboth Beach Town Hall Workshop – September 16, 2017
Grove Park o City of Rehoboth Beach Town Hall Workshop – September 16, 2017
Henlopen Avenue o o City of Rehoboth Beach Town Hall Workshop – September 16, 2017
Henlopen Avenue o o City of Rehoboth Beach Town Hall Workshop – September 16, 2017
City of Rehoboth Beach Town Hall Workshop – September 16, 2017
Construction Plan • Working hours are 7:30 am to 6:00 pm, Monday thru Friday • Installation expected to be 50 to 80 LF per day • Trench width will be ~6 ft • Depth of pipe varies • Contractor will be limited to ~200 LF of open-cut trench at any time • Traffic control will extend on 200 ft on each side • Various road closures are expected - Henlopen • Parking gravel/grass areas along northside of roadway will be impacted • Paving will be completed at end of project City of Rehoboth Beach Town Hall Workshop – September 16, 2017
City of Rehoboth Beach Town Hall Workshop – September 16, 2017
City of Rehoboth Beach Town Hall Workshop – September 16, 2017
City of Rehoboth Beach Town Hall Workshop – September 16, 2017
Deauville Beach City of Rehoboth Beach Town Hall Workshop – September 16, 2017
Deauville Beach City of Rehoboth Beach Town Hall Workshop – September 16, 2017
Outfall City of Rehoboth Beach Town Hall Workshop – September 16, 2017
Questions? City of Rehoboth Beach Town Hall Workshop – September 16, 2017