Clinton Combined Sewer Overflow (CSO) Storage Facility Project Bruce G. Munn, Nicholas Capozza, Ryan C. Fisher, A.J . McGinn J une 4, 2013 Onondaga County Executive Onondaga County Executive Joanne M. Mahoney Joanne M. Mahoney Project T


slide-1
SLIDE 1

Onondaga County Executive Joanne M. Mahoney

Clinton Combined Sewer Overflow (CSO) Storage Facility Project

Onondaga County Executive Joanne M. Mahoney

Bruce G. Munn, Nicholas Capozza, Ryan C. Fisher, A.J . McGinn J une 4, 2013

slide-2
SLIDE 2

Onondaga County Executive Joanne M. Mahoney

Project T eam Acknowledgement

  • Environmental Engineering Associates, LLP
  • GHD
  • O’Brien & Gere
  • ARCADIS

Onondaga County Department of Water Environment Protection

  • Matthew J. Millea, Deputy County Executive
  • T
  • m Rhoads PE, Commissioner
  • Nicholas Capozza, Project Manager
slide-3
SLIDE 3

Onondaga County Executive Joanne M. Mahoney

Project T eam Acknowledgement

Brierley Associates – Geotechnical Engineering

Bryant Associates – Structural Inspection Services Fisher Associates – Site/ Civil Inspection Services B&L Engineering – Site/ Traffic Design Group One Design – Architectural Design Landscape & Prospect – Landscape Architecture PB Americas – Noise Mitigation

CDM / C+S J

  • int Venture – Construction Management

J ett Industries/ Kiewit Construction – General Contractor

slide-4
SLIDE 4

Onondaga County Executive Joanne M. Mahoney

Project Background

  • Judgment on Consent signed in 1989
  • Amended Consent Judgment (ACJ) signed 1998

Capture >85% of average annual CSOs Removal of floatables Achieve water quality standards for bacteria in Onondaga Lake

  • County negotiated 4th Stipulation ACJ November 2009

3.7 MG Clinton CSO storage operational by December 31, 2013 Incorporation of Green Infrastructure for CSO reduction 95% CSO Capture by December 31, 2018

slide-5
SLIDE 5

Onondaga County Executive Joanne M. Mahoney

Project Location

Onondaga Lake Metro WWTP Destiny USA Clinton CSO Storage Facility Armory Square S.U. Sheraton

slide-6
SLIDE 6

Onondaga County Executive Joanne M. Mahoney

Project Location

  • Insert CSO map from Ed
slide-7
SLIDE 7

Onondaga County Executive Joanne M. Mahoney

Key Project Goals/ Challenges

  • M eet ACJ milestones and requirements

– Complete Design November 2010 – Commence Construction July 2011 – Commence Operation December 31, 2013

  • Keep all CSO storage below grade

– Allow reuse of parking lot above CSO Storage – High saline content of groundwater up to 80,000 mg/ l – Comply with BMP’s for groundwater dewatering

slide-8
SLIDE 8

Onondaga County Executive Joanne M. Mahoney

Key Project Goals/ Challenges

  • Other County Goals

– Maximize CSO Storage – Requirement to accommodate 1 year

2 hour storm flow

– Be consistent with “Save the Rain Program”

  • Local Construction Concerns

– M itigation of construction noise – Parking/ Traffic mitigation – Archeological/ Environmental concerns

slide-9
SLIDE 9

Onondaga County Executive Joanne M. Mahoney

CSO Storage Facility Alternatives

  • 1. Conventional Dewatering/ Construction
  • 2. Tunneling Construction
  • 3. Four Vertical Slurry Wall Tanks/ Cut and Cover

Conveyance

  • 4. Three Vertical Slurry Wall Tanks/ Single Tunnel
slide-10
SLIDE 10

Onondaga County Executive Joanne M. Mahoney

slide-11
SLIDE 11

Onondaga County Executive Joanne M. Mahoney

slide-12
SLIDE 12

Onondaga County Executive Joanne M. Mahoney

slide-13
SLIDE 13

Onondaga County Executive Joanne M. Mahoney

slide-14
SLIDE 14

Onondaga County Executive Joanne M. Mahoney

Alternative Cost Analysis

1 Cut-and-Cover (single tank) 2 Three Tunnels 3 Slurry Wall Three Tank/ Tunnel 4 Slurry Wall four tank and cut-and- cover Construction Cost $55,800,000 $36,700,000 $41,200,000 $48,800,000 Overflow Pumping Addition $3,300,000 $3,300,000 $3,300,000 $3,300,000 Contingency (20%) $11,800,000 $8,000,000 $8,900,000 $10,400,000 Subtotal Construction Cost $70,900,000 $48,000,000 $53,400,000 $62,500,000 Escalation to Construction Mid Point in 2012 (6%) $4,300,000 $2,900,000 $3,200,000 $3,800,000 Total Estimated Construction Cost $75,200,000 $50,900,000 $56,600,000 $66,300,000

slide-15
SLIDE 15

Onondaga County Executive Joanne M. Mahoney

Unique Design Aspects

  • Innovative Geotechnical

Approach

Slurry diaphragm wall

construction

Jet grout plug and sheeting

groundwater containment

Open face + closed face

TBM options

  • Specialized Construction

Prequalification

Jet grouting Tunneling

  • Project Labor Agreement

Provisions

Union work force Exemption from Wicks Law One construction contract

slide-16
SLIDE 16

Onondaga County Executive Joanne M. Mahoney

Use of Green T echnologies

  • Recovery and reuse of storm drainage flows for CSO

Storage Cleaning

  • Bioswales and storm flow treatment
  • Green roof on West Chamber
  • Use of LED site lighting and parking lot lighting
  • “Flow through by gravity” design
slide-17
SLIDE 17

Onondaga County Executive Joanne M. Mahoney

Construction Approach

  • Project Bid July 2011 - $70,640,000

– General Contractor - Jeff Industries/

Kiewit Construction

  • Contract Awarded August 2011
  • Revised Construction Approach

Reinforced concrete box tunnels vs. circular

tunnels

slide-18
SLIDE 18

Onondaga County Executive Joanne M. Mahoney

Facility layout

slide-19
SLIDE 19

Onondaga County Executive Joanne M. Mahoney

West Chamber

slide-20
SLIDE 20

Onondaga County Executive Joanne M. Mahoney

West Structure

slide-21
SLIDE 21

Onondaga County Executive Joanne M. Mahoney

East Chamber

slide-22
SLIDE 22

Onondaga County Executive Joanne M. Mahoney

slide-23
SLIDE 23

Onondaga County Executive Joanne M. Mahoney

slide-24
SLIDE 24

Onondaga County Executive Joanne M. Mahoney

slide-25
SLIDE 25

Onondaga County Executive Joanne M. Mahoney

slide-26
SLIDE 26

Onondaga County Executive Joanne M. Mahoney

slide-27
SLIDE 27

Onondaga County Executive Joanne M. Mahoney

slide-28
SLIDE 28

Onondaga County Executive Joanne M. Mahoney

Project Status

  • Project is 70% complete
  • Scheduled for operational December 31, 2013
  • 12 month start up and performance period,

December 31, 2014

  • Project updates to follow
slide-29
SLIDE 29

Onondaga County Executive Joanne M. Mahoney

QUES TIONS?

Onondaga County Executive Joanne M. Mahoney

Bruce Munn bruce.munn@ghd.com (315) 679 5800