Community Meeting 22 August Fingerboards Project Description - - PowerPoint PPT Presentation

community meeting 22 august
SMART_READER_LITE
LIVE PREVIEW

Community Meeting 22 August Fingerboards Project Description - - PowerPoint PPT Presentation

Community Meeting 22 August Fingerboards Project Description Outline of Presentation This presentation is aimed at providing the following: Overview of the Fingerboards project description Mining and processing methods


slide-1
SLIDE 1

Community Meeting 22 August Fingerboards Project Description

slide-2
SLIDE 2

Outline of Presentation

2

This presentation is aimed at providing the following:

  • Overview of the Fingerboards project description
  • Mining and processing methods
  • Rehabilitation and restoration
  • Water sourcing and management
  • Required infrastructure
  • Outline of the footprint in the project area
  • Outline what changes* have been made to the project
  • Logistics
  • Water management
  • Infrastructure

* Changes are shown in blue text in the presentation

slide-3
SLIDE 3

Project Location

3

slide-4
SLIDE 4

Project Area – 1675 hectares

4

slide-5
SLIDE 5

Overall Process

5

slide-6
SLIDE 6

Mining method

6 Pasture Re-seeding Topsoil Placement Fines Consolidation using amphiroles Sand Stacking Tailings Free flowing sand dozer Overburden Removal by Excavator Topsoil stripping by scraper Soil Conditioning

800m

  • Conventional dry mining operation
  • Ore slurried to processing plant
  • Progressive mining sequence
  • Two mining units and pits will be used after year 1
  • Capacity of 1500 tph of ore treatment
slide-7
SLIDE 7

Processing method

7

  • Conventional wet gravity separation to concentrate the product
  • Only uses water for mineral separation
  • Percent solids of fine tailings increased in a thickener
  • Sand tailings returned to mine void
  • Fine tailings sent to tailings storage facility (the temporary TSF)

Gravity Circuit Thickener Feed Tank Water Tank Screening Plant Magnetic Circuit

slide-8
SLIDE 8

Rehabilitation and Restoration

8

slide-9
SLIDE 9

Rehabilitation and Restoration

9

slide-10
SLIDE 10

Mining Layout – first years

10

slide-11
SLIDE 11

Water

11

  • Water is required for:
  • Processing of the ore (~ 2.5 GL per year)
  • Dust management – spraying haul roads using water carts (370 ML per year)
  • Site ablutions
  • Offices and workshops
  • Project will require approximately 3 GL of water per year
  • Most water lost to:
  • Seepage from sand tailings
  • Evaporation from tailings
slide-12
SLIDE 12

Water Management

12

How will water be managed by Kalbar? Kalbar’s water management plan aims to achieve the following:

  • Minimise the amount of new water used by:

– Maximising water recovered from tailings – Capturing and using rain water falling in mine dams and mine void – Use “mine contact” rain water as process water – If required, managed discharge of treated mine contact water

  • Minimise the impact on environmental flows to the Mitchell and Perry Rivers

– Controlled release of rain water falling on non-mining areas within project area – Prevent uncontrolled release of water from site by using water catchment management dams

  • Have a positive impact on Mitchell River flow during summer months

– Release stored water from site in a controlled manner during summer months

slide-13
SLIDE 13

Surface Water

13

  • Water sourced from the Mitchell River as winterfill take and use licence
  • Two options considered for off-take locations from the Mitchell River
  • Water will be stored in a 2.2 GL fresh water dam within the project area
  • Rain water falling away from mining activities will flow naturally from project area
  • Rain water falling in catchment that doesn’t come into contact with disturbed land

will be released in a controlled manner to the river system

  • Rain water falling on area disturbed by mining activity will be captured in dams
  • This water will be re-used as process water
  • Use of this water will be off-set with fresh water
  • Areas within the catchment dam footprint is considered as disturbed land
slide-14
SLIDE 14

Water Management

14

slide-15
SLIDE 15

Groundwater - Monitoring

15

slide-16
SLIDE 16

Groundwater - Sourcing

16

  • Ground water will be used to supplement water

requirements

  • Sourced from the Lower Aquifer (Latrobe Group)
  • Impact of extraction has been modelled for 15 years

at 3 GL per annum

  • Assessed a large area in the EES for bore field
  • Cultural Heritage
  • Biodiversity
  • Boreholes will disturb a small area of land
  • Groundwater from bore will be piped to process

water dam 2 km

slide-17
SLIDE 17

Roads – Road re-alignment options

17

slide-18
SLIDE 18

Footprint of Disturbance - Hectares

18

Description Old New Topsoil strip 35 35 Overburden strip 23 23 Ore and pit floor 18 18 Course sand tailings and fine tailings cell construction 19 19 Overburden placement 5 5 Topsoil placement 35 35 Mining sub-total 135 135 Fines tailing storage 90 90 Topsoil stockpiles 45 Off path sub-total 90 135 All other infrastructure 55 90 TOTAL

280 360

slide-19
SLIDE 19

Infrastructure

19

slide-20
SLIDE 20

Logistics

20

slide-21
SLIDE 21

Rail Sidings - Fernbank

21

  • Siding located close to project area on private land
  • Will utilise a private haulage road from project area
  • Haulage road aligned with power and water services corridor
  • Option included in the EES assessments
  • Traffic
  • Cultural heritage
  • Biodiversity
  • Noise and vibration
  • Visual
  • Air quality
  • Socioeconomic
slide-22
SLIDE 22

Rail Siding - Bairnsdale

22

  • An alternative option is to use the existing siding in Bairnsdale
  • Concentrate will still be loaded into containers at the mine site
  • Containers will be trucked to Bairnsdale via Lindenow South (see map below)
  • Proposed route will avoid traffic along main road in Bairnsdale
  • Intersection on Princes Highway will be upgraded
  • Trucks directed around race course to siding
  • Siding located near Fennings yard will need to be upgraded
  • Option included in the EES assessments
  • e.g. traffic, cultural heritage, biodiversity and socioeconomic
slide-23
SLIDE 23

Enquiries: Victor Hugo - Chief Executive Officer Mobile: +61 408 803 222 Email: victor.hugo@kalbarresources.com.au Kalbar Resources Limited ABN 30 149 545 362 www.kalbarresources.com.au

slide-24
SLIDE 24

Section 7 Exemption

24