Complex Open Cut Optimisation Modification IPC Briefing 27 March - - PowerPoint PPT Presentation

complex
SMART_READER_LITE
LIVE PREVIEW

Complex Open Cut Optimisation Modification IPC Briefing 27 March - - PowerPoint PPT Presentation

Moolarben Coal Complex Open Cut Optimisation Modification IPC Briefing 27 March 2019 Overview Moolarben Coal Complex Modification Description Environmental Assessment 2 Moolarben Coal Complex Currently Approved Stage 1


slide-1
SLIDE 1

Moolarben Coal Complex Open Cut Optimisation Modification IPC Briefing 27 March 2019

slide-2
SLIDE 2

Moolarben Coal Complex

Modification Description

Environmental Assessment

2

Overview

slide-3
SLIDE 3

3

Moolarben Coal Complex – Currently Approved

Stage 1 (PA 05_0117):

Approved September 2007

Construction 2009, operations 2010

Open Cuts (OC1, OC2 & OC3)

Underground (UG4)

CHPP and rail loop

Stage 2 (PA 08_0135):

Approved January 2015

Open Cut (OC4)

Underground (UG1 and UG2)

ROM coal to Stage 1 CHPP

Current Operations

OC1, OC2, OC4, UG1, CHPP Approved Moolarben Coal Complex

UG4 CHPP OC1 OC2 OC3 UG1 OC4 UG2

Stage 1 Stage 2

slide-4
SLIDE 4

Increased open cut production limits from 13 to 16 Mtpa (Stages 1 and 2 combined)

Realignment of OC3 infrastructure

Revised OC3/OC2 pit limits

OC2 to OC4 internal road

Bypass conveyor

Water treatment facility, revised EPL release point and release conditions

Final landuse in OC2 and OC3 (proposed change to native vegetation from agricultural land)

Other minor infrastructure changes within extent of approved disturbance

No change to the approved underground mining operations

No change to final voids

4

Modification Description – Overview

Modification General Arrangement

Relocated EPL Release Point Bypass Conveyor OC2 to OC4 Internal Road Realigned OC3 Infrastructure and Pit Limits Extension to OC2 Pit Limit Water Treatment Facility

Proposed Modifications:

slide-5
SLIDE 5

The Modification would not change the currently approved:

5

Modification Description – Overview

Underground operations (layouts and production limits)

OC1 or OC4 pit limits

Hours of operation

Blasting frequency limits

Site access

Method of reject disposal

Peak workforce

Final voids

slide-6
SLIDE 6

Increased Open Cut Production Limits

6

Modification Description

Stage 1 Project Approval open cut coal production limit:

  • Currently 8 Mtpa combined total from OC1, OC2 and OC3
  • The Modification seeks to increase this from 8 to 10 Mtpa

Stage 2 Project Approval open cut coal production limit:

  • Currently 12 Mtpa from OC4
  • The Modification seeks to increase this from 12 to 16 Mtpa

Combined Stage 1 and Stage 2 open cut production is currently limited to 13 Mtpa in total:

  • The Modification seeks to increase annual open cut production limits from 13 to 16 Mtpa

(Stages 1 and 2 combined)

Associated production limit changes:

  • Increased combined annual open cut and underground ROM coal production limits from 21 to 24 Mtpa
  • Increased annual coal processing (washing limit) from 13 to 16 Mtpa
  • Increased annual product coal limit from 18 to 22 Mtpa
slide-7
SLIDE 7

Realigned OC2 to OC3 haul road

Relinquishment of approved disturbance and OC3 out of pit emplacement

Relocated OC3 MIA

OC3 revised pit limits

OC2 revised pit limit

7

Modification Description

Modification Disturbance Area

“Relinquishment”

Area Extension to OC2 Pit Limit Approved Haul Road and MIA Modified Haul Road Modified MIA OC3 Pit Limit Extensions Approved OC3 Emplacement OC3 Pit Limit Reductions

OC3 Infrastructure and OC2/OC3 Pit Limits

slide-8
SLIDE 8

Unsealed internal road would be constructed between OC2 and OC4

Not used to haul coal or overburden

Used for the occasional transfer of mining equipment

  • nly

Internal road would generally follow an existing track

Bypass Conveyor

Bypass conveyor would be constructed to enable

  • pen cut ROM coal to bypass the CHPP

Bypass would create additional marketing

  • pportunities and reduce the production of rejects

Associated minor infrastructure upgrades within approved disturbance limits

8

Modification Description

Internal Road

Bypass Conveyor, Realigned Haul Road and Bypass Coal Stockpile Area Internal Road

slide-9
SLIDE 9

OC2 is approved to be rehabilitated to a combination of agricultural land and native vegetation

OC3 is approved to be rehabilitated to agricultural land

This Modification proposes an increased proportion of OC2 and OC3 to be rehabilitated to native vegetation

Revised rehabilitation outcomes would improve biodiversity and connectivity in the final landform

9

Modification Description

Final Land Use

slide-10
SLIDE 10

Requirement identified through ongoing review of site water balance

Avoids build up of mine water on-site in the long-term

Ensures controlled releases in accordance with EPL water quality release limits

Brine generated by the water treatment process managed in the first instance by diluting with stored water and used in dust suppression

Residual brine permanently stored within the UG4 void (following UG4 mining)

10

Modification Description

Water Treatment Facility

Brine Dams Water Treatment Plant Raw Water Dam

slide-11
SLIDE 11

EPL 12932 discharge point (EPL ID1) relocated from current location (into Bora Creek) to environmentally superior location at the confluence of Bora Creek and the Goulburn River

Discharge water would be piped from the water treatment facility to the relocated discharge point

Proposed discharge point avoids potential erosion from controlled releases along Bora Creek

11

Modification Description

Relocation of EPL Release Point

Revised EPL Release Point Approved EPL Release Point (EPL ID1) Indicative Pipeline

Goulburn River Diversion at the confluence with Bora Creek Bora Creek (looking downstream) - avoided

Water Treatment Facility

slide-12
SLIDE 12

12

Environmental Assessment – Surface Water

Controlled Releases

MCO’s existing EPL (12932) authorises:

  • Up to 10 ML/day controlled release
  • Salinity limit of 900 µS/cm (maximum)

Modification proposes:

  • Relocation of existing EPL authorised release point (EPL ID1) to an environmentally superior location
  • Increased controlled release volume during certain periods of the mine life

Collaborative development of proposed release limits with the EPA and DPE:

  • Reduction in existing EPL 12932 salinity limit from 900 µS/cm to 685 µS/cm

Revised limit of 685 µS/cm developed in consultation with EPA and DPE per ANZECC process

  • No change to existing EPL 12932 volume limit for the majority of the mine life:

No change to existing 10 ML/day limit up to the commencement of mining operations in UG4 and following completion of mining operations in UG4

Up to 15 ML/day during mining operations in UG4

Greater than 15 ML/day during prolonged wet periods, with the approval of EPA

slide-13
SLIDE 13

13

Environmental Assessment – Biodiversity

Disturbance and Offsets

Modification Proposes:

  • Disturbance of ~80 ha in the Modification Area (comprising

39 ha native vegetation and 41 ha non-native vegetation)

  • “Relinquishment” of 34.5 ha of vegetation previously

approved for clearing (including 15 ha of native vegetation)

  • Additional land-based offset (known as “Gilgal”)

OEH has reviewed and accepted the offset calculations as presented in the Biodiversity Assessment Review

The DPE Assessment Report considers the proposed impacts to be acceptable, subject to the identified avoidance, mitigation and offsetting measures

MCO would secure the Gilgal biodiversity offset area in accordance with the draft modified conditions of approval

“Gilgal” is owned by MCO and abuts nature reserve

Existing Biodiversity Offset Area Gilgal National Park

slide-14
SLIDE 14

14

Environmental Assessment – Air Quality

Air Quality Assessment

The Modification proposes increased annual production limits and minor increases in disturbance areas

The Air Quality Assessment for the Modification predicted no exceedances of relevant PM10, PM2.5, total suspended particulates or dust deposition criteria at any privately-owned receptors due to emissions from the Moolarben Coal Complex incorporating the Modification

The DPE Assessment Report considered that predicted air quality would be similar to the existing approved levels and can be effectively managed under the existing conditions of approval

MCO would continue the operation of real-time and proactive air quality management system

MCO would install a real-time PM2.5 monitor as part of its Air Quality Monitoring Program

slide-15
SLIDE 15

15

Environmental Assessment – Noise

Noise Assessment

The proposed optimisations to open cut operations (including production increase to 16Mtpa ROM) can be achieved with no material change to the existing mining fleet

The Noise Assessment for the Modification predicts:

  • The Moolarben Coal Complex would continue to comply with the existing noise limits at all private

residences

  • Rail noise along the Sandy Hollow-Gulgong Railway would continue to comply with the relevant criteria of

the Rail Infrastructure Noise Guideline

The DPE Assessment Report considers that predicted noise levels would be similar to the approved levels and can be effectively managed under the existing conditions of approval

MCO would continue the operation of its real-time and proactive noise management system

slide-16
SLIDE 16

16

DPE Assessment Report

Conclusions

The DPE Assessment Report made the following conclusions:

  • Any additional impacts from the Modification would be minor, including cumulative impacts
  • Controlled releases would be as per ANZECC and would be at the currently approved release rate for the

majority of the mine life

  • Additional vegetation clearing would be relatively small and compensated by a significant land based offset

(and other approved mechanisms)

  • Amenity impacts (i.e. noise and air quality) can be managed under the existing conditions of approval

DPE has proposed draft modified conditions of Project Approvals (05_0117 and 08_0135) with input from other agencies

MCO accepts DPE’s draft modified conditions

slide-17
SLIDE 17

Presentation end