CTC Item 26: Innovations in Transportation San Francisco Oakland - - PowerPoint PPT Presentation

ctc item 26 innovations in transportation san francisco
SMART_READER_LITE
LIVE PREVIEW

CTC Item 26: Innovations in Transportation San Francisco Oakland - - PowerPoint PPT Presentation

CTC Item 26: Innovations in Transportation San Francisco Oakland Bay Bridge Implosions California Transportation Commission December 6, 2017 1 This is how i t started SFOBB Pier E9 Following the 1989 Loma Prieta Earthquake Bay


slide-1
SLIDE 1

1

CTC Item 26: Innovations in Transportation – San Francisco Oakland Bay Bridge Implosions

California Transportation Commission December 6, 2017

slide-2
SLIDE 2

This is how i t started

SFOBB Pier E9 Following the 1989 Loma Prieta Earthquake

slide-3
SLIDE 3

Bay Area Faults and Major Roadways

slide-4
SLIDE 4

Earthquake Reports

slide-5
SLIDE 5

Innovation was the Direction Following the 1994 Northridge EQ

Brian Maroney, PE, Dr. Engr. Chief Bridge Engineer for the Toll Bridge Seismic Retrofit Program Deputy Toll Bridge Program Manager California Department

  • f

Transportation

slide-6
SLIDE 6
slide-7
SLIDE 7

Examples of Innovation in the Toll Bridge Program

The Toll

Bridge Program (from LP to NR earthquakes) AB144 TBPOC Weekly cabinet Meetings (environmental, design, construction, PM) Peer Review in Design & Construction (SFOBB East Spans, Dumbarton & Antioch) Pre-bid Contractor Technical Outreach Pre-bid fabricator audits Pre-bid engineering approval (YBI rollout-rollin, OTD SSD, Cantilever) Pier E3 Implosion Demonstration Project Pile Driving Demonstration Project Caged Fish Study Pile Driving Energy Attenuator and Demonstration Blast Attenuation System

             Probabilistic

Seismic Ground Motions (SFOBB

East Spans, Dumbarton, Antioch and now spreading)

Probabilistic Estimating High Performance Concrete (but not exotic) A706M Reinforcing Steel Large Diameter Battered Piles to control Seismic Motions Pile tip Acceptance Criteria Overlapping staged Construction Contracts Quarterly Reports to the Legislature Concept of Project & Program Contingency Pier 7 (“Campus Concept”) Group Environmental Resource Agency Meetings Contractor-Constructed proto-types and proof tests BRIM (bridge information Management Post-Future EQ User’s Manual Lane-by-Lane Deck Joint …and many many more.

              

7

slide-8
SLIDE 8

InYESovation Innovation Venn Diagram

Knowledge Work Supportive Environment This is where InYESovation happens

8

BHM-2016

slide-9
SLIDE 9

The Environment Was of Extreme Value to A ll Involved

slide-10
SLIDE 10

Cantilever

slide-11
SLIDE 11
slide-12
SLIDE 12

504' Spans Being Prepared fo r Lowering Without a Single Pile

slide-13
SLIDE 13

504 Truss

  • n

Two Barges

13

slide-14
SLIDE 14

504' Spans Original Construction

slide-15
SLIDE 15

288 Truss

  • n

Solid Piers

15

slide-16
SLIDE 16

288 Truss on 2 floating Barges

16

slide-17
SLIDE 17

288' Spans Original Construction

Temporary bent Work continues in cantilever beyond the temporary bent to reach the next pier

slide-18
SLIDE 18

≈235’ ≈224’ ≈215’ ≈215’ ≈224’ ≈235’

18

Pier E3

slide-19
SLIDE 19

Two General Types of Piers

Marine

Typical: E6 – E18 Timber Pile Supported Typical: E4 – E5 Concrete Caisson

Hollow Voids Pier Cap ~ Water Line Cell Wall Concrete Slab Concrete Pile Cap

~50’

~ Mud Line

Foundations Types

19

slide-20
SLIDE 20

Weekly Schedule Updates

20

slide-21
SLIDE 21

Weekly Schedule Updates

21

slide-22
SLIDE 22
  • Major Marine Piers (E3 – E18)

Successfully Removed

  • With

Environmental Responsibility

  • Under

Budget

  • Ahead
  • f

Schedule

22

slide-23
SLIDE 23

Blast Event Video

Piers E9 and E10 Blast Event

5

slide-24
SLIDE 24

1) Planning/Design Multi-Pier Implosion Video 2) Actual Multi-Pier Implosion Video

24

slide-25
SLIDE 25

E14, E15, E16 Blast Day Plan

slide-26
SLIDE 26
  • What About the Remaining Marine

Piers?

  • Piers E2 (YBI) and E19-E22 (OTD)

Under Consideration for Retention

– Increase focus on restoring public access to the Bay – Experience the new bridge – W ater access opportunities – Connect with history – Timeliness

26

slide-27
SLIDE 27

Stakeholder Coordination

9

slide-28
SLIDE 28

Thank you CTC and STA for your Leadership and Teamwork