DCPT The Danish Centre of Particle Therapy Information meeting - - PowerPoint PPT Presentation

▶
dcpt the danish centre of particle therapy
SMART_READER_LITE
LIVE PREVIEW

DCPT The Danish Centre of Particle Therapy Information meeting - - PowerPoint PPT Presentation

DCPT The Danish Centre of Particle Therapy Information meeting November 26, 2014 The Danish Centre of Particle Therapy Information meeting Agenda Welcome and introduction The project from a clinical view Information


slide-1
SLIDE 1

DCPT The Danish Centre of Particle Therapy

Information meeting – November 26, 2014

slide-2
SLIDE 2

The Danish Centre of Particle Therapy – Information meeting

Agenda

–

Welcome and introduction

–

The project from a clinical view

–

Information about the equipment tender

–

Information about the building tender

–

The prequalification round

–

Any other business

26-11-2014 DCPT - Information meeting - November 26, 2014 2

slide-3
SLIDE 3

The Danish Centre of Particle Therapy – Information meeting

The project from a clinical view - by professor, chief physician Cai Grau, Aarhus University/ Aarhus University Hospital

26-11-2014 DCPT - Information meeting - November 26, 2014 3

slide-4
SLIDE 4

The Danish Centre of Particle Therapy – Information meeting

Information about the equipment tender

–

General time schedule

–

Status as per today

–

Anticipated plan of activities

26-11-2014 DCPT - Information meeting - November 26, 2014 4

slide-5
SLIDE 5

Building: Time from contract to start of installation of equipment: 15 months Equipment: Time from contract to delivery

  • n the site and start of

installation: 20 months

26-11-2014 DCPT - Information meeting - November 26, 2014 5

slide-6
SLIDE 6

The Danish Centre of Particle Therapy – Information meeting

Information about the building tender

–

Time schedule for prequalification, dialogue and the tendering process

–

Expectations of:

– The dialogue process – The contractor – The advisors – The design phase – User involvement – Cooperation

26-11-2014 DCPT - Information meeting - November 26, 2014 6

slide-7
SLIDE 7

The Danish Centre of Particle Therapy – Information meeting

26-11-2014 DCPT - Information meeting - November 26, 2014 7

–

Time schedule for prequalification, dialogue and the tendering process

slide-8
SLIDE 8

The Danish Centre of Particle Therapy – Information meeting

What are we building?

– Site area approx. 5000 m2 (64m x 78m) – Floor area approx. 8000 m2 – Located in the south-west corner of The New University

Hospital (DNU)

– As an extension of the oncological research centre – Next to the existing oncological functions

– Overall economy approx. DKK 800 mill.

– construction economics approx. DKK 330 mill.

– First patient expected at the beginning of 2018

26-11-2014 DCPT - Information meeting - November 26, 2014 8

slide-9
SLIDE 9

The Danish Centre of Particle Therapy – Information meeting

Where are we building?

26-11-2014 DCPT - Information meeting - November 26, 2014 9

slide-10
SLIDE 10

The Danish Centre of Particle Therapy – Information meeting

26-11-2014 DCPT - Information meeting - November 26, 2014 10

slide-11
SLIDE 11

The Danish Centre of Particle Therapy – Information meeting

26-11-2014 DCPT - Information meeting - November 26, 2014 11

slide-12
SLIDE 12

The Danish Centre of Particle Therapy – Information meeting

26-11-2014 DCPT - Information meeting - November 26, 2014 12

slide-13
SLIDE 13

The Danish Centre of Particle Therapy – Information meeting

26-11-2014 DCPT - Information meeting - November 26, 2014 13

slide-14
SLIDE 14

The Danish Centre of Particle Therapy – Information meeting

Expectations for the dialogue process

–

The dialogue material will include (incomplete):

– BID (Building Information Document) from the equipment supplier – Functional requirements on the building – Room data programme with requirements on each room with

reference to size, function, content etc.

– Interfaces and requirements on proximity to other rooms in DCPT – Interfaces and requirements on proximity to other functions at DNU – Descriptions of patient cases and logistics flow – Technical requirements – General conditions – And other matters

26-11-2014 DCPT - Information meeting - November 26, 2014 14

slide-15
SLIDE 15

The Danish Centre of Particle Therapy – Information meeting

Expectations for the dialogue process

–

The turnkey contractor must challenge the technical requirements of BID so that it is optimised as much as possible with regard to:

– Radiation protection / optimisation / execution – Technical supplies – Construction schedule – Incentive schemes –

Suggestions of the turnkey contractor of how to solve critical issues from the room data programme to general discussions with users

–

Interfaces and risk areas

–

Constructability

–

The cooperation with the equipment supplier and the builder in general

–

Quality assurance

26-11-2014 DCPT - Information meeting - November 26, 2014 15

slide-16
SLIDE 16

The Danish Centre of Particle Therapy – Information meeting

Expectations for the turnkey contractor

–

Qualifications

– Competencies of management of complex building projects,

technically as well as timewise

– Competencies of cooperation with major external suppliers – Competencies of communication in other languages – primarily

English – and with people with different cultural backgrounds

– Extensive professional knowledge of execution of complex concrete

constructions

– Competencies of radiation protection – Experience of user involvement – The wish and the will to cooperation

26-11-2014 DCPT - Information meeting - November 26, 2014 16

slide-17
SLIDE 17

The Danish Centre of Particle Therapy – Information meeting

Expectations for the advisors

–

Qualifications

– Extensive professional knowledge and competencies of – Radiation protection – Complex concrete constructions – Complex technical installations – Building of hospitals – User involvement – Communication in other languages – primarily English – and with

people with different cultural backgrounds

– Necessary focus and capacity – Compliance with the stages and benchmarks of the project – The wish and the will to cooperation

26-11-2014 DCPT - Information meeting - November 26, 2014 17

slide-18
SLIDE 18

The Danish Centre of Particle Therapy – Information meeting

The prequalification round

– Formal requirements – Number of prequalified turnkey contractor teams – Submission of prequalification material – Announcement of selected prequalified turnkey contractor teams – Fee

26-11-2014 DCPT - Information meeting - November 26, 2014 18

slide-19
SLIDE 19

The Danish Centre of Particle Therapy – Information meeting

The prequalification round

–

Formal requirements

– Prequalification document on the internet as a help – The contract notice, item III.2.1)

  • Company name etc.
  • Presentation of turnkey contract team
  • Declaration regarding compliance of §45 and unsettled due debt

– The contract notice, item III.2.2)

  • Economic information - turnover, result before tax, equity and

solvency ratio in schematized form for the most recent 3 years, supplemented with the corresponding annual accounts

  • Statement from the management declaring no important

changes since the latest published accounts

26-11-2014 DCPT - Information meeting - November 26, 2014 19

slide-20
SLIDE 20

The Danish Centre of Particle Therapy – Information meeting

The prequalification round

–

Formal requirements

– The contract notice, III.2.3)

  • Project references from the latest 5 years from corresponding or

comparable projects with emphasis on radiation protection, concrete technology, building of hospitals, technically complex buildings etc. A maximum of 15 references in total and a minimum of 3 references from each member of the team

  • Danish companies must submit key figures
  • Information of technical capacity
  • Overall description of quality assurance system
  • Overall description of safety and health system

26-11-2014 DCPT - Information meeting - November 26, 2014 20

slide-21
SLIDE 21

The Danish Centre of Particle Therapy – Information meeting

The prequalification round

–

Number of prequalified turnkey contractor teams

  • A minimum number of 3 and a maximum number of 5 turnkey

contractor teams are anticipated to be selected on the basis of the

  • bjective criteria stated in III.2.2 and III.2.3

–

Submission of prequalification material

  • December 16, 2014, at 12.00 - 1 US

B stick as well as 1 original and 5 copies in ” hard copy” .

  • Announcement of selected prequalified turnkey contractor teams
  • n January 12, 2015
  • Sending out of dialogue material, January 21, 2015

–

Fee

  • Each prequalified turnkey contract team, which submits a

conditional tender will receive a fee corresponding to EUR 40.000,-

26-11-2014 DCPT - Information meeting - November 26, 2014 21

slide-22
SLIDE 22

The Danish Centre of Particle Therapy – Information meeting

–

Any other business

26-11-2014 DCPT - Information meeting - November 26, 2014 22