Pre-submittal Conference Jeff Ray, E.I.T.
Project Engineer, Plants and Major Projects
Dos Rios WRC Electrical System Improvements – Phase 2 Project
November 29, 2016
Dos Rios WRC Electrical System Improvements Phase 2 Project Jeff - - PowerPoint PPT Presentation
Dos Rios WRC Electrical System Improvements Phase 2 Project Jeff Ray, E.I.T. Project Engineer, Plants and Major Projects November 29, 2016 Pre-submittal Conference November 29, 2016 Introduction Sign attendance sheet Owner:
Project Engineer, Plants and Major Projects
November 29, 2016
November 29, 2016
Page 2
November 29, 2016
Page 3
November 29, 2016
Page 4
SAWS Board Award April 2017 Notification of Selected Firm February 2017 Interviews (if necessary) January 17, 2017 Proposals Due December 9, 2016 By 2:00 p.m. Answers Posted December 6, 2016 4:00 p.m. Questions Due December 5, 2016 By 4:00 p.m.
November 29, 2016
Page 5
project.
November 29, 2016
Page 6
November 29, 2016
Page 7
November 29, 2016
Page 8
– Acknowledgement of Security Procedures, Addendums, and Contract Terms and Conditions
– List and describe 3 relevant projects within last 7 years your firm served:
verified.
– Firm’s record of performance
November 29, 2016
Page 9
– Organizational chart identifying key personnel (including sub-consultants) with resumes – Additional skills, experience, and/or qualifications specific to your firm
– Detailed approach explaining how Respondent’s Project Management Team would execute and complete the services
November 29, 2016
Page 10
November 29, 2016
Page 11
November 29, 2016
Page 12
– Be very specific in responses and avoid “boiler plate” responses – Highlight areas that are unique to your firm – Contact the SMWB Program Specialist for assistance
– Ensure all items included and all documents signed
November 29, 2016
Page 13
November 29, 2016
Page 14
November 29, 2016
Page 15
November 29, 2016
Page 16
November 29, 2016
Page 17
November 29, 2016
Page 18
November 29, 2016
Page 19
November 29, 2016
Page 20
November 29, 2016
Page 21
Substation #1
13.2 KV / 480 V, 1,000 KVA 13.2 KV / 480 V, 1,000 KVA
Substation #2
November 29, 2016
Page 22
MCC-RS-2 MCC-RS-1
480 V, 1,000 A (NEMA 1 Enclosures)
November 29, 2016
Page 23
November 29, 2016
Page 24
November 29, 2016
Page 25
Project Engineer, Plants and Major Projects
November 29, 2016