Agenda Item 10 Elizabeth River Tunnels Project Construction Update HRTPO Board Presentation Daniel A. Norman, PE Assistant Construction Director Thursday, 19 March 15 ERT Project Schedule Construction Approximately 70% Complete


slide-1
SLIDE 1

HRTPO Board Presentation

Daniel A. Norman, PE Assistant Construction Director Thursday, 19 March 15

Elizabeth River Tunnels Project Construction Update

Agenda Item 10

slide-2
SLIDE 2

ERT Project Schedule

Segment_______________ Completion Date Refurbishment of Existing Downtown Tunnels • August 2016 New MLK Freeway Extension

  • December 2016

New Midtown Tunnel

  • December 2016

Refurbishment of Existing Midtown Tunnel

  • May 2018

Construction Approximately 70% Complete

slide-3
SLIDE 3

ERT Project Component 1:

Existing Tunnel Rehabilitation

slide-4
SLIDE 4

DTT Rehabilitation: Ceiling Removal

slide-5
SLIDE 5

DTT Rehabilitation: Barrier Repair

slide-6
SLIDE 6

DTT Rehabilitation:

Fire Protection & Ventilation Upgrades

I nstallation of fire protection board I nstallation of longitudinal ventilation system

slide-7
SLIDE 7

DTT-WB Lighting Before … and After

slide-8
SLIDE 8

ERT Project Component 2:

MLK Freeway Extension

slide-9
SLIDE 9

MLK Freeway Extension

London Blvd. I-264 MLK Extension High St.

Architectural Rendering

slide-10
SLIDE 10

MLK Extension: Pile Driving

slide-11
SLIDE 11

MLK Extension: Ped Bridge Cap Pour

slide-12
SLIDE 12

MLK Extension: Structural Steel Erection

slide-13
SLIDE 13

MLK Extension: Structural Steel Erection

slide-14
SLIDE 14

ERT Project Component 3:

New MTT Approaches

slide-15
SLIDE 15

New MTT: Portsmouth Approach

Aerial View

Existing MTT Approach New MTT Approach

slide-16
SLIDE 16

New MTT: Portsmouth Approach

Surface View

slide-17
SLIDE 17

New MTT: Norfolk Approach

Aerial View

Existing MTT Approach New MTT Approach

slide-18
SLIDE 18

New MTT: Norfolk Approach

Surface View

slide-19
SLIDE 19

ERT Project Component 4:

New Midtown Tunnel

slide-20
SLIDE 20

New MTT: Final Concept

  • Concrete shell, Immerse Tube Tunnel (ITT)
  • Westbound tube connecting Norfolk to Portsmouth
  • Two vehicular lanes and an egress corridor

Jet Fans Deluge System Promat Utility Corridor Egress Corridor

slide-21
SLIDE 21

New MTT: Plan & Profile

slide-22
SLIDE 22

New MTT: Tunnel Element Fabrication

(1 min. time lapse video)

slide-23
SLIDE 23

New MTT: Float Out of Litter 1

(1 min. time lapse video)

slide-24
SLIDE 24

New MTT: Element Tow Down

slide-25
SLIDE 25

New MTT: Elements Moored in Portsmouth

slide-26
SLIDE 26

New MTT: Screed Barge

slide-27
SLIDE 27

New MTT: Lay Barge

slide-28
SLIDE 28

New MTT: Portsmouth Slot

slide-29
SLIDE 29

New MTT: Immersion of Element in Slot

slide-30
SLIDE 30

New MTT: Immersion of Element in River

slide-31
SLIDE 31

New MTT – Elements 1-3 Walk Through

slide-32
SLIDE 32