Energy Efficiency & Sustainable Construction Act of 2008, EESCA - - PowerPoint PPT Presentation

energy efficiency sustainable construction act of 2008
SMART_READER_LITE
LIVE PREVIEW

Energy Efficiency & Sustainable Construction Act of 2008, EESCA - - PowerPoint PPT Presentation

Energy Efficiency & Sustainable Construction Act of 2008, EESCA aka Peach Points Program aka Peach Points Program Green Building Standards for the State of Georgia Green Building Standards for the State of Georgia The Bill Signed by


slide-1
SLIDE 1

Energy Efficiency & Sustainable Construction Act of 2008, EESCA aka “Peach Points Program” aka Peach Points Program

Green Building Standards for the State of Georgia Green Building Standards for the State of Georgia

slide-2
SLIDE 2

The Bill

Signed by Governor Perdue on May 6, 2008 “The General Assembly finds that the welfare of this state is enhanced by the promotion of effective energy and environmental standards for construction, rehabilitation, and maintenance of state‐funded facilities and that such standards in turn improve this state’s capacity to design, build and operate high‐performance buildings, contributing to economic growth, promoting job development, and increasing energy conservation.” Directed through the Department of Community Affairs with consultation from the Georgia State Finance and Investment Commission

slide-3
SLIDE 3

Forming the Standards

The Objectives

1 Optimize Energy Performance 1 Optimize Energy Performance 2 Increase demand for Georgia construction materials and products 3 Improve environmental quality from reduced pollutant discharge 4 Conserve energy and promote local renewable sources 5 Protect and restore the State’s natural resources 6 Reduce potable water consumption 7 Use life cycle cost analysis to determine a project’s environmental performance 8 Encourage obtaining Energy Star designation

slide-4
SLIDE 4

Background & Overview

Regulated Buildings

All new construction building projects exceeding 10,000 sq. ft. A renovation project that is more than 50% of the replacement value of the facility A change in occupancy Any roof replacement project exceeding 10,000 square feet A commercial interior tenant fit‐out project exceeding 10,000 square feet of leasable area where the state is intended to be the lessor of such property.

slide-5
SLIDE 5

Background & Overview

Exceptions

A major facility project shall not include a building regardless of size that does not have A major facility project shall not include a building, regardless of size, that does not have conditioned space A state owned building that is on the historical registry Any local, county, or municipal building (or K‐12)

slide-6
SLIDE 6

Background & Overview

Effective Date

Requirements apply to all major facilities Requirements apply to all major facilities projects entering into design agreements after

J l 1 2010 July 1, 2010

slide-7
SLIDE 7

Requirements Requirements

  • 1. Fundamental Commissioning
  • 2. 15% Water Use Reduction
  • 3. 10% Georgia Based Materials and Products

Incentives Incentives

  • 1. Enhanced Commissioning [10 points]
  • 2. Water Use Reduction of 25% or more [up to 20 points]

3 Georgia Based Materials and Products of 20% or more [up to 20 points]

  • 3. Georgia Based Materials and Products of 20% or more [up to 20 points]
  • 4. Energy Use Reduction shown through Energy Modeling [up to 50 points]
slide-8
SLIDE 8

Standards from the Bill Standards from the Bill

Senate Bill 130

Path 1: Minimum Requirements

Georgia Peach Standards Georgia Peach Green Building

Path 2: Incentive Program

Rating System Energy Efficiency & Sustainable Construction Act of 2008 Peach Points

slide-9
SLIDE 9

Georgia Peach Green Building Rating System

Total Point Certification Level

12 30 P i 12‐30 Points = 31‐50 Points = 51‐70 Points = 71‐100 Points =

slide-10
SLIDE 10

Commissioning

Requirements (p.2)

Fundamental Commissioning Fundamental Commissioning

Incentives (p 3) Incentives (p.3)

Additional Commissioning 10 Points for completion 10 Points for completion

slide-11
SLIDE 11

Commissioning

What Systems are Commissioned?

HVAC & R equipment and controls heat recovery Mechanical HVAC & R equipment and controls, heat recovery, renewable energy, lab systems, and test and balance Electrical Controls Lighting and daylighting controls and renewable energy Plumbing Systems Domestic hot water systems Others (not required): Building Envelope, Emergency Power, Potable Water Systems, Booster Pump Systems, Irrigation Systems

slide-12
SLIDE 12

Commissioning

The Steps {Fundamental}

1 Prepare Owner’s Project Requirements p j q 2 Prepare Basis of Design 3 Prepare Commissioning {Cx} Plan 4 Incorporate C req irements into Constr ction Doc ments 4 Incorporate Cx requirements into Construction Documents 5 Introduction and Task assignment meeting i.e. Cx Kickoff 6 Verification of Installation 7 Completion of start‐up test sheets 8 Functional performance tests and verification of TAB reports 9 Summary {Final} Commissioning Report y { } g p

slide-13
SLIDE 13

Commissioning

The Steps {Additional}

1 Conduct Cx design review prior to mid‐construction documents g p 2 Review contractor submittals applicable to systems being commissioned 3 Develop a systems manual for the commissioned systems 4 Verif that the req irements for training are completed 4 Verify that the requirements for training are completed

slide-14
SLIDE 14

Water Use Reduction

Requirement (p.10)

15% Water Use Reduction using the Energy Policy Act of 1992 as a baseline design case 15% Water Use Reduction using the Energy Policy Act of 1992 as a baseline design case

Incentive (p.11)

Water Use Reduction of 25% or more Water Use Reduction Water‐Use Reduction Percentage 15% 25% 35% 45% 55% 65% 75% 85% 95% 100% Points Earned Req. 2 4 6 8 10 12 14 16 20

slide-15
SLIDE 15

Water Use Reduction

What is the Baseline? (p.12)

Energy Policy Act of 1992 Requirements Energy Policy Act of 1992 Requirements

Fixture Flow Rate Water Closets 1.6 gal/flush Urinals 1.0 gal/flush Showerheads 2.5 gal/min. Faucets 2 5 gal/min Faucets 2.5 gal/min. Replacement Aerators 2.5 gal/min. Metering Faucets 0.25 gal/cycle

slide-16
SLIDE 16

Georgia Based Materials & Products

Requirement (p.10)

10% of All building materials & products must be Georgia Based 10% of All building materials & products must be Georgia Based

Incentive (p.11)

Georgia Based Material & Product use of 20% of more G i B d Georgia Based Materials 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Points Earned Req. 2 4 6 8 10 12 14 16 20

slide-17
SLIDE 17

Georgia Based Materials & Products

Defining Georgia Based (p.18)

  • 1. Harvested: agricultural products
  • 1. Harvested: agricultural products

OR

  • 2. Extracted: minerals

OR

  • 3. Manufactured: all milling, processing and production
slide-18
SLIDE 18

Energy Savings & LCCA

Recommendation (p.24)

Reduce Energy consumption by 30% such that life cycle cost analysis yields a payback of no Reduce Energy consumption by 30% such that life cycle cost analysis yields a payback of no more than 10 years.

Incentive Incentive (p.26)

All energy use reduction is awarded by points accordingly Energy Savings Percentage 0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50% Points Earned 5 10 15 20 25 30 35 40 45 50

slide-19
SLIDE 19

Energy Savings & LCCA

What does it mean?

Do Energy Modeling Do Energy Modeling. Energy Savings Percentage 0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50%+ Sh Si l P b k Show Simple Payback : 7 y or Less YES YES YES YES YES If simple payback is greater than 7 years: Then Show Life Cycle Cost Show Life Cycle Cost Analysis: 10 y or Less YES YES YES YES YES

slide-20
SLIDE 20

Energy Savings & LCCA

Energy Modeling

The use of computer based

LCCA

Used to assess the true cost p tools to simulate 1 full year of energy use.

  • f ownership.

Accounts for: A great tool for comparing energy saving techniques, Accounts for: Acquisition Operation systems, and design methods. Maintenance Disposal

slide-21
SLIDE 21

Energy Savings & LCCA

Finding the Simple Payback

Determining whether the increase initial cost of an improvement g p will payback within the given time frame [7 years] Simple Payback = Incremental First Year Cost First Year Annual Savings

slide-22
SLIDE 22
slide-23
SLIDE 23

What is What is

{SS} Sustainable Sites {WE} Water Efficiency {EA} Energy and Atmosphere {MR} Materials and Resources {EQ} Indoor Environmental Quality {RP} R i l P i it {RP} Regional Priority

slide-24
SLIDE 24

&

Correlation of GA PEACH Requirements/Incentives and Maximum Points Earned through LEED Credits through LEED Credits

LEED System Direct Indirect None New Construction 29 43 38 Core & Shell 31 34 44 Commercial Interiors 39 20 38 Existing Building O&M 31 31 50 Certified Silver Gold Platinum Existing Building O&M 31 31 50 40‐49 50‐59 60‐79 80+

slide-25
SLIDE 25

Hypothetical Peach Demonstration

Go Fish Georgia Center

Perry, GA Commissioning Completed 0 pts. Water Use Reduction Completed 59.9% {8 pts.} ate Use educt o Co p eted 59.9% {8 pts.} Georgia Based Materials Completed 27.6% {2 pts.} 35 Total Points O ll P j t R ti 2 P h Energy Savings & LCCA 26.33% {25 pts.} Overall Project Rating – 2 Peaches

slide-26
SLIDE 26
slide-27
SLIDE 27

Energy Ace University AIA/CES C i i Ed i P id AIA/CES Continuing Education Provider

What You Need To Know About Energy Modeling & Commissioning Georgia’s Energy & Efficiency Act of 2008 (EESCA) Workshop LEED & Green Globes: Two Green Building Rating Systems Energy Ace: LEED & Green Globes Office Tour as a Learning Tool An Introduction to the International Green Construction Code

Schedule a Lunch and Learn at Your Office!

An Introduction to the International Green Construction Code

slide-28
SLIDE 28

Thank You!

Wayne Robertson , leed ap

866.610.LEED wayner@energyace.com For More Information please visit:

www.energyace.com