FREIA Test Stand Status and Outlook Roger Ruber for the FREIA - - PowerPoint PPT Presentation
FREIA Test Stand Status and Outlook Roger Ruber for the FREIA - - PowerPoint PPT Presentation
FREIA Test Stand Status and Outlook Roger Ruber for the FREIA Laboratory Uppsala University ESS WP10 Internal Review 22 May 2014 What & Whom? Facility for Research Instrumentation and Accelerator Development State-of-the-art Equipment
What & Whom?
22-May-2014 WP10 Review - Roger Ruber - FREIA Status and Outlook 2
Facility for Research Instrumentation and Accelerator Development
cryogenics
- liquid helium
- liquid nitrogen
control room
- equipment controls
- data acquisition
RF power sources 3 bunkers with test stands horizontal cryostat vertical cryostat
Competent and motivated staff
collaboration with HEP & NP (IFA), solid-state electronics (Teknikum), Ångström workshop and TSL 28 Feb 2014
Funded by KAWS, Government, Uppsala Univ.
State-of-the-art Equipment
The New FREIA Laboratory
22-May-2014 WP10 Review - Roger Ruber - FREIA Status and Outlook 3 18 June 2013
Photos courtesy T. Thörnlund/UU
17 October 2013 15 October 2013 30 January 2014
Inaugurated 18 June 2013
25 Oct. 2013 19 February 2014
First Liquid Helium 14 March 2014
On-going Projects (UU-ESS Contract)
Frequency [MHz] Total # of cavities Total # of cryomodules 352.21 26 13
High-power Spoke Linac Testing
UU-ESS-IPNO-CERN Collaboration
- high power soak testing of
power source, controls, amplitude and phase stability with accelerating cavity
- test cavity tuning system, dynamic load,
electron emission and multipactoring
RF Source Development
UU-ESS-CERN-Industry Collaboration
- vacuum tube amplifier (Thales,
Electrosys)
- solid-state amplifier (Siemens)
- SSA module & combiner optimization
(NXP, ESRF)
22-May-2014 WP10 Review - Roger Ruber - FREIA Status and Outlook 4
ESS funding 2011 – 2015 spoke prototype
Future Projects (New UU-ESS Contract)
Spoke Linac Cryomodules (13#) UU-ESS-IPNO Collaboration
- continue prototype testing (2016)
- acceptance testing of spoke linac
cryostat with 2 cavities each
- requires high throughput and planning
(7-8 weeks per cryomodule)
Spoke Linac Valve Boxes (13#) UU-ESS-IPNO Collaboration
- valve box connecting cryomodule to the
cryogenic distribution line
- prototype testing
- series testing (tbc)
22-May-2014 WP10 Review - Roger Ruber - FREIA Status and Outlook 5
Contractual Time Line
ESS-UU contract 2011, updated 2013 (until end 2015) Discussion started on new contract ESS deliverables
- 30-Jun-2014: prototype cavity → delayed (~Dec-2014?) and LLRF
- 30-Jun-2015: prototype cryomodule and LLRF
UU deliverables
- 30-Jun-2014: test plan proposal
- 30-Jun-2015: cavity test report
- 31-Dec-2015: cryomodule test status report
- 30-Jun-2016: cryomodule test report (if contract extension)
→ UU might need to delay due to delayed cavity delivery
22-May-2014 WP10 Review - Roger Ruber - FREIA Status and Outlook 6
Spoke Cavity & Cryomodule
- IPN Orsay design
– single spoke – f0 = 352.21 MHz – Toper = ~2K
- Phase 1: Bare cavity test
– with antenna (and helium tank) – low power – verify Orsay measurement at FREIA
- Phase 2: Dressed cavity test
– with power coupler, tuners – full power – verify behaviour before ordering series
- Phase 3: Cryomodule & valve box test
– full power on both cavities – verify behaviour before ordering series
22-May-2014 WP10 Review - Roger Ruber - FREIA Status and Outlook 7
deformation
The Test Stand
- Three main subsystems needed
RF Power Source Cryostat Cryogenics Spoke Cavity (superconducting)
Courtesy of P. Duthil
Bunker To avoid radiation in public areas:
22-May-2014 WP10 Review - Roger Ruber - FREIA Status and Outlook 8
Test Stand Implementation (Phase 1)
22-May-2014 WP10 Review - Roger Ruber - FREIA Status and Outlook 9
SSA Power Station Tetrode Power Station Bunker
(Spoke Cryomodule)
Helium Cold Gas Heater HNOSS Horizontal Cryostat
Helium Liquefier
RF Transmitter
Tetrode based Commercial tender: Electrosys
- first prototype, ESS pre-series #1
- based on 2x TH-595, water+air cooled
- SSA pre-amplifier
Solid-state based Industry development: Siemens
- R&D towards alternative technology
- based on 4x 100 kW 19” racks
- vendor-specific combiners
– different design 1st and 2nd stage
22-May-2014 WP10 Review - Roger Ruber - FREIA Status and Outlook 10
Tetrode TH-595 Test Results
22-May-2014 WP10 Review - Roger Ruber - FREIA Status and Outlook 11
RF Distribution
Connecting
- 3x RF power station
– 2x tetrode – 1x SSA
- 3x cavity
– 1x in HNOSS – 2x in cryomodule (CM)
- 2 lines
– 1x coaxial line: SSA/tetrode to HNOSS/CM – 1x waveguide line: tetrode to CM
- use
– circulator w/o pressurization (prototyping) – ferrite and resistive loads (prototyping) – coaxial switch – directional couplers etc
22-May-2014 WP10 Review - Roger Ruber - FREIA Status and Outlook 12
Cryogenics
Cryogenic System Commercial tender: Linde
- Over 140 l/h at 4.5K (LN2 pre-cooling)
- 2000 l LHe dewar/buffer, 3+1 outlets
- 20 m3 LN2 tank
- 100 m3 gasbag + recovery system
- HNOSS connected in closed loop
22-May-2014 WP10 Review - Roger Ruber - FREIA Status and Outlook 13
HNOSS Horizontal Cryostat
HNOSS: Horizontal Nugget for Operation of Superconducting Systems Commercial tender: Cryo Diffusion Design: ACS
- Main Vacuum Vessel
– 3240 x ø1300mm inner volume – “beam” axis at 1600mm
- Valve box (on top of main vessel)
- Interconnection box (ICB)
– Distributes cryogens to HNOSS and CM
- Cryogenic transfer lines
– LN2 and LHe
- Gas heater for return GHe
– from 2K to 300K
- Control system
+ mock-up cavity for acceptance test
22-May-2014 WP10 Review - Roger Ruber - FREIA Status and Outlook 14
Bunker for Radiation Protection
22-May-2014 WP10 Review - Roger Ruber - FREIA Status and Outlook 15
Chicane:
- Waveguides
- Return GHe lines
Bunker interior
10 400 mm 4 800 mm 4 000 mm
Expected average < 1µSv/h outside the bunker
Controls and Monitoring
- LLRF
– developed by Lund University – based on DESY µTCA (special 500MHz module)
- Controls and Interlocks
– EPICS standard – using ESS control box – based on NI cRIO system
- Monitoring
– LabVIEW – based on NI hardware
- FPGA with FlexRIO ADCs (5772:12bit, 1.6Gs/s)
- PXI ADCs (5160: 10bit, 2.5Gs/s, 500MHz)
– help from NI engineers for code development
22-May-2014 WP10 Review - Roger Ruber - FREIA Status and Outlook 16
Auxiliary Systems
Vacuum
- sub-atmospheric pumps
- insulation vacuum cryostats
- “beam” vacuum cavities
Cooling
- Cooling
– RF power station – vacuum pumps – cryo compressors – power couplers (tbc)
22-May-2014 WP10 Review - Roger Ruber - FREIA Status and Outlook 17
Project Planning Time Line
22-May-2014 WP10 Review - Roger Ruber - FREIA Status and Outlook 18
2013 2014 2015 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Cavity bare X dressed X Cryomodule module X valve box X Controls LLRF X X RF transmitter tetrode O X SSA X distribution X X Cryogenics liquefier X 2K pumps O X Cryostat O X Controls controls X monitoring X
Status Overview
- Technical maturity
– overall delay in order of 3-6 months – prototype testing prepares us for series testing – based on proven technology
- Requirements and interfaces
– workshop on testing organized last Nov 2013, next one after Summer – discussion continuing, working on test proposal
- Outstanding procurement & developments
– valve box for cryomodule testing – RF distribution parts – vacuum pumps and mobile clean room
- Resources
– staff is limited which delays some work but working on new recruitment – excellent team with broad knowledge, well defined responsibilities – excellent collaboration with IPNO, ESS, CERN and DESY
22-May-2014 WP10 Review - Roger Ruber - FREIA Status and Outlook 19
Conclusions
22-May-2014 WP10 Review - Roger Ruber - FREIA Status and Outlook 20
- Status
– have delays, but we manage it – time might be short towards end of contract & ESS decision on order
- FREIA laboratory enables
– excellent test facilities for (spoke) cavities – development and test of cavities, controls and others...
- FREIA team is good on the way
to complete its tasks!
- We should agree on the new