Activity Progress Since February Meeting
- New roadway pavement opened in southeast quadrant February 14th
- Drilled shafts for Abutment #10 and Bent #9 east of UPRR completed
- Abutment #10 columns formed; concrete to be placed today
- Permanent driveways and side street transitions are complete
- Abutment #1, Bent #2 and Bent #3 drill shafts west of UPRR completed
- Completed cap for Abutment #1
- North footing of Bent #2 is complete and column work is in progress
- Retaining wall and embankment fill work continues west of UPRR
- Continued utility work in the center of Harrisburg Blvd.