Harrisburg Overpass Construction Update

March 7, 2016

slide-2
SLIDE 2

Activity Progress Since February Meeting

  • New roadway pavement opened in southeast quadrant February 14th
  • Drilled shafts for Abutment #10 and Bent #9 east of UPRR completed
  • Abutment #10 columns formed; concrete to be placed today
  • Permanent driveways and side street transitions are complete
  • Abutment #1, Bent #2 and Bent #3 drill shafts west of UPRR completed
  • Completed cap for Abutment #1
  • North footing of Bent #2 is complete and column work is in progress
  • Retaining wall and embankment fill work continues west of UPRR
  • Continued utility work in the center of Harrisburg Blvd.

2

slide-3
SLIDE 3

Road Closure of Harrisburg @ UPRR

3

  • Beginning: Sunday, March 13
  • Duration: 3 months
  • Local Access: Utilize u-turns at

UPRR to access local businesses

slide-4
SLIDE 4

Remaining Utility Work (Phase 3) East of Union Pacific Railroad

5

slide-5
SLIDE 5

Remaining Utility Work (Phase 3) West of Union Pacific Railroad

6

slide-6
SLIDE 6

6

West of Union Pacific Railroad

slide-7
SLIDE 7

West of Union Pacific Railroad

8

slide-8
SLIDE 8

8

East of Union Pacific Railroad

slide-9
SLIDE 9

East of Union Pacific Railroad

10

slide-10
SLIDE 10

30 Day Look Ahead

10

Closure of Harrisburg at UPRR (March 13) West of UPRR

  • Install temporary U-turns for local traffic
  • Complete footings and columns for Bents #2 and #3
  • Complete drill shafts for Bents #4 and #5
  • Continue constructing retaining walls

East of UPRR

  • Complete demolition of existing pavement and sub surface
  • Install temporary U-turns for local traffic
  • Continue with drilled shafts at Bents #8, #7 and #6
  • Work on footings and columns at Abutment #10, bents #9 and #8
  • Hughes Street Utility work in progress (waterline and storm)