SLIDE 49 Alternatives Matrix – Replacements
Existing Alignment (State Typ) Detour Existing Alignment (State Typ) Temp Bridge New Alignment (State Typ) Detour New Alignment (State Typ) Temp Bridge New Alignment (Town Typ) Detour New Alignment (Town Typ) Temp Bridge
Construction w/ CE and Contingencies
$4,253,600 $5,326,100 $4,407,000 $5,479,500 $5,132,400 $6,204,900
Preliminary Engineering
$818,000 $1,024,300 $847,500 $1,053,800 $987,000 $1,193,300
Right of Way
$30,000 $60,000 $30,000 $60,000 $30,000 $60,000
Total Cost
$5,101,600 $6,410,400 $5,284,500 $6,593,300 $6,149,400 $7,458,200
Local Share
$255,080 (5%) $641,040 (10%) $264,225 (5%) $659,330 (10%) $307,470 (5%) $745,820 (10%)
Design Life (years)
80 80 80 80 80 80
Typical
2-9-9-2 2-9-9-2 2-9-9-2 2-9-9-2 5-11-11-5 5-11-11-5
Project Development Duration
4 years 4 years 4 years 4 years 4 years 4 years
Construction Duration
12 months 24 months 12 months 24 months 12 months 24 months
Closure Duration
12 weeks None 12 weeks None 12 weeks None