HORNSEY TOWN HALL RENAISSANCE HORNSEY TOWN HALL CREATIVE TRUST HARINGEY COUNCIL SPEAKERS 1.0 Introduction by Paul Smith - Haringey Planning Authority 2.0 David Williamson - Haringey Council 3.0 Graeme Jennings - Hornsey Town Hall Creative
1.0 Introduction by Paul Smith - Haringey Planning Authority 2.0 David Williamson - Haringey Council 3.0 Graeme Jennings - Hornsey Town Hall Creative Trust 4.0 Fanos Panayides - John McAslan + Partners
SPEAKERS
COMMUNITY PARTNERSHIP
Haringey Council and the Hornsey Town Hall Creative Trust are work- ing closely together to bring their vision into a reality. Together, the Council and Trust have worked with John McAslan + Partners and Capita Symonds to develop an innovative solution that meets community needs
THE VISION
“A world-class model of civic renaissance, an arena for all that harnesses a spirit of progress, community, creativity and enterprise for future generations in Haringey, London and beyond.”
PROJECT AND APPROACH
PROJECT AND APPROACH
Income Receipts from
- development set Capital
budget for Town hall Works Appropriate Scale for
- Conservation Area and
setting of Listed buildings Appropriate materials,
- massing and Quality
Planning Constraints
- Client/Community
- Aspirations for mix of uses
Scope of heritage
- restoration required
Extent of refurbishment as
- community /cultural centre
TOWN HALL REBURBISHMENT Identify viable mix of
- uses in line with project
aspirations Identify scope and extent
- f uses required
Financially sustainability
- perating model with no
external subsidy BUSINESS PLAN
FACILITATING DEVELOPMENT
PROJECT AND APPROACH
HORNSEY TOWN HALL
FACILITATING DEVELOPMENT TOWN HALL REBURBISHMENT BUSINESS PLAN
CONTEXT APPRAISAL
HORNSEY TOWN HALL
Finsbury Park Underground King’s Cross and Euston Mainline
H A R I N G E Y
Central London St Paul’s Cathedral
5 M I L E S
CITY CONTEXT
5 m i n s w a l k 1 m i n s w a l k 1 5 m i n s w a l k 2 m i n s w a l k 2 5 m i n s w a l k Harringey Green Lanes South Tottenham Seven sisters Crouch Hill Finsbury Park Upper Holloway Harringey Hornsey Alexandra Palace Manor House Turnpike Lane Wood green Arsenal Archway Highgate
Hornsey Town Hall
Cinemas Theatres Music Comedy Libraries Art galleries
CULTURAL MAP
SITE APPRECIATION
CLINIC BROADWAY ANNEX HORNSEY LIBRARY MEWS T H E B R O A D W A Y HARINGEY PARK
HATHERLEY GARDENS
Weston Park
POOR QUALITY DERELICT BUILDING
SUN PATH
HORNSEY TOWN HALL
SITE APPRECIATION
CLINIC BROADWAY ANNEX HORNSEY LIBRARY MEWS T H E B R O A D W A Y HARINGEY PARK
HATHERLEY GARDENS
Weston Park
POOR QUALITY DERELICT BUILDING EXISTING SERVICE YARD OPPORTUNITIES FOR PUBLIC COURTYARD SPACE
SUN PATH
HORNSEY TOWN HALL
SITE APPRECIATION
CLINIC BROADWAY ANNEX HORNSEY LIBRARY MEWS T H E B R O A D W A Y HARINGEY PARK
HATHERLEY GARDENS
Weston Park
POOR QUALITY DERELICT BUILDING EXISTING SERVICE YARD OPPORTUNITIES FOR PUBLIC COURTYARD SPACE LACK OF ENGAGEMENT OF TOWN HALL WITH PUBLIC SPACE.
SUN PATH
HORNSEY TOWN HALL
SITE APPRECIATION
CLINIC BROADWAY ANNEX HORNSEY LIBRARY MEWS T H E B R O A D W A Y HARINGEY PARK
HATHERLEY GARDENS
Weston Park
POOR QUALITY DERELICT BUILDING EXISTING SERVICE YARD OPPORTUNITIES FOR PUBLIC COURTYARD SPACE LACK OF ENGAGEMENT OF TOWN HALL WITH PUBLIC SPACE. WELL PROPORTIONED PUBLIC AMENITY SPACE
SUN PATH
HORNSEY TOWN HALL
SITE APPRECIATION
CLINIC BROADWAY ANNEX HORNSEY LIBRARY MEWS T H E B R O A D W A Y HARINGEY PARK
HATHERLEY GARDENS
Weston Park
POOR QUALITY DERELICT BUILDING EXISTING SERVICE YARD OPPORTUNITIES FOR PUBLIC COURTYARD SPACE LACK OF ENGAGEMENT OF TOWN HALL WITH PUBLIC SPACE. WELL PROPORTIONED PUBLIC AMENITY SPACE ASSESS VEHICULAR TRAFFIC PATTERNS
SUN PATH
HORNSEY TOWN HALL
SITE APPRECIATION
CLINIC BROADWAY ANNEX HORNSEY LIBRARY MEWS T H E B R O A D W A Y HARINGEY PARK
HATHERLEY GARDENS
Weston Park
POOR QUALITY DERELICT BUILDING EXISTING SERVICE YARD OPPORTUNITIES FOR PUBLIC COURTYARD SPACE LACK OF ENGAGEMENT OF TOWN HALL WITH PUBLIC SPACE. WELL PROPORTIONED PUBLIC AMENITY SPACE ASSESS VEHICULAR TRAFFIC PATTERNS EXISTING COURTYARDS PROVIDE VALUABLE EXTERNAL SPACE
SUN PATH
HORNSEY TOWN HALL
SITE APPRECIATION
CLINIC BROADWAY ANNEX HORNSEY LIBRARY MEWS T H E B R O A D W A Y HARINGEY PARK
HATHERLEY GARDENS
Weston Park
POOR QUALITY DERELICT BUILDING EXISTING SERVICE YARD OPPORTUNITIES FOR PUBLIC COURTYARD SPACE LACK OF ENGAGEMENT OF TOWN HALL WITH PUBLIC SPACE. WELL PROPORTIONED PUBLIC AMENITY SPACE ASSESS VEHICULAR TRAFFIC PATTERNS EXISTING COURTYARDS PROVIDE VALUABLE EXTERNAL SPACE PRIME FRONTAGE FOR NEW FACILITATING DEVELOPMENT TO ENHANCE STREETSCAPE
SUN PATH
HORNSEY TOWN HALL
Maintain and enhance setting of
- Listed Building
Fundamentally improve visibility and
- connectivity of main entrance from
High Street Reinforce North-South pedestrian
- routes through site and permeability
Identify possibilities for new public
- realm and greater connectivity with
- ther areas of interest
Introduce common language of
- appropriate materials for the public
realm Promote extended programme of uses
- for arts activities in Public Square
Encourage enhancements to local and
- wider transport to improve access and
connectivity to local amenities Reinforce and compliment local
- character and townscape
DEVELOPMENT PRINCIPLES
BUILDING APPRAISAL
LOWER GROUND FLOOR PLAN
Supper Room East Wing
High Signifi cance Signifi cant Some Signifi cance Neutral with signifi cant elements Detrimental
BUILDING APPRAISAL
GROUND FLOOR PLAN
Assembly Hall Assembly Foyer West Wing East Wing Entrance Hall Rates Office Link Block
Green Room
Historic and Architectural Significance Drawings
FIRST FLOOR PLAN
Assembly Hall Committee Rooms West Wing East Wing 1st Floor Landing Council Chamber Link Block
Green Room
BUILDING APPRAISAL
High Signifi cance Signifi cant Some Signifi cance Neutral with signifi cant elements Detrimental
SECOND FLOOR PLAN
West Wing East Wing 2nd Floor Landing Link Block
Historic and Architectural Significance Drawings
ASSEMBLY HALL BLOCK COUNCIL CHAMBER BLOCK EAST BLOCK LINK BLOCK WEST BLOCK
BUILDING APPRAISAL
Building Organisation
TOWN HALL PROPOSALS
PERFOR- MANCE / EVENT SPACES CINEMA / FILM OFFICES / ENTERPRISE SUITES RESTAURANT / CAFE / BAR RETAIL COMMUNITY MEETING SPACES EDUCATION WORKSHOPS / STUDIOS RESIDENTIAL
Design Components
EXHIBITION
OPTIMISING BUSINESS PLAN
Usage Mix and Flexibility
ACCOMODATION TYPES RELATIVE AREAS FUTURE FLEXIBILITY
CINEMA / FILM CINEMA / FILM EXHIBITION PRIMARY EVENT SPACES EHHIBITION EHHIBITION RESIDENTIAL RESIDENTIAL CINEMA / FILM GROSS AREA GROSS AREA OFFICE / ENTERPRISE SUITES OFFICE / ENTERPRISE SUITES EDUCATION WORKSHOPS / STUDIOS EDUCATION WORKSHOPS / STUDIOS EDUCATION WORKSHOPS / STUDIOS COMMUNITY MEETING SPACES RESTAURANT / CAFE / BAR RESTAURANT / CAFE / BAR RESTAURANT / CAFE / BAR RETAIL RETAIL PRIMARY EVENT SPACES PRIMARY EVENT SPACES
ASSEMBLY HALL DRAMA, CONFERENCES, CLASSICAL, JAZZ, ROCK, SPORT, DANCE, CINEMA, COMMUNITY ACTIVITIES - FETE RESIDENTIAL WING SUPPER ROOM MULTI PURPOSE SPACE, YOUTH SERVICES, STUDIO EXHIBITION SPACES ART GALLERY, COMMUNITY EVENTS, JUMBLE SALES PUBLIC SQUARE OUTDOOR PERFORMANCE, VENTS, PUBLIC ART COMMITTEE ROOMS AND PERFORMANCE SUITE STUDIO THEATRE, FILM CLUB, REHEARSAL SPACE, DRAMA STUDIO ROOF TOP TERRACE OVERLOOKING SQUARE
FUNCTIONS
Adjacency and Distribution
ROOF TERRACE TO COMMITTEE ROOMS RESIDENTIAL EXTENSION TO EAST WING NEW OPENINGS FROM EVENT SPACE ONTO READING GARDEN BLACK BOX PERFORMANCE SPACE BALCONY TO ASSEMBLY HALL VERTICAL DIVISION OF THE ASSEMBLY HALL NEW GET-IN ARRANGEMENTS TO THEATRE NEW TERRACE TO CENTRAL COURTYARD NEW OPENINGS FROM CAFE ONTO SQUARE NEW OPENINGS FROM LOWER GROUND STUDIOS TO GARDEN COURTYARD
KEY ARCHITECTURAL MOVES
REPLACEMENT OF SPRUNG FLOOR RETRACTABLE RAKED SEATING RENEWED STAGE NEW SEPARATING WALL AND SOUND/LIGHT LOBBY NEW ABOVE STAGE TECHNICAL ZONE ACOUSTIC ISOLATION OF ROOF ACOUSTIC TREATMENT OF WINDOWS AND MEANS OF BLACK- OUT PERFORMANCE LIGHTING BRIDGES BLACK BOX PERFORMANCE SPACE BAR/FOYER AREA REPAIRED TIMBER PANELLING AND INTERNAL FINISHES FOYER TO FRONT SQUARE BAR/LOUNGE OVERLOOKING TOWN SQUARE
ASSEMBLY HALL
ROOF TOP TERRACE
NEW LIFT CORE PROVIDING DISABLED ACCESS BAR LOUNGE FUNCTION COMMITTEE ROOMS REINSTATED TO ORIGINAL SIZE REFURBISHED PANELLING TOILETS NEW ‘BLACK BOX’ PERFORMANCE SPACE NEW CONTROL BOX EXISTING STAIRCASE BAR / FOYER AREA NEW SOUND / LIGHT LOBBY AND ACCESS TO ASSEMBLY HALL ASSEMBLY HALL
COMMITTEE ROOMS AND PERFORMANCE SUITE
NEW ROOF LIGHT TO ‘BLACK BOX’ FOYER READING & EVENT GARDEN LIBRARY TERRACE AND READING STEPS POTENTIAL OPENING FROM REAR OF TO LIBRARY TO GARDEN NEW OPENING FROM EVENT & FUNCTION SPACE TO GARDEN RAMPED ACCESS TO GARDEN
NEW OPENING TO READING GARDEN
ACCESS TO ROOF TERRACE NEW LIFT ACCESS TO ALL LEVELS EXISTING LIFT ACCESS TO ALL LEVELS FOR RESIDENTIAL USE EXISTING LIFT ACCESS TO ALL LEVELS PRINCIPAL ENTRANCE LEVEL ACCESS AT LOWER GROUND FLOOR RAMPED ACCESS TO EVENT GARDEN
ACCESS STRATEGY
Fully accessible Building
- Introduction of sensitive interventions
- Refurbishment of existing heritage lifts
- New centralised lift in Assembly Hall Block
- serving all levels
Level access to courtyard spaces and surrounding
- site
FACILITATING DEVELOPMENT
Design Components
New build Block A New build Block B Broadway Annexe Mews HTH East Wing Hornsey Town Hall Substation Link Building
NEW BUILD MEWS BLOCKS
NEW BUILD RESIDENTIAL COMPRISING 4 NO. MEWS HOUSES 2 1/2 STOREYS RESIDENTIAL NSA 5,993 SQFT
NEW BUILD RESIDENTIAL BLOCK A
66 DWELLINGS ARRANGED OVER 5 STOREYS WITH UNDERCROFT AND BASEMENT PARKING NSA 51,045 SQFT
TOTAL RESIDENTIAL NSA 98,314 SQFT LINK BLOCK BUILDING
6 RESIDENTIAL DWELLINGS ARRANGED OVER 4 STOREYS NSA 4,433 SQFT
BROADWAY ANNEXE BUILDING WEST
CONVERSION AND EXTENSION TO ACCOMMODATE 8 RESIDENTIAL DWELLINGS AT FIRST AND SECOND FLOORS NSA 4,799 SQFT
HTH EAST WING
13 RESIDENTIAL DWELLINGS INCLUDING 2 ROOF EXTENSIONS ON THE 3RD FLOOR NSA 11,707 SQFT
NEW BUILD BLOCK B
26 DWELLINGS ARRANGED OVER 5 STOREYS NSA 20,336 SQFT
EXISTING BUILDINGS PROPOSED NEW BUILDINGS SITE AREA REFURBISHED EXISTING BUILDINGS SURROUNDING BUILDINGS
LANDSCAPE AND EXTERNAL WORKS
Site Plan
MASS AND SCALE
Site Section
BLOCK A BLOCK B TOWN HALL TOWN SQUARE
ELEVATIONAL TREATMENT
West Elevation
BLOCK A HARINGEY PARK
ELEVATIONAL TREATMENT
Haringey Park Elevation
HORNSEY LIBRARY BLOCK A HARINGEY PARK
ARCHITECTURAL LANGUAGE
Material Palette
ENVIRONMENTAL STRATEGY
Combined Heat & Power unit for clean and reduced
- carbon heat generation
Reduced water usage
- High performance glazing and wall insulation
- Cycle parking provision minimum 1 per dwelling
- Residential blocks located away from major street noise
- High efficiency low energy lighting
- Natural ventilation and light
- Waste and recycling facilities
LANDSCAPE AND EXTERNAL WORKS
Analysis
PRIMARY DESIRE LINES BUILDING ENTRANCES SECONDARY DESIRE LINES PEDESTRIAN ROUTES PEDESTRIAN SITE ENTRANCES BUILDING ENTRANCES SECONDARY PEDESTRIAN ROUTESMAIN
LANDSCAPE AND EXTERNAL WORKS
Site Plan
LANDSCAPE AND EXTERNAL WORKS
Precedent / Reference Images
LANDSCAPE AND EXTERNAL WORKS
Town Square
- 1. THE VILLAGE GREEN
- 2. THE TOWN SQUARE
- A. BUS STOP/SHELTER
- B. RAISED SEATING PLANTER
- C. RELOCATED FOUNTAIN
- D. KIOSK
- E. FEATURE PAVING BANDS
[EVENT SPACE]
- F. INFORMAL SEATING
- G. BIKE STANDS
- H. TEMPORARY PAVILIONS/STALLS
LANDSCAPE AND EXTERNAL WORKS
Flexibility
A FLEXIBLE SQUARE WITH MAJOR EVENTS ARRANGEMENT A FLEXIBLE SQUARE FOR TEMPOARY EVENTS & EVERYDAY USE
LANDSCAPE AND EXTERNAL WORKS
Market
LANDSCAPE AND EXTERNAL WORKS
Event / Screening
LANDSCAPE AND EXTERNAL WORKS
Town Square
LANDSCAPE AND EXTERNAL WORKS
Town Square
PHASING
Lower Ground Plan Ground Plan
PHASING
First Floor Plan Second Floor Plan
LAYOUTS
Lower Ground Plan Ground Plan
LAYOUTS
First Floor Plan Second Floor Plan
Proposals: Enabling Development £6m
New Build Block A 4 storeys New Build Hatherley Gdns 2.5 storeys
NEW BUILD RESIDENTIAL HATHERLEY GARDENS GEA 375sqm BLOCK A (4 STOREYS) GEA 3715sqm REFURBISHED FOR RESIDENTIAL HTH EAST WING (as existing) GEA 1606sqm BROADWAY ANNEX BUILDING REFURBISHED OFFICE (as existing) GEA 1384sqm
Proposals: Enabling Development £8m
New Build Block A 4 storeys New Build Hatherley Gdns 2.5 storeys
NEW BUILD RESIDENTIAL HATHERLEY GARDENS GEA 375sqm BLOCK A (4 STOREYS) GEA 6359sqm REFURBISHED FOR RESIDENTIAL HTH EAST WING(as existing) GEA 1606sqm BROADWAY ANNEX BUILDING REFURBISHED OFFICE (as existing) GEA 1384sqm
Proposals: Enabling Development £8m
New build Mews 1/2 storeys. Single storey roof extension Single storey roof extension Service pavillion
NEW BUILD MEWS BLOCKS 1/2 STOREYS GEA 520sqm NEW BUILD RESIDENTIAL BLOCK A (3/4 STOREYS) GEA 4970sqm HTH EAST WING REFURBISHED FOR RESIDENTIAL (as existing) GEA 1606sqm SINGLE STOREY ROOF EXTENSIONS GEA 320sqm NEW BUILD PAVILLION GEA 30sqm BROADWAY ANNEX BUILDING REFURBISHED OFFICE (as existing) GEA 900sqm SINGLE STOREY ROOF EXTENSION GEA 420sqm 1ST FLOOR RETAINED GEA 584sqm
New Build Block A 3 storeys New build Block A 3/4 storeys
Proposals: Enabling Development £8m
BROADWAY ANNEX BUILDING REFURBISHED OFFICE (as existing) GEA 1384sqm SINGLE STOREY ROOF EXTENSION GEA 420sqm NEW BUILD MEWS BLOCKS 1/2 STOREYS GEA 520sqm NEW BUILD PAVILLION GEA 30sqm
New Build Block A 4 storeys New build Mews 1/2 storeys. Single storey roof extension Service pavillion
NEW BUILD RESIDENTIAL BLOCK A (3/4 STOREYS) GEA 4970sqm BLOCK B (4 STOREYS) GEA 1840sqm
New build Block A 4 storeys New build Block B 4 storeys
Proposals: Enabling Development £8m
BROADWAY ANNEX BUILDING REFURBISHED OFFICE (as existing) GEA 1384sqm SINGLE STOREY ROOF EXTENSION GEA 420sqm NEW BUILD MEWS BLOCKS 1/2 STOREYS GEA 520sqm NEW BUILD PAVILLION GEA 30sqm
New build Block A 6 storeys New Build Block A 4 storeys New build Mews 1/2 storeys. Single storey roof extension Service pavillion
NEW BUILD RESIDENTIAL BLOCK A (4/6 STOREYS) GEA 6,935sqm
Proposals: Enabling Development £10m
New Build Block A 5/6 storeys New Build Block B 4 storeys New Build Hatherley Gdns 2.5 storeys
NEW BUILD RESIDENTIAL HATHERLEY GARDENS GEA 375sqm BLOCK A (4 STOREYS) GEA 7,250sqm BLOCK B (4 STOREYS) GEA 1,880sqm REFURBISHED FOR RESIDENTIAL HTH EAST WING(as existing) GEA 1606sqm BROADWAY ANNEX BUILDING REFURBISHED OFFICE (as existing) GEA 1384sqm
Proposals: Enabling Development £10m
BROADWAY ANNEX BUILDING REFURBISHED OFFICE (as existing) GEA 1384sqm SINGLE STOREY ROOF EXTENSION GEA 420sqm HTH EAST WING REFURBISHED FOR RESIDENTIAL (as existing) GEA 1606sqm SINGLE STOREY ROOF EXTENSIONS GEA 320sqm NEW BUILD MEWS BLOCKS 1/2 STOREYS GEA 520sqm NEW BUILD PAVILLION GEA 30sqm
New Build Block A 4 storeys New build Mews 1/2 storeys. New build Block B 4 storeys Single storey roof extension Single storey roof extension Service pavillion
NEW BUILD RESIDENTIAL BLOCK A (4/5 STOREYS) GEA 6335sqm BLOCK B (4 STOREYS) GEA 1840sqm
New build Block A 5 storeys
Proposals: Enabling Development £10m
BROADWAY ANNEX BUILDING REFURBISHED OFFICE (as existing) GEA 1384sqm SINGLE STOREY ROOF EXTENSION GEA 420sqm NEW BUILD MEWS BLOCKS 1/2 STOREYS GEA 520sqm NEW BUILD PAVILLION GEA 30sqm
New build Mews 1/2 storeys. New build Block B 4 storeys Single storey roof extension Service pavillion
NEW BUILD RESIDENTIAL BLOCK A (5/7 STOREYS) GEA 8,300sqm BLOCK B (4 STOREYS) GEA 1840sqm
New Build Block A 5 storeys New build Block A 7 storeys
Proposals: Enabling Development £10m
BROADWAY ANNEX BUILDING REFURBISHED OFFICE (as existing) GEA 1384sqm SINGLE STOREY ROOF EXTENSION GEA 420sqm HTH EAST WING REFURBISHED FOR RESIDENTIAL (as existing) GEA 1606sqm SINGLE STOREY ROOF EXTENSIONS GEA 320sqm NEW BUILD MEWS BLOCKS 1/2 STOREYS GEA 520sqm NEW BUILD PAVILLION GEA 30sqm
New build Mews 1/2 storeys. Single storey roof extension Single storey roof extension Service pavillion
NEW BUILD RESIDENTIAL BLOCK A (5/7 STOREYS) GEA 8300sqm
New Build Block A 5 storeys New build Block A 7 storeys
Proposals: Enabling Development Maximum Development Option
HTH EAST WING REFURBISHED FOR RESIDENTIAL (as existing) GEA 1606sqm SINGLE STOREY ROOF EXTENSIONS GEA 320sqm NEW BUILD MEWS BLOCKS 1/2 STOREYS GEA 520sqm NEW BUILD PAVILLION GEA 30sqm
New build Mews 1/2 storeys. New build Block B 4 storeys Single storey roof extension Single storey roof extension Service pavillion
BROADWAY ANNEX BUILDING REFURBISHED FOR RESIDENTIAL (as existing) GEA 1384sqm SINGLE STOREY ROOF EXTENSION GEA 420sqm NEW BUILD RESIDENTIAL BLOCK A (5/7 STOREYS) GEA 8,300sqm BLOCK A SUBSTATION SITE (4 STOREYS) GEA 800sqm BLOCK B (4 STOREYS) GEA 1840sqm
New Build Block A 5 storeys New build Block A 7 storeys
Proposals: Enabling Development £8.5m
BROADWAY ANNEX BUILDING REFURBISHED OFFICE (as existing) GEA 1384sqm SINGLE STOREY ROOF EXTENSION GEA 420sqm HTH EAST WING REFURBISHED FOR RESIDENTIAL (as existing) GEA 1606sqm SINGLE STOREY ROOF EXTENSIONS GEA 320sqm NEW BUILD MEWS BLOCKS 1/2 STOREYS GEA 520sqm NEW BUILD PAVILLION GEA 30sqm
New Build Block A 4 storeys New build Mews 1/2 storeys. New build Block B 4 storeys Single storey roof extension Service pavillion
NEW BUILD RESIDENTIAL BLOCK A (4/6 STOREYS) GEA 5,050sqm BLOCK A SUBSTATION SITE (4 STOREYS) GEA 960sqm BLOCK A (3/4 STOREYS) GEA 900sqm
Single storey roof extension New build Block A 6 storeys
Proposals: Enabling Development £9m
BROADWAY ANNEX BUILDING REFURBISHED OFFICE (as existing) GEA 1384sqm SINGLE STOREY ROOF EXTENSION GEA 420sqm HTH EAST WING REFURBISHED FOR RESIDENTIAL (as existing) GEA 1606sqm SINGLE STOREY ROOF EXTENSIONS GEA 320sqm NEW BUILD MEWS BLOCKS 1/2 STOREYS GEA 520sqm NEW BUILD PAVILLION GEA 30sqm
New build Mews 1/2 storeys. Single storey roof extension Service pavillion
NEW BUILD RESIDENTIAL BLOCK A (3/6 STOREYS) GEA 4,750sqm BLOCK A SUBSTATION SITE (4 STOREYS) GEA 720sqm BLOCK B (3/5 STOREYS) GEA 1,800sqm
New Build Block A 4 storeys New build Block B 4 storeys
COSTS
Project Costs / Budget
Sale of CAB Residential
Total
LBH Internal Costs "On-Costs" Construction Project Contingency
Total Phase I £480,000 £10,500,000 £ £10,980,000 £528,000 £2,383,991 £10,413,000 £1,000,000 £ £14,324,991
- £3,344,991
1 2 3 4 5 6
Phase II £475,200 £2,160,000 £ £2,635,200
- £2,635,200
7
Phase III £503,800 £2,290,000 £ £2,793,800
- £2,793,800
1 2 7
Notes: 1 - Receipts from sale of CAB site 2 - Figure provided by Haringey Council - Estimated adjustment to Knight Frank's 98k NSA 0% AH scheme to reflect current scheme showing 3.8% Affordable Housing - subject to further developers appraisal 3 - London Borough of Haringey internal costs provided by Haringey December 2009 4 - Professional fees, surveys and investigations agreed and forecast to end of project provided by Capita Symonds February 2010 5 - Phase 1 construction cost from Stage D Cost Estimate prepared by Capita Symonds February 2010 6 - Project contingency figure provided by Haringey February 2010 7 - Estimated on-costs @ 22% of Construction Cost
Capital Receipts Capital Expenditure Capital Funding Gap
COSTS
Construction Cost Summary All Phases
PHASE 1 PHASE 2 PHASE 3 Building Works 3,479,000 610,000 750,000 Services 3,792,000 600,000 300,000 External Works 308,000 350,000 600,000 Contractors Prelims & Profit 2,080,000 400,000 430,000 Construction Contingency 966,000 200,000 210,000 Inflation
- 212,000
0% excl TOTAL 10,413,000 * 2,160,000 * 2,290,000 * GIFA (m2) 3,945 732 308 £/m2 £2,640 £2,951 £7,435 PHASE 1 PHASE 2 PHASE 3
COST ESTIMATE SUMMARY
Building Works Services External Works Contractors Prelims & Profit Construction Contingency
COSTS
Phase 1 Construction Cost Summary
PHASE 1 Substructure 358,000 Superstructure 919,000 Internal Finishes 650,000 FF&E 981,000 Services 3,716,000 Annexe Building 337,000 Demolition 165,000 External Works 292,000 Diversions 10,000 Contractor's Preliminaries 1,337,000 Contractor's OH&P 701,000 Contingency 946,000 TOTAL 10,412,000 Exc VAT GIFA (m2) 3,945 £/m2 £2,639 Note: *All sums have been adjusted to include for BCIS TPI forcast to 4Q 2010. This represent a -2% on current day prices
COST ESTIMATE SUMMARY
£358,000 £919,000 £650,000 £981,000 £3,716,000 £165,000 £292,000 £1,337,000 £701,000 £946,000 £337,000 £10,000 Substructure Superstructure Internal Finishes FF&E Services Annexe Building Demolition External Works Diversions Contractor's Preliminaries Contractor's OH&P Contingency