HYDROGEN SULPHIDE REMOVAL FROM GEOTHERMAL POWER STATION COOLING - PowerPoint PPT Presentation
TUBULAR BIOREACTOR FOR HYDROGEN SULPHIDE REMOVAL FROM GEOTHERMAL POWER STATION COOLING WATER Rob Fullerton Beca Ltd, New Zealand Taupo North Island NZ Taupo Wairakei Wairakei Geothermal Power Station Wairakei one of earliest
TUBULAR BIOREACTOR FOR HYDROGEN SULPHIDE REMOVAL FROM GEOTHERMAL POWER STATION COOLING WATER Rob Fullerton – Beca Ltd, New Zealand
Taupo – North Island NZ Taupo Wairakei
Wairakei Geothermal Power Station • Wairakei – one of earliest geothermal power stations in the world • commissioned 1958 – 1963, installed capacity 192MW • current capacity 157MW
Cooling Water System ~17 m 3 /s Waikato River water for direct condenser cooling A Station B Station CW in CW out CW = Cooling water
Cooling Water System Geothermal steam 0.2m 3 /s Cooling water Steam Turbines + condensate Direct contact 17m 3 /s condensers 17.2m 3 /s Water pumps 157MW power Waikato River Waikato River
The Challenge H 2 S in the geothermal steam condenses into the cooling water and is discharged back to the river – aquatic impacts H 2 S concentration in discharge about 1000mg/m 3 (~1mg/L) Discharge Permit: H 2 S discharge to river ─ Prior 2012 : No consented limit - 10,000 kg/week ─ By 20 August 2012: 2,800 kg/week (72% reduction) ─ By 20 August 2016: 630 kg/week (94% reduction) Requires sulphide reduction to ~50 mg/m 3
The Challenge Geothermal steam containing H 2 S 0.2m 3 /s Cooling water Steam Turbines + condensate 17.2m 3 /s 1000ppb H 2 S Direct contact 17m 3 /s condensers To be reduced to 50ppb by Cooling water 2012 157MW power Waikato River Waikato River
Sulphide Oxidising Bacteria - A Solution? • Need for strategy to control sulphide recognised • Thinking started in 2000 • SOB naturally occurring – esp. in geothermal areas • Biological sulphide oxidation - conversion of H 2 S to sulphate • SOB biofilm observed on existing outfall structure • Cooling water from power station 30 - 35 o C, pH ~6, dissolved CO 2 • Could SOB be used to achieve 95% sulphide removal?
Initial Pilot Trials – 2000 - 2005 Algae overgrowth
Sheets – channels - Pipes
The Eureka Moment SOBs seem to grow best in fast moving flow
Pilot Testing – Initial pipe trials Sulphide sampling • Biofilm established on inside of pipe – good H 2 S removal • High velocity prevents excessive biomass build-up • Lack of light prevents algal growth • Pipe bioreactor proved in concept
Pilot Testing 2010 100mm dia. x 200m /150mm dia. X 400m
SOB Biofilm Beginning section 100m End section 200m
100mm dia. x 200m results
150mm dia. x 400m results
Sulphide Removal Model S = substrate concentration 𝑒𝑇 𝑒𝑢 = 𝜈 𝑛 𝐶 𝑇 µ m = maximum specific growth rate 𝑍 (𝐿 𝑡 + 𝑇) K s = half-saturation constant B = biomass concentration Y = biomass yield • Sulphide concentration is low B >> S • biofilm quasi-steady state with constant thickness, viz. growth = detachment 𝑒𝑇 𝑇 dS/dt = rate of substrate change 𝑒𝑢 = −𝑤 𝑛 v m = maximum substrate utilisation rate (𝐿 𝑡 + 𝑇) k s = half saturation constant • Calculate removal rate for each pipe segment (gH 2 S/m 2 /d) • Fit to non-linear least squares Monod model
Monod curve fitting K s = 235mg/m 3 v m = 13.85 gH 2 S/m 2 /d
Design Curve Minimum pipe length ~160m +25% safety factor = 200m
Pipe bioreactor - process concept 100mm dia. x 200m Outlet Velocity 0.8m/s sulphide Flow = 6.7L/s < 50ppb 100mm Sulphide oxidising bacteria biofilm Power station cooling water forms on pipe inside surface Inlet sulphide = 1000ppb
Full scale pipe bioreactor concept plant Flow = 17m 3 /s ~2000 pipes x 200m in parallel 390km of pipe !! 200 x pipes per layer 10 layers
Proposed sulphide treatment system 2012 Geothermal steam + H 2 S Pipe bioreactor 17.2m 3 /s Steam Turbines Direct contact condensers 17m 3 /s 4.2m3/s cooling 13m 3 /s 1000ppb water 50ppb H 2 S H 2 S 157MW power 2,800kg/week 17.2m 3 /s Waikato River Waikato River
Proposed sulphide treatment system 2016 Geothermal steam + H 2 S 13.2m 3 /s 1000ppb H 2 S Pipe bioreactor Steam Turbines Direct contact condensers 13m 3 /s <80ppb H 2 S Cooling water 630kg/week 120MW power Waikato River Waikato River
Full Scale design Challenges Design began January 2011 Never been done before – collaboration between contractor and designer Physical constraints – high groundwater + hot (60 o C) Power station can’t stop – build off-line Hydraulics – available head 1.5m – require pumping Energy efficiency – design low head system How to install 380km of 100mm dia. HDPE pipe
Innovative “over – under” syphon 100m Bioreactor pipe configuration ― 1890 pipes ― 5 banks of 378 pipes ― 42 pipes x 9 layers ― Magnetic flow meter each bank
Bioreactor Layout
Site Overview December 2011
Construction of pipe field PE Pipe Design ─ Extruded on site ─ 100m lengths ─ No joints ─ 2.5mm wall ─ Embedded into weak cement matrix – “ soilcrete ” ─ 378km in 5 months
Construction of pipe field
Construction of pipe field Soilcrete embedment made from local pumice sand
Construction of pipe field
Construction of pipe field Return chamber – end pipe field
Pump inlet channel
Bioreactor outlet channel
Bypass weir
Bioreactor Performance
Permit Compliance
Full scale performance H 2 S concentration meeting target of >80% (~50mg/m 3 ) Power station meeting sulphide mass emission limit of 2,800 kg H 2 S/week Optimisation of operating conditions to minimise power consumption Current performance gives confidence to meet 2016 discharge limit of 630 kg H 2 S/week
The world’s largest tubular bioreactor
Recommend
More recommend
Explore More Topics
Stay informed with curated content and fresh updates.