ISCO of TCE-Impacted Groundwater in Bedrock through an Enhanced - - PowerPoint PPT Presentation

isco of tce impacted groundwater in bedrock through an
SMART_READER_LITE
LIVE PREVIEW

ISCO of TCE-Impacted Groundwater in Bedrock through an Enhanced - - PowerPoint PPT Presentation

ISCO of TCE-Impacted Groundwater in Bedrock through an Enhanced Fracture Network Omer J. U Uppa ppal , , Bria ian B Blum, P , P.G., K ., Kyle yle W War arren, , Erica S a Sterzin inar ar, S , Stewar art A Abram ams, s, P P.E.


slide-1
SLIDE 1

ISCO of TCE-Impacted Groundwater in Bedrock through an Enhanced Fracture Network

Omer J. U Uppa ppal, , Bria ian B Blum, P , P.G., K ., Kyle yle W War arren, , Erica S a Sterzin inar ar, S , Stewar art A Abram ams, s, P P.E.

slide-2
SLIDE 2

PRESENTATION OUTLINE

  • Site Background
  • COCs, geology/hydrogeology, remedial objective

previous ISCO remedial actions/timeline

  • ISCO Implementation - 2011
  • Enhanced Fracture Network
  • Permanganate Injections
  • Post-Remediation Results
  • Next Steps
  • Technical Impracticability
slide-3
SLIDE 3

SITE BACKGROUND

  • 200-Acre Industrial R&D

Facility since the 1940s

  • Trichloroethene (TCE) plume

identified in the early 1980s

  • The plume occupies an area
  • f approximately 3 million

square feet.

  • ISRA triggered in 1996

Chatham, New Jersey U.S.G.S. Topographic Quadrangle

200 200-Acr cre S e Site w e withi hin the New ewar ark B k Basi sin` n`

slide-4
SLIDE 4 G:Data9\1734904\Cadd Data\Dwg\Powerpoint\Langan Env Wkshp\TCE Contours-Intermediate2.dwg

INTERMEDIATE ZONE TCE PLUME

SOURCE ZONE “B” SOURCE ZONE “A”

slide-5
SLIDE 5 This image cannot currently be displayed. G:Data9\1734904\Cadd Data\Dwg\Powerpoint\Langan Env Wkshp\TCE Contours-Int Oct 2003.dwg

SOURCE ZONE “B” SOURCE ZONE “A”

INTERMEDIATE ZONE TCE PLUME

slide-6
SLIDE 6

SITE GEOLOGY

  • Four stratigraphic units
  • Glacial Till
  • Saprolite
  • Columnar Basalt – Target Formation
  • Feltville Formation
  • Vertical faults and columnar nature
  • f joints likely facilitated vertical

migration of contaminants.

  • Poorly connected fractures form a

complex network with low hydraulic connectivity.

slide-7
SLIDE 7

SITE CONCEPTUAL MODEL

slide-8
SLIDE 8

PREVIOUS REMEDIAL ACTIVITIES

  • DNAPL Source Zone Pilot Tests
  • Implementation of SVE Pilot

Test – 2003

  • Implementation of ISCO Pilot

Test – 2003

  • Blast fracture trenches

installation – 2006

  • 51,024 gallons (31,320 lbs.) 2.5%

Potassium Permanganate & 10% Sodium Permanganate solution injected from 2003 to 2009

NOVEMBER 2005 JANUARY 2008

INTERMEDIATE ZONE TCE PLUME

slide-9
SLIDE 9

REMEDIAL ACTIVITIES

  • 9 Blast fracture trenches totaling

approximately 21,400 linear feet were installed onsite to facilitate chemical oxidant injections.

  • 327 blast and injection boreholes

SEPTEMBER 2011 JANUARY 2008

INTERMEDIATE ZONE TCE PLUME

slide-10
SLIDE 10

TRENCH CROSS SECTION

KMnO4/NaMnO4

slide-11
SLIDE 11

TRENCH LAYOUT

slide-12
SLIDE 12

ISCO INJECTION - 2011

  • Additional Injections

October through November 2011

  • The objective was to

mitigate the residual “source” of TCE groundwater plume with concentrations greater than 1,000 ppb.

INTERMEDIATE ZONE TCE PLUME

SEPTEMBER 2011

slide-13
SLIDE 13

ISCO INJECTION - 2011

  • 43,200 gallons (9,151 lbs.) 2.5%

Potassium Permanganate solution injected into 32 intermediate injection wells and 8 deep injection wells

  • Hydraulic fracturing
  • Injection pressures were up to

100 PSI.

slide-14
SLIDE 14

ISCO INJECTION - 2011

  • Techniques used to

facilitate oxidant delivery

  • Specially designed
  • xidant distribution

manifolds

  • High pressure

wellhead assemblies

  • Overnight gravity

feed injection scheme

slide-15
SLIDE 15

BEDROCK INJECTION STRATEGY

  • Six deep injection wells and 1

Intermediate injection well were hydro-fractured to facilitate chemical oxidant injections.

  • Overnight gravity feed to facilitate

improved injection rates.

  • The project scope was finished

several weeks ahead of schedule and under budget due to these aggressive injection strategies.

slide-16
SLIDE 16

HYDRAULIC FRACTURING

  • Fracturing of rock by a pressurized liquid
  • Increases connectivity of aquifer and well yield
  • Performed by Northeast Water Production, Inc.
  • Direct hydraulic connection was observed at several injection wells, as a

function of water level fluctuations, water table mounding in well casings, and limited daylighting (surfacing) following hydro-fracturing.

OVERBURDEN OVERBURDEN WEATHERED BEDROCK WEATHERED BEDROCK BASALT BASALT

slide-17
SLIDE 17

ISCO ACTIVITIES

TOTAL OF ALL ISCO ACTIVITIES Potassium Permanganate (lbs.) Sodium Permanganate (KMnO4 equiv. lbs.)1 10% Modified Fenton's Reagent (gallons) Pilot Test October 2003 to December 2003 4,320

  • Interim Remedial Measure

June 2006 to November 2007 5,870 18,480 1,270 DNAPL Entry Zone Oxidant Placement October 2007 1,600 200

  • Supplemental Injections

October to November 2009 850

  • Additional Injections

October to November 2011 9,150

  • Totals

21,790 18,680 1,270 GRAND TOTAL 40,470 pounds

slide-18
SLIDE 18

REMEDIAL ACTION RESULTS

INTERMEDIATE ZONE

slide-19
SLIDE 19

REMEDIAL ACTION RESULTS

DEEP 1 ZONE

slide-20
SLIDE 20

REMEDIAL ACTION RESULTS

slide-21
SLIDE 21
  • Reduction in size of groundwater plume
  • 71% reduction in intermediate bedrock zone
  • 21% reduction in deep 1 bedrock zone
  • Reduction in average TCE concentrations by

88%

  • Elimination of DNAPL Source Zones
  • Remaining plume TCE concentrations are

expected to decrease over time

REMEDIAL ACTION RESULTS

slide-22
SLIDE 22

TECHNICAL IMPRACTABILITY WAIVER

  • Groundwater contamination depth extends up to 585 feet bgs.
  • Fracture diameter, spacing, orientation, vertical extent, and

connectivity within and between formations cannot be accurately determined.

  • Dissolved TCE contamination has diffused into interstitial

spaces, dead-end fractures and solution voids along contaminated fracture flow paths.

  • Approximately 1.6 million square feet of the plume underlies a

developed residential area.

  • Limitations of subsurface remediation technologies
slide-23
SLIDE 23

ONGOING ACTIVITIES

  • Polishing Injection – August 2014
  • Injected 2,711 gallons of 5% sodium permanganate
  • 16 IW’s
  • Two rounds of post-injection sampling
  • Concentrations up to 30,000 ppb remaining in limited

areas approximately 100 feet into the bedrock

slide-24
SLIDE 24

ONGOING ACTIVITIES…

  • Planned Polishing

Injection

  • Scheduled for October 2014
  • Injection of 8,650 gallons of

5% sodium permanganate

  • 8 converted MW’s and 21

IW’s

  • Gravity feed injection
  • Post-injection sampling
slide-25
SLIDE 25

VIDEO

slide-26
SLIDE 26

QUESTIONS?

slide-27
SLIDE 27

THANK YOU