ISCO of TCE-Impacted Groundwater in Bedrock through an Enhanced - - PowerPoint PPT Presentation
ISCO of TCE-Impacted Groundwater in Bedrock through an Enhanced - - PowerPoint PPT Presentation
ISCO of TCE-Impacted Groundwater in Bedrock through an Enhanced Fracture Network Omer J. U Uppa ppal , , Bria ian B Blum, P , P.G., K ., Kyle yle W War arren, , Erica S a Sterzin inar ar, S , Stewar art A Abram ams, s, P P.E.
PRESENTATION OUTLINE
- Site Background
- COCs, geology/hydrogeology, remedial objective
previous ISCO remedial actions/timeline
- ISCO Implementation - 2011
- Enhanced Fracture Network
- Permanganate Injections
- Post-Remediation Results
- Next Steps
- Technical Impracticability
SITE BACKGROUND
- 200-Acre Industrial R&D
Facility since the 1940s
- Trichloroethene (TCE) plume
identified in the early 1980s
- The plume occupies an area
- f approximately 3 million
square feet.
- ISRA triggered in 1996
Chatham, New Jersey U.S.G.S. Topographic Quadrangle
200 200-Acr cre S e Site w e withi hin the New ewar ark B k Basi sin` n`
INTERMEDIATE ZONE TCE PLUME
SOURCE ZONE “B” SOURCE ZONE “A”
SOURCE ZONE “B” SOURCE ZONE “A”
INTERMEDIATE ZONE TCE PLUME
SITE GEOLOGY
- Four stratigraphic units
- Glacial Till
- Saprolite
- Columnar Basalt – Target Formation
- Feltville Formation
- Vertical faults and columnar nature
- f joints likely facilitated vertical
migration of contaminants.
- Poorly connected fractures form a
complex network with low hydraulic connectivity.
SITE CONCEPTUAL MODEL
PREVIOUS REMEDIAL ACTIVITIES
- DNAPL Source Zone Pilot Tests
- Implementation of SVE Pilot
Test – 2003
- Implementation of ISCO Pilot
Test – 2003
- Blast fracture trenches
installation – 2006
- 51,024 gallons (31,320 lbs.) 2.5%
Potassium Permanganate & 10% Sodium Permanganate solution injected from 2003 to 2009
NOVEMBER 2005 JANUARY 2008
INTERMEDIATE ZONE TCE PLUME
REMEDIAL ACTIVITIES
- 9 Blast fracture trenches totaling
approximately 21,400 linear feet were installed onsite to facilitate chemical oxidant injections.
- 327 blast and injection boreholes
SEPTEMBER 2011 JANUARY 2008
INTERMEDIATE ZONE TCE PLUME
TRENCH CROSS SECTION
KMnO4/NaMnO4
TRENCH LAYOUT
ISCO INJECTION - 2011
- Additional Injections
October through November 2011
- The objective was to
mitigate the residual “source” of TCE groundwater plume with concentrations greater than 1,000 ppb.
INTERMEDIATE ZONE TCE PLUME
SEPTEMBER 2011
ISCO INJECTION - 2011
- 43,200 gallons (9,151 lbs.) 2.5%
Potassium Permanganate solution injected into 32 intermediate injection wells and 8 deep injection wells
- Hydraulic fracturing
- Injection pressures were up to
100 PSI.
ISCO INJECTION - 2011
- Techniques used to
facilitate oxidant delivery
- Specially designed
- xidant distribution
manifolds
- High pressure
wellhead assemblies
- Overnight gravity
feed injection scheme
BEDROCK INJECTION STRATEGY
- Six deep injection wells and 1
Intermediate injection well were hydro-fractured to facilitate chemical oxidant injections.
- Overnight gravity feed to facilitate
improved injection rates.
- The project scope was finished
several weeks ahead of schedule and under budget due to these aggressive injection strategies.
HYDRAULIC FRACTURING
- Fracturing of rock by a pressurized liquid
- Increases connectivity of aquifer and well yield
- Performed by Northeast Water Production, Inc.
- Direct hydraulic connection was observed at several injection wells, as a
function of water level fluctuations, water table mounding in well casings, and limited daylighting (surfacing) following hydro-fracturing.
OVERBURDEN OVERBURDEN WEATHERED BEDROCK WEATHERED BEDROCK BASALT BASALT
ISCO ACTIVITIES
TOTAL OF ALL ISCO ACTIVITIES Potassium Permanganate (lbs.) Sodium Permanganate (KMnO4 equiv. lbs.)1 10% Modified Fenton's Reagent (gallons) Pilot Test October 2003 to December 2003 4,320
- Interim Remedial Measure
June 2006 to November 2007 5,870 18,480 1,270 DNAPL Entry Zone Oxidant Placement October 2007 1,600 200
- Supplemental Injections
October to November 2009 850
- Additional Injections
October to November 2011 9,150
- Totals
21,790 18,680 1,270 GRAND TOTAL 40,470 pounds
REMEDIAL ACTION RESULTS
INTERMEDIATE ZONE
REMEDIAL ACTION RESULTS
DEEP 1 ZONE
REMEDIAL ACTION RESULTS
- Reduction in size of groundwater plume
- 71% reduction in intermediate bedrock zone
- 21% reduction in deep 1 bedrock zone
- Reduction in average TCE concentrations by
88%
- Elimination of DNAPL Source Zones
- Remaining plume TCE concentrations are
expected to decrease over time
REMEDIAL ACTION RESULTS
TECHNICAL IMPRACTABILITY WAIVER
- Groundwater contamination depth extends up to 585 feet bgs.
- Fracture diameter, spacing, orientation, vertical extent, and
connectivity within and between formations cannot be accurately determined.
- Dissolved TCE contamination has diffused into interstitial
spaces, dead-end fractures and solution voids along contaminated fracture flow paths.
- Approximately 1.6 million square feet of the plume underlies a
developed residential area.
- Limitations of subsurface remediation technologies
ONGOING ACTIVITIES
- Polishing Injection – August 2014
- Injected 2,711 gallons of 5% sodium permanganate
- 16 IW’s
- Two rounds of post-injection sampling
- Concentrations up to 30,000 ppb remaining in limited
areas approximately 100 feet into the bedrock
ONGOING ACTIVITIES…
- Planned Polishing
Injection
- Scheduled for October 2014
- Injection of 8,650 gallons of
5% sodium permanganate
- 8 converted MW’s and 21
IW’s
- Gravity feed injection
- Post-injection sampling