JOINT CONVENTION ON THE SAFETY OF SPENT FUEL MANAGEMENT AND ON THE - - PowerPoint PPT Presentation

joint convention on the safety of spent fuel management
SMART_READER_LITE
LIVE PREVIEW

JOINT CONVENTION ON THE SAFETY OF SPENT FUEL MANAGEMENT AND ON THE - - PowerPoint PPT Presentation

JOINT CONVENTION ON THE SAFETY OF SPENT FUEL MANAGEMENT AND ON THE SAFETY OF RADIOACTIVE WASTE MANAGEMENT The United Kingdom of Great Britain and Northern Ireland NATIONAL REPORT PRESENTATION For the Second Review Meeting 15 th to 24 th May


slide-1
SLIDE 1

1

The United Kingdom of Great Britain and Northern Ireland NATIONAL REPORT PRESENTATION For the Second Review Meeting 15th to 24th May 2006, Vienna JOINT CONVENTION ON THE SAFETY OF SPENT FUEL MANAGEMENT AND ON THE SAFETY OF RADIOACTIVE WASTE MANAGEMENT

slide-2
SLIDE 2

2

JOINT CONVENTION ON THE SAFETY OF SPENT FUEL MANAGEMENT AND ON THE SAFETY OF RADIOACTIVE WASTE MANAGEMENT Presented by Dr Mike Weightman

HM Chief Inspector of Nuclear Installations, Health & Safety Executive

and

Dr Joe McHugh

Head of Radioactive Substances Regulation, Environment Agency

slide-3
SLIDE 3

3

Presentation Structure

  • Introduction
  • Overview of Radioactive Waste and

Spent Fuel Management in the UK

  • Major Developments since 2003
  • Questions and Comments
  • Summary
slide-4
SLIDE 4

4

The UK Report

  • Prepared from inputs of

Government Departments, Regulatory Bodies, and Industry

  • Explains how the UK

achieves and maintains a high level of safety and environmental protection in spent fuel and radioactive waste management

slide-5
SLIDE 5

5

Scope

Reprocessing

X Naturally

  • ccurring

radioactive material X Defence programme waste

slide-6
SLIDE 6

6

Basic Policy – Safety and Environment

UK Government’s basic policy is to ensure adequate statutory powers and other measures to protect people and the natural environment from harmful levels of radioactivity

slide-7
SLIDE 7

7

Basic Policy – Safety and Environment

  • Must meet LIMITS,

and

  • Reduce further in

line with: ALARP/BPEO/BPM

(Taking into account all relevant factors)

slide-8
SLIDE 8

8

Definition of Waste

  • It is the decision of the owner of any radioactive

material as to whether there is any foreseen use and hence whether it is radioactive waste

  • Regulatory control is the same under nuclear

licensing whether or not it is declared as waste – hence the type and level of regulatory control does not depend on such decisions by the owners

Radioactive Waste Management Policies

slide-9
SLIDE 9

9

Radioactive Waste Management Policies

Categorisation

  • VLLW

– Can be disposed of with ordinary refuse – <400kBq () in 0.1m3, <40kBq () per item

  • LLW

– not exceeding 4GBq/te () or 12 GBq/te ()

  • ILW

– Greater specific activity than LLW but no need to consider self heating

  • HLW

– Need to consider self heating

slide-10
SLIDE 10

10

Regulatory Bodies

  • Health & Safety Executive (HSE) / Nuclear

Installations Inspectorate (NII)

  • Environment Agency (EA) or Scottish

Environment Protection Agency (SEPA)

slide-11
SLIDE 11

11

Regulatory Bodies Safety Environment

slide-12
SLIDE 12

12

Northern Ireland Regulatory System

There are no nuclear installations in Northern Ireland Northern Ireland has its own regulatory system and bodies that parallel those in the rest of the UK

slide-13
SLIDE 13

13

Regulatory System

Nature of UK Regulatory Framework

  • Goal Setting

– Minimisation of risk so far as is reasonably practicable – ALARP / ALARA / BPEO / BPM

  • Emphasis in legislation

– Responsibilities and competence of Operators – Robust arrangements – Early, open and transparent engagement

slide-14
SLIDE 14

14

Regulatory System

Key Health and Safety Legislation

  • Health and Safety at Work Act

– And all implementing regulations made under it e.g. Ionising Radiation Regulations

  • Nuclear Installations Act

– Grant of Site Licence with 36 Licence Conditions

slide-15
SLIDE 15

15

Regulatory System

Key Environmental Legislation

  • Radioactive Substances Act 1993
  • Multi-media authorisation including limits and

conditions

  • Environment Protection Act 1990
  • e.g. waste management, contaminated land
slide-16
SLIDE 16

16

Regulatory System

Nuclear Site Licence HSE grant this under the Nuclear Installations Act, and can attach conditions:

  • In the interests of safety
  • With respect to handling, treatment

and disposal of nuclear matter Nuclear Site Licence applies to all people

  • n the site. The site licensee is responsible

for ensuring compliance

slide-17
SLIDE 17

17

Regulatory System

Licence Conditions Goal setting:

“Licensee must make and implement adequate arrangements” “Adequate arrangements” can be tailored to:

  • Suit business need
  • Suit the stage of operation – from

construction to decommissioning

Covers various aspects including radioactive waste management and decommissioning

slide-18
SLIDE 18

18

Regulatory System

Radioactive Substances Act

  • Environment Agency and
  • Scottish Environment Protection Agency
  • Details at:

www.environment-agency.gov.uk www.sepa.org.uk

slide-19
SLIDE 19

19

Regulatory System

Radioactive Substances Act

  • Prior authorisation needed for the discharge

and disposal of radioactive waste

  • Determining an application involves

appropriate consultation with stakeholders e.g. HSE, FSA, Local Authority, public

  • Reviewed periodically
  • Attach conditions to the authorisation
slide-20
SLIDE 20

20

UK Facilities - SELLAFIELD

slide-21
SLIDE 21

21

UK Facilities - SELLAFIELD

Reprocessing

Magnox THORP

slide-22
SLIDE 22

22

Magnox Encapsulation Plant

UK Facilities - SELLAFIELD

slide-23
SLIDE 23

23

UK Facilities MAGNOX STATIONS

slide-24
SLIDE 24

24

UK Facilities MAGNOX STATIONS

Magnox Stations

  • Hunterston A
  • Chapelcross
  • Calder Hall
  • Wylfa
  • Trawsfynydd
  • Berkeley
  • Oldbury
  • Hinkley Point A
  • Dungeness A
  • Bradwell
  • Sizewell A
slide-25
SLIDE 25

25

UK Facilities MAGNOX STATIONS

Magnox Stations DECOMMISSIONING Shut down and all fuel removed from site.

  • Hunterston A
  • Trawsfynydd
  • Berkeley
  • Bradwell
  • Hinkley Point A
slide-26
SLIDE 26

26

UK Facilities MAGNOX STATIONS

Magnox Stations SHUT DOWN Defuelling

  • Chapelcross
  • Calder Hall
slide-27
SLIDE 27

27

UK Facilities MAGNOX STATIONS

Magnox Stations OPERATING

  • Wylfa
  • Oldbury
  • Dungeness A
  • Sizewell A
slide-28
SLIDE 28

28

UK Facilities MAGNOX STATIONS

Spent Fuel Storage

  • Wet storage for at

least 90 days

  • Except Wylfa dry

storage

slide-29
SLIDE 29

29

UK Facilities MAGNOX STATIONS

Radioactive Waste Underground vaults Above ground vaults Reactor voids Tanks

slide-30
SLIDE 30

30

UK Facilities at AGR and PWR Stations

slide-31
SLIDE 31

31

AGR Stations PWR Station

  • Torness
  • Hunterston B
  • Hartlepool
  • Heysham I & II
  • Hinkley Point B
  • Dungeness B
  • Sizewell B

UK Facilities at AGR and PWR Stations

slide-32
SLIDE 32

32

UK Facilities at AGR and PWR Stations

AGR Stations PWR Station

Spent Fuel Storage

  • Wet storage for at

least 100 days

  • Long term storage in

ponds

slide-33
SLIDE 33

33

UK Facilities at AGR and PWR Stations

Radioactive Waste

Voids Wet waste storage tanks Desiccant storage Ion exchange resin storage tanks

slide-34
SLIDE 34

34

UK Facilities – UKAEA Sites

slide-35
SLIDE 35

35

UK Facilities – UKAEA Sites

Sites being decommissioned

  • Dounreay
  • Windscale
  • Harwell
  • Winfrith
slide-36
SLIDE 36

36

UK Facilities – UKAEA Sites

Spent Fuel Storage

  • Dounreay
  • Windscale
  • Harwell
slide-37
SLIDE 37

37

UK Facilities – UKAEA Sites

Radioactive Waste

Engineered Stores Vaults and Silos ILW liquid waste tanks Miscellaneous stores

slide-38
SLIDE 38

38

UK Facilities – GE Healthcare, Amersham

Amersham and Cardiff Sites Decay storage in stainless steel drums Harwell Site “Sea dump” type drums undergoing sorting and repacking

Radioactive Waste

slide-39
SLIDE 39

39

UK Decommissioned Sites

Decommissioned sites Research Reactors at: Scottish Universities Northern Universities ICI Billingham

slide-40
SLIDE 40

40

Inventory of Spent Fuel

10 20 30 40 50 60

Dounreay Windscale Harwell Winfrith

Tonnes

slide-41
SLIDE 41

41

Inventory of Spent Fuel

500 1000 1500 2000 2500 3000 3500 4000 4500 M agnox Stations M agnox AGR LW R Other Tonnes

Sellafield

slide-42
SLIDE 42

42

Inventory of Spent Fuel

AGRs – 2450 spent fuel elements at BE sites PWR – all fuel discharged since going critical in 1995 held on Sizewell B site

slide-43
SLIDE 43

43

Radioactive waste from all sources (2004 inventory)

661 190 164 19 816 14 5 240 10

200 400 600 800 1000 HLW ILW LLW Hundreds m3

Not yet conditioned Conditioned When all conditioned

Inventory of Radioactive Waste

slide-44
SLIDE 44

44

Inventory of Radioactive Waste

Expected volumes of conditioned waste to end of life

9 816 240 4 13 1600 20100 2420 20400

5000 10000 15000 20000 25000 HLW ILW LLW Hundreds m3

Stocks Arisings Total

slide-45
SLIDE 45

45

Inventory of Radioactive Waste

High Level Waste Inventory

  • Net reduction of 189m3 (12%) in liquid HLW

stocks from 2001 to 2004 inventories.

  • BNG Sellafield continues to meet the legal

requirement set for reduction of liquid HLW stocks

slide-46
SLIDE 46

46

Inventory of Radioactive Waste

Annual Disposals of LLW

5 10 15 20 25 30

1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003

Thousands m3

Supercompaction introduced

slide-47
SLIDE 47

47

MAJOR DEVELOPMENTS since 2003

  • Nuclear Decommissioning Authority
  • HSE Safety Assessment Principles
  • Committee on Radioactive Waste

Management

  • Waste Disposal
  • Nirex
slide-48
SLIDE 48

48

Nuclear Decommissioning Authority (NDA)

– A non-departmental public body reporting to the Department of Trade and Industry – set up in April 2005 to take strategic responsibility for the UK’s civil nuclear legacy

slide-49
SLIDE 49

49

Nuclear Decommissioning Authority (NDA)

Core objective is to ensure that the 20 nuclear sites within its area of responsibility are decommissioned and cleaned up – safely – securely – cost effectively and – in ways that protect the environment for this and future generations

slide-50
SLIDE 50

50

Nuclear Decommissioning Authority (NDA)

NDA role is to lead the development of a unified and coherent UK decommissioning strategy NDA’s first strategy was approved by UK Ministers on 31st March 2006

slide-51
SLIDE 51

51

Funded by a combination of: – direct Government funding; and – commercial income from:

  • electricity generation
  • reprocessing and storage of spent fuel
  • the manufacture of nuclear fuel

Budget is determined by the UK Government Funding determined for the current and following two years, and allocated on an annual basis

Nuclear Decommissioning Authority (NDA)

slide-52
SLIDE 52

52

Nuclear Decommissioning Authority (NDA)

The NDA ensures its strategic responsibilities are fulfilled through contracts for the management and operation of its sites These sites are regulated by the independent safety and environmental regulatory bodies (HSE, EA, SEPA)

slide-53
SLIDE 53

53

Nuclear Decommissioning Authority (NDA)

  • Berkeley PS & Labs
  • Bradwell
  • Calder Hall
  • Capenhurst
  • Chapelcross
  • Culham JET
  • Dounreay
  • Dungeness A
  • Harwell
  • Hinkley Point A
  • Hunterston A
  • Oldbury
  • Sellafield
  • Sizewell A
  • Springfields
  • Trawsfynydd
  • Windscale
  • Winfrith
  • Wylfa
  • LLW repository at

Drigg

slide-54
SLIDE 54

54

Nuclear Decommissioning Authority (NDA)

Site Licensee Company

Employees (including employees contributed by Parents)

NDA

Subcontractors perform the scope

  • f their Subcontracts

Parent Company(ies)

Regulators

Initial Contracting Structure

slide-55
SLIDE 55

55

Nuclear Decommissioning Authority (NDA)

Licensee has primary responsibility for safe

  • perations

however NDA is accountable for its own actions under general health and safety legislation and has a duty to secure safe decommissioning

slide-56
SLIDE 56

56

Nuclear Decommissioning Authority (NDA)

The NDA has duties under the HSWA74 :

  • for its employees (s2);
  • for persons other than its employees(s3);

and may be liable as an organisation commissioning work by a contractor (ss36&37) and interacting with the Nuclear Site Licensee

slide-57
SLIDE 57

57

NDA Strategy

Next 5 years

– create robust, costed and funded clean up plans – demonstrate real progress in reducing high hazards in legacy facilities – complete competitions for managing and operating nearly all sites – determine a better approach to interim Intermediate Level Waste (ILW) storage and Low Level Waste (LLW) disposal – review end states and timescales for all sites

slide-58
SLIDE 58

58

NDA Strategy

Within 25 years

  • aim to:

– achieve final site clearance at Harwell, Winfrith, Culham, Capenhurst, Springfields – accelerate decommissioning at Dounreay

  • aspire to:

– accelerate the decommissioning of Magnox reactors and achieve site clearance (subject to Government approving a business case and agreeing that this represents the best way forward)

slide-59
SLIDE 59

59

NDA Strategy

Within 75 years aim is:

– to decommission the plants and facilities at Sellafield – to have all the wastes placed safely under long term management arrangements

slide-60
SLIDE 60

60

NDA Strategy

Nuclear Skills

Key NDA initiatives are:

  • a Nuclear Skills Institute that will carry out world

class research and delivery of MSc courses

  • a National Nuclear Skills Academy that will

establish skills requirements nationally and deliver training local to the relevant NDA sites.

Waste Decommissioning Operations Nuclear Materials Competition &

slide-61
SLIDE 61

61

  • The revised SAPs are out for comment until

the end of May 2006 at www.hse.gov.uk/nuclear/saps

  • Views on the document would be welcome

HSE Safety Assessment Principles (SAPs)

slide-62
SLIDE 62

62

HSE Safety Assessment Principles (SAPs)

SAPs have been:

  • benchmarked against the most recent IAEA Safety

Standards that represent good practice

  • benchmarked against WENRA harmonisation work
  • expanded to better address the increased pace of

remediation and decommissioning activities

  • updated to be consistent with HSE’s thinking on

societal risk

slide-63
SLIDE 63

63

  • No fundamental shift in the numerical

targets

  • Some changes in detail
  • Targets are to assist HSE’s assessors

in making judgements HSE Safety Assessment Principles (SAPs)

slide-64
SLIDE 64

64

Dr J O McHugh

Head of Radioactive Substances Regulation, Environment Agency

slide-65
SLIDE 65

65

Committee on Radioactive Waste Management (CoRWM)

An independent committee appointed by the UK Government and the devolved administrations for Scotland, Wales and Northern Ireland.

– to recommend the best option for long-term management of higher-activity radioactive wastes – to do this in an open, transparent and inclusive way – to deliver its recommendations by July 2006

Future decisions and policies will be made by UK Government and devolved administrations

slide-66
SLIDE 66

66

Committee on Radioactive Waste Management (CoRWM)

CoRWM began its work in November 2003 and has carried it out in three broad phases:

– Phase 1: programme planning and early analysis – Phase 2: finalising assessment methodology (inventory, assessment criteria and shortlist of

  • ptions for detailed assessment)

– Phase 3: detailed assessment of shortlisted

  • ptions and reporting
slide-67
SLIDE 67

67

The options that CoRWM carried forward for detailed assessment were:

– long term interim storage – geological disposal – phased geological disposal (with a period of retrievability built in) – near surface disposal of decommissioning wastes (which are relatively short lived)

Committee on Radioactive Waste Management (CoRWM)

slide-68
SLIDE 68

68

Committee on Radioactive Waste Management (CoRWM)

CoRWM published its draft recommendations on 27 April 2006 (see www.corwm.org.uk) :

– geological disposal the best available approach – coupled with a safe and secure interim storage programme – siting of facilities based on early community involvement

Final round of public and stakeholder consultation prior to final recommendation July 2006

slide-69
SLIDE 69

69

Committee on Radioactive Waste Management (CoRWM)

Expert inputs to CoRWM’s work have included:

  • expert panels convened to support CoRWM’s option

assessment work

  • engagement with national scientific institutions e.g. the

Royal Society and the Geological Society

  • peer review and quality assurance groups
  • review and advice from a Government panel of experts
slide-70
SLIDE 70

70

CoRWM’s public and stakeholder engagement has involved:

  • citizens’ panels and stakeholder panels
  • citizen and stakeholder round tables
  • CoRWM’s Young People’s Programme
  • a National Stakeholder Forum
  • written and website consultations
  • a discussion guide for social networks/websites
  • implementation specialist workshops

Committee on Radioactive Waste Management (CoRWM)

slide-71
SLIDE 71

71

Next steps:

  • draft recommendations have been welcomed
  • Ministers await delivery of CoRWM’s final

recommendations in July 2006

  • UK Government and devolved administrations will

then decide future policy and its delivery in the light

  • f CoRWM’s final recommendations
  • announcement of the way forward will be made in

due course

Committee on Radioactive Waste Management (CoRWM)

slide-72
SLIDE 72

72

Waste Disposal

Very Low Level Wastes (VLLW)

– UK practice is to send it to landfill sites or for incineration – new landfill sites need approval by the planning authority – operation is subject to licensing by the environmental regulator

  • Landfill disposal of VLLW or incineration is

currently used mainly by hospitals, universities, etc.

slide-73
SLIDE 73

73

Waste Disposal

VLLW

  • The UK has commissioned a fresh review that

is due to report later this year (2006)

– will update earlier assessments – extend them to provide further assurances about VLLW disposals from the few nuclear sites using this disposal route

slide-74
SLIDE 74

74

Waste Disposal

LLW

  • LLW management discussed at two national

stakeholder workshops in 2005

  • Publication of a Government consultation

document on 28 February 2006

– including a statement of proposed future policy

  • LLW management policy statement will be

finalised in light of the consultation, due to close at the end of May 2006

slide-75
SLIDE 75

75

Low Level Waste Repository at Drigg

slide-76
SLIDE 76

76

Waste Disposal

Low Level Waste Repository at Drigg (LLWR)

  • The Environment Agency (EA) has reviewed

the Post-closure Safety Case for the LLWR

  • Taking into account the possible effects of

coastal erosion in the future, the EA has amended the conditions of the authorisation regarding solid waste disposal on the site

slide-77
SLIDE 77

77

Waste Disposal

Amended authorisation for LLWR at Drigg

  • Disposal in the current disposal area can

continue

  • EA will not authorise a new vault until BNGSL

can show that the potential future impacts from coastal erosion are minimised

  • EA will then review the remaining capacity of

the LLWR, and publish its findings

  • Details on EA website at

www.environment-agency.gov.uk

slide-78
SLIDE 78

78

Nirex

Originally set up in 1982 by the nuclear industry to provide it with waste disposal services Nirex’s programme for developing a deep repository was abandoned in 1997 The company continues to

– provide advice on standards for the conditioning and packaging of radioactive waste – compile the UK Radioactive Waste Inventory – serve as the main UK source of knowledge on underground disposal of waste

slide-79
SLIDE 79

79

Nirex

To ensure Nirex advice is independent of the nuclear industry, the company was taken into joint Defra/DTI ownership from 1 April 2005 A jointly owned shareholding company has been established for this purpose The long-term future of Nirex will be decided in light of CoRWM’s recommendations and policy decisions taken by Government in light of them

slide-80
SLIDE 80

80

ANSWERS TO QUESTIONS RECEIVED

slide-81
SLIDE 81

81

Remediation of Contaminated Land

  • Regulations are being drafted
  • Number of affected sites is uncertain – but

will initially not apply to licensed nuclear sites

  • The person who caused the contamination

will be responsible for remediation

– if they cannot be found the owner or occupier of the land will be responsible

  • The relevant environment agency will

regulate remediation

Contaminated Land

slide-82
SLIDE 82

82

Discharges

Progressive reduction of discharges

  • Discharges to sea and atmosphere have

been declining as a result of a range of improvements including:

– minimisation of the creation of radioactive waste – developments in abatement technology (eg Tc99) – closures of old plant (e.g. Magnox power station closure programme)

slide-83
SLIDE 83

83

Spent Sources

Orphan Spent Sources

  • New regulations (2005) require:

“The appropriate Agency shall be prepared or have made provision, including assignment of responsibilities, to recover any orphan source and shall have drawn up appropriate response plans and measures”

  • Government funding for recovery and

disposal of orphan and disused sources

slide-84
SLIDE 84

84

Spent Sources

Responsibility for spent sources The holder is responsible for any source until

– it is returned to the supplier or manufacturer – transferred to another holder – placed in a recognised installation

The Government has issued draft guidance

  • n acceptable ways in which holders can

make financial provision for disused sources

http: / / www.defra.gov.uk/ corporate/ consult/ ha ss-regs-directions/ hass-eaguidance.pdf

slide-85
SLIDE 85

85

Spent Sources

Disposal of Spent Sealed Sources

  • Recycling is encouraged where possible
  • Those meeting the LLW criteria can normally be

disposed of to the Low Level Waste Repository at Drigg

  • Higher activity sources are currently placed in storage

at Sellafield and will be managed in future as Intermediate Level Waste

  • The future long-term management of sources will be

considered as part of the ongoing policy reviews

slide-86
SLIDE 86

86

Spent Sources

Programme Cyclamen

  • Project to implement both fixed and mobile radiation

detection systems at UK points of entry

  • The ‘Cyclamen’ capability will screen all traffic types,

including

  • Containers
  • Airfreight
  • Vehicles
  • Passengers
  • Baggage and parcels
  • Some such systems are already operational at a

number of UK ports and airports

  • HM Revenue & Customs responsible for operation
slide-87
SLIDE 87

87

Substitution

Return of waste to overseas customers

  • ILW substitution covers the UK long-term

management of ILW from re-processed

  • verseas spent nuclear fuel and the return of

an additional, equivalent, amount of HLW

  • Returns of HLW from overseas reprocessing

contracts are scheduled to commence in 2008

slide-88
SLIDE 88

88

Dr M W Weightman

HM Chief Inspector of Nuclear Installations, Health and Safety Executive

slide-89
SLIDE 89

89

Safety Assessment

Periodic Safety Reviews

  • The requirement to undertake periodic reviews
  • f safety cases applies to all facilities on a

licensed site including radioactive waste management facilities

  • Periodic Safety Reviews (PSR) are currently

undertaken on a 10 year cycle

  • Expectations for these reviews are explained in

the document T/AST/050 www.hse.gov.uk/ foi/ internalops/ nsd/ tech _asst_guides/ tast050.pdf

slide-90
SLIDE 90

90

Safety Assessment

Aspects of a Periodic Review

– identify and address ageing processes that may limit the safe life of any items – review changes in relevant safety standards, analytical methodologies,inspection techniques etc and apply them as appropriate – validate relevant plant and process information and documentation – review operating experience

slide-91
SLIDE 91

91

Decommissioning

Distinction between operation and decommissioning

– A single licence covers the facility from the start of construction through to the end of decommissioning – From the viewpoint of licensing, there is no distinction between the different stages of the life of an installation – However different safety case / operating constraints / management arrangements

slide-92
SLIDE 92

92

Decommissioning

Decommissioning in Design Account should be taken of the need for

  • decommissioning. This should include:

– methods to prevent the spread of contamination – control of activation – design features to facilitate clean out and decommissioning – design features to reduce dose uptake by decommissioning workers

slide-93
SLIDE 93

93

Decommissioning

Decommissioning on non-licensed sites Safety is ensured through the same regulatory and management processes as during the operational phase. e.g.

– Special risk assessment is required under the Ionising Radiations Regulations 1999 – If new disposal routes are required e.g. for contaminated building rubble, then application must be made for a variation to disposal authorisation

slide-94
SLIDE 94

94

Regulators

Interface between EA/SEPA and HSE

  • Codified in Memoranda of Understanding

(MoUs). Website references in report

  • Objectives of the MoUs are to ensure that:

– activities of the regulators are consistent, coordinated and comprehensive – the possibility of conflicting requirements being placed on licensees is avoided – synergies are exploited – duplication of activity is minimised

slide-95
SLIDE 95

95

Regulators

Radiation Protection Regulators

– HSE in Great Britain and – HSE (NI) in Northern Ireland

  • Separate (but almost identical) legislation
  • Annual liaison committee between these two

bodies and the three environment agencies

– the Environment Agency – Scottish Environment Protection Agency – Environment and Heritage Service for Northern Ireland)

slide-96
SLIDE 96

96

Records

Requirements to maintain records

  • Obligations under licence:

– LC6 Documents records authorities – LC25 Operational records – LC35 Decommissioning

  • Expectations described in document

T/AST/024 “Management of Radioactive Materials and Radioactive Waste on Nuclear Licensed Sites”, on the HSE’s website www.hse.gov.uk

slide-97
SLIDE 97

97

Summary

The UK has made, and will continue to make, progress on many of the issues highlighted in the first review meeting: notably

slide-98
SLIDE 98

98

Summary

Policies and practices (Article 32)

The UK is nearing completion of the initial

stage of reviewing policy on the long-term management of radioactive waste, with the independent Committee (CoRWM) due to report in July 2006.

This was an open, transparent and

inclusive process that the UK will take forward in further policy development

slide-99
SLIDE 99

99

Summary

Policies and practices (Article 32)

The UK, through the NDA, now has a

national strategy for decommissioning approved by Government.

slide-100
SLIDE 100

100

Summary

Articles 21-24 (General Safety Provisions) Nuclear Skills

The UK is looking to establish

  • a Nuclear Skills Institute that will carry out

research and delivery of MSc courses

  • a National Nuclear Skills Academy that will

establish skills requirements nationally and deliver local training

slide-101
SLIDE 101

101

Summary

Safety of decommissioning (Article 26)

  • The creation of a the NDA with a specific remit to

deliver and finance the decommissioning of facilities operated by BNFL and UKAEA, was completed in 2005.

  • NDA is looking to accelerate decommissioning

where this is appropriate

  • NDA provides a UK wide strategic focus for

decommissioning

slide-102
SLIDE 102

102

Summary

Disused sealed sources (Article 28)

  • Government funding for recovery and

disposal of orphan and disused sources

  • Programme established for the safe reuse

and disposal of disused sources

slide-103
SLIDE 103

103

Summary

Progress in Decommissioning

Successful progress in:

  • safe shutdown, defuelling and

decommissioning of Magnox Power Reactor fleet.

  • decommissioning of UKAEA and
  • ther research sites.
  • decommissioning legacy plant at

Sellafield

slide-104
SLIDE 104

104

Summary

Progress in Radioactive Waste Management

Successful progress in:

  • putting Medium Active Concentrate into a

passive state while meeting targets for Tc99 discharges ahead of schedule.

  • reducing liquid HLW stocks through vitrification.
  • repackaging PCM to modern standards
  • treating active sodium from PFR
slide-105
SLIDE 105

105

The United Kingdom of Great Britain and Northern Ireland NATIONAL REPORT PRESENTATION For the Second Review Meeting 15th to 24th May 2006, Vienna JOINT CONVENTION ON THE SAFETY OF SPENT FUEL MANAGEMENT AND ON THE SAFETY OF RADIOACTIVE WASTE MANAGEMENT