Lost in Time:
the black hole between ESIA completion and project commencement
Presenter: Bryony Walmsley
Moderator: Bridget John
bridget@iaia.org
International Association for Impact Assessment www.iaia.org
Lost in Time: the black hole between ESIA completion and project - - PowerPoint PPT Presentation
Lost in Time: the black hole between ESIA completion and project commencement Presenter: Bryony Walmsley Moderator: Bridget John bridget@iaia.org International Association for Impact Assessment www.iaia.org IAIA Webinar Series 13 March:
Presenter: Bryony Walmsley
Moderator: Bridget John
bridget@iaia.org
International Association for Impact Assessment www.iaia.org
A Case Study
Social Impact Assessment
Visit http://www.iaia.org/webinars.php
Recording? Questions? Slides available?
Bryony Walmsley Southern African Institute for Environmental Assessment
southern Africa funded by various Development Finance Institutions (DFIs)
are integrated into ESIAs and ESMPs for Bank‐financed projects;
social, health and gender issues during project implementation;
mitigation measures on the ground;
initial screening to project completion
years
>12 years to completion
authority
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Project 1 Project 2 MR ? Project 3 Project 4 Project 5 Project 6 Project 7 MR ? 2012 2007 2019 2020 2008 2009 2010 2011 2013 2014 2015 2016 2017 2018
"Government will not tolerate a construction firm slowing down the entire plan. The contractor has two months to finish the job. Mangaka residents and Tanzanians in general need to start using the road for their economic activities," said the Minister of Works Transport and Communication. Tanzania Daily News, 18/07/16 “It (the Kazungula Bridge over the Zambezi River linking Botswana and Zambia) should have taken place a long time ago but I don’t know what is wrong with the people that we entrust with our government.” Truck Driver 07/11/17 “Contractor suspends construction of Nampula road - Cuamba due to lack of payment” Macua Blog 30/12/16 Project 2: 2y behind schedule Project 1: almost 3y behind schedule Project 7: 3y behind schedule
Categorisation Project appraisal Loan agreement Compliance audits Project completion report Pre‐ feasibility Project conception Feasibility Tenders Construction Operations Screening Scoping ESIA/ESMP ESMP implementation ESMP/EMS? Uncritical, promotes benefits Mitigation conflation EMP budgets changed Lack of critical evaluation
social track record Expenditure vs budget? Social/health KPIs and loan conditions? Monitoring of results? Effectiveness? Not on basis
sensitivity, vulnerability and risk Not on basis
sensitivity, vulnerability and risk? Inadequate id of dis‐ advantaged and Vulnerable Groups Inadequate description and IA of social, gender and health issues ESMP not included Who implements social and health measures? MoH? Env Auths? Labour? Developer? Who implements social and health measures? MoH? Env Auths? Labour? Developer?
TIME
change
inadequate
ESIA/ESMP!
Bank Client (private/govt) Resident Engineer (E&S monitor) Contractor ECO Social / community
Environmental authority
negative impacts or enhancing benefits
E&S safeguards?
meetings and reports
affected communities
conducted
and E&S) not assigned to projects
Bank Client (private/govt) Resident Engineer (E&S monitor) Contractor ECO Social / community
Environmental authority
project scope
to perform all necessary tasks
employed by the contractor
conditions e.g. TB, Hepatitis, as well as NCDs, pollution‐induced diseases, injuries, etc
health consequences e.g. dust, fumes, gas, noise, vibration, water pollution, soil contamination, etc
facilities and services in project areas
government
Inappropriate in rural Africa Way too late!
monitoring
social indicators
need to be more detailed so can account for expenditure against budget
mitigation and realisation of project benefits
social track records during procurement
within 3 years of approval, or if project scope changes
gender, social welfare, OHS, etc
impose penalties if necessary
(but it helps)
ESIA completion and the start of project construction
clearly specified operational procedures and guidelines
“There is no excuse for any company, lender or investor to claim to be unaware that their investments could impact human rights.”
Maplecroft, Amnesty International, 2002
Bryony Walmsley Southern African Institute for Environmental Assessment
Next webinar is 13 March: Overview of Proposed Canadian Impact Assessment Act
International Association for Impact Assessment www.iaia.org