May 20, 2019 How We Got Here Rectory Committee formed May 2016 - PowerPoint PPT Presentation
St. Anthony of Padua Parish May 20, 2019 How We Got Here Rectory Committee formed May 2016 Goal: Study the physical structure of the rectory to determine needs Going into this project, the committee had the plan to renovate because
St. Anthony of Padua Parish May 20, 2019
How We Got Here • Rectory Committee formed May 2016 • Goal: Study the physical structure of the rectory to determine needs • Going into this project, the committee had the plan to renovate because we felt we were starting with a good, solid structure
History of the Rectory • Built in 1951 • 3 rd rectory built for our parish • Previous rectory (2 nd rectory) was 66 years old when the current rectory was built • Modest repairs and renovations done over the years
Condition of the Rectory After a thorough examination of the rectory, the following issues were identified: • Roof – aged, worn- • HVAC out shingles & flat • Previous flooding in roof the basement • Single-pane windows • Asbestos • Ceiling, subfloor, & • Accessibility needs dry wall rot • 30+ year old • Original wiring furniture & decor • Original plumbing • Tuck-pointing and other exterior updates Virtual Tour of Rectory
Cost Comparison REMODEL EXISTING RECTORY NEW CONSTRUCTION 2916 SF 1 st FL, 2419 SF 2 nd FL, 2916 SF Basement, 3,384 SF Residence, 805 SF Church Support 275 SF Breezeway & Breezeway, 4,189 Basement Demo of interior finishes & $697,860 Demolition of existing $ 25,000 MEP’s to studs rectory & breezeway, Re-frame for ADA compliance asbestos abatement Install new MEP’s then finish out Remove flat roof & reframe $ 87,500 Rectory construction $575,280 with new trusses Replace existing windows $ 37,200 Church support $136,850 construction Asbestos abatement $ 20,000 Basement, concrete $ 94,584 ramp, etc. Install 3-stop elevator $110,000 Second floor storage $ 14,000 with stairs Furnishings $ 50,000 TOTAL $952,560 TOTAL $895,714
Decision to Build vs Renovate • Cost • Multi-story living space vs single story • 68 year old building • Size / Square Footage of new construction
Buildings & Maintenance Projects Asphalt Parking Lots 2019 $ 115,000 HVAC for Church 2020 $ 60,000 FOB Key System & 2020 $ 25,000 Security System for Church Total $ 200,000
Timeline • September 2017 Received approval from Diocesan Commission for Buildings & Property • 2018 Fr. Chuck gathered parish feedback • Fall 2018 Fr. Chuck & Construction Committee reviewed & finalized plans • 2019 Education & Campaign process – 65% of rectory construction cost must be “in hand” before construction can begin
Timeline (cont.) • January 2020 Move out of rectory – Relocating Fr. Chuck & Fr. Mark to Shumway – Moving furniture / items to parish center – Tossing items of no value • Jan – March 2020 Demolition • March 2020 Out for bid to contractors • April 2020 New construction begins 6-9 month construction process
We Ask For Your Help Please Pray For • Guidance of the Holy Spirit • The success of our campaign • The construction process • The safety of our workers
We Ask For Your Help We Need Volunteers • To be part of our campaign committee • To be willing to open your homes for Home Gatherings • To help us move out of the rectory • To help with the Treasure Sale in the spring
We Ask For Your Help Pledge A Gift To The Campaign • One-time gift • 3 year pledge • Encourage family and friends to participate
QUESTIONS?