May 20, 2019 This PowerPoint presentation was prepared by the - - PowerPoint PPT Presentation

may 20 2019 this powerpoint presentation was prepared by
SMART_READER_LITE
LIVE PREVIEW

May 20, 2019 This PowerPoint presentation was prepared by the - - PowerPoint PPT Presentation

Monthly Stakeholder Meeting May 20, 2019 This PowerPoint presentation was prepared by the Florida Department of Transportation (FDOT) staff and has been made available to the public as part of public records access. Any dissemination of this


slide-1
SLIDE 1

Monthly Stakeholder Meeting May 20, 2019

slide-2
SLIDE 2

2

This PowerPoint presentation was prepared by the Florida Department of Transportation (FDOT) staff and has been made available to the public as part of public records access. Any dissemination of this presentation by anyone or entity

  • ther than FDOT staff is not official. Any questions can be sent to FDOT-

D6PIO@dot.state.fl.us. This presentation may not be altered.

slide-3
SLIDE 3

3

CURRENT DESIGN STATUS

  • Roadway plans for I-95 north segment (segment 2A) complete
  • 90% roadway plans for SR 836 and I-395
  • Roadway plans for NE 13th Street complete
  • Phase I TCP plans complete for I-95, I-395 and SR-836
  • 60% signature bridge plans
  • TCP Generic plans and detour rouse complete

OVERALL DESIGN STATUS

  • Roadway - 75%
  • Structures – 40%
  • Maintenance of Traffic (MOT) – 45%

MAJOR DESIGN SUBMITTALS TO DATE:

slide-4
SLIDE 4

4

CONSTRUCTION MILESTONES

N Improve operations on NB I-95 by extending auxiliary lane Open Communal Areas under I-395/Complete Project

slide-5
SLIDE 5

* This schedule does not reflect days added to the contract for holidays, weather days or special events

5

  • Installation of new drainage (Phase 1 - completed)
  • Construction of foundations for new overhead sign structures This work will require

continuous weekend lane closures starting at 11 p.m. on Friday until 5:30 a.m. on Monday (Ongoing)

  • Construct median barrier wall (Ongoing)
  • Begin concrete pavement replacement (June)

UPCOMING CONSTRUCTION ACTIVITIES THREE MONTH LOOK AHEAD

slide-6
SLIDE 6

* This schedule does not reflect days added to the contract for holidays, weather days or special events

6

I-95 SIGN STRUCTURE DRILLED SHAFT OPERATIONS

slide-7
SLIDE 7

* This schedule does not reflect days added to the contract for holidays, weather days or special events

7

I-95 SIGN STRUCTURE DRILLED SHAFT OPERATIONS

slide-8
SLIDE 8

* This schedule does not reflect days added to the contract for holidays, weather days or special events

8

Preparations for foundation work on northbound I-95 bridge approaching ramp to I-195 (ongoing)

slide-9
SLIDE 9

* This schedule does not reflect days added to the contract for holidays, weather days or special events

9

Trestle Bridge Construction

slide-10
SLIDE 10

* This schedule does not reflect days added to the contract for holidays, weather days or special events

10

  • Nighttime eastbound lane closures for soil boring operations (Ongoing)
  • Installation of ITS devices for the Smart Workzone Management System (Ongoing)
  • Nighttime single and double lane closures on SR 836 (Ongoing)

UPCOMING CONSTRUCTION ACTIVITIES THREE MONTH LOOK AHEAD

slide-11
SLIDE 11

11

SR 836 PHASE 1

N

LEGEND

Median Work Zone

Eastbound and westbound SR 836 travel lanes have been shifted to the right and a work zone has been set up in the median

slide-12
SLIDE 12
  • Install temporary barrier wall from approximately NW 18 Avenue to west of the Miami

River to set up a work zone in the middle (mid-April)

12 TBW TBW Remove existing barrier wall

SR 836 PHASE 1 – STEP 1A

  • Temporary barrier wall (TBW) installed from east of the toll gantry to west of the Miami

River

  • Removal of existing median barrier wall for the first eight spans (Ongoing)
  • Nighttime closures of NW 17 Avenue will be implemented when there are demolition

activities overhead (May)

WESTBOUND SR 836 EASTBOUND SR 836

slide-13
SLIDE 13

* This schedule does not reflect days added to the contract for holidays, weather days or special events

13

SR 836 BARRIER WALL DEMOLITION

slide-14
SLIDE 14

14 TBW TBW Closure Pour

SR 836 PHASE 1 – STEP 1A

  • After median concrete barrier wall is removed the contractor will perform a concrete

closure pour to join the two bridges (May/June) WESTBOUND SR 836 EASTBOUND SR 836

slide-15
SLIDE 15

* This schedule does not reflect days added to the contract for holidays, weather days or special events

15

SR 836 CLOSURE POUR

slide-16
SLIDE 16

16

SR 836 PHASE 1 – STEP 1

Widening of SR 836 to the south to create future eastbound lanes Future widening for westbound SR 836

Shift eastbound SR 836 traffic to the median to begin widening to the south (June) WESTBOUND SR 836 EASTBOUND SR 836

slide-17
SLIDE 17

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

17

  • Utility relocations (Ongoing)
  • Widening activity on NE 13 Street between Biscayne Boulevard and NE 2 Avenue

(June/July)

  • Bridge foundation work for I-395 collector-distributor bridges (June/July)
  • Permanent closure of NE 12 Street between Biscayne Boulevard and NE 2 Avenue;

Traffic to be routed to NE 13 Street (July/August) UPCOMING CONSTRUCTION ACTIVITIES THREE MONTH LOOK AHEAD

slide-18
SLIDE 18

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

18

Bridge foundation work for westbound Signature Bridge (October)

UPCOMING CONSTRUCTION ACTIVITIES THREE MONTH LOOK AHEAD

slide-19
SLIDE 19

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

19

slide-20
SLIDE 20

MAINTENANCE OF TRAFFIC (MOT)/HOURS

I-395 SPECIFIC

Mainline Nightly Closures

  • 10 pm to 5:30 am Sunday thru Thursday
  • 1 am to 7 am Saturday and Sunday

SR 836 SPECIFIC

Mainline Nightly Closures

  • 8 pm to 5:30 am Sunday thru Thursday
  • 8:30 pm to 9 am Friday
  • 8:30 pm to 11 am Saturday

I-95 SPECIFIC

Mainline Nightly Closures

  • 9 pm to 5:30 am Sunday thru Thursday

RAMPS

  • 10 pm to 6:30 am Sunday thru Thursday​
  • 11 pm to 7 am Friday and Saturday​

SPECIAL NOTES:

  • Special events will be taken into account when scheduling closures
  • Hours noted above are for single lane closures, multi-lane closures will occur later
  • Weekend lane closures will be permitted on I-95 from 11 p.m. on Friday to 5:30 a.m. on Monday
  • The contract documents allows for weekend closures on certain ramps

20

slide-21
SLIDE 21
  • Provide drivers with real-time

travel information;

  • Encourage motorists to take

alternate routes;

  • Clear incidents more quickly,

thereby reducing secondary incidents; and

  • Make work zones safer for

highway workers and motorists. Smart Work Zone Management System (SWZMS) - The project will implement a SWZMS that will utilize Intelligent Transportation System (ITS) Devices such as traffic cameras, data collection devices and portable message signs to:

TRAFFIC MANAGEMENT SYSTEM

21

slide-22
SLIDE 22

22

COMMUNITY OUTREACH

PROJECT WEBSITE

  • www.i-395miami.com
  • Sign-up for project alerts/updates

Lane Closure information Upcoming construction activities Presentations

  • Calendar of events

OUTREACH OFFICE IN THE OVERTOWN COMMUNITY

  • 1035 NW 3 Avenue, Miami, Florida 33136

STAKEHOLDER MEETINGS

  • Ongoing individual stakeholder meetings and presentations
  • Next stakeholder meeting – May 20
slide-23
SLIDE 23

786-280-0983 OGonzalez@mrgmiami.com Contact: Oscar Gonzalez

www.i-395miami.com

THANK YOU!

23