SLIDE 3 3
CURRENT DESIGN STATUS
- Roadway plans for I-95 north segment (segment 2A) complete
- 90% roadway plans for SR 836 and I-395
- Roadway plans for NE 13th Street complete
- Phase I TCP plans complete for I-95, I-395 and SR-836
- 60% signature bridge plans
- TCP Generic plans and detour rouse complete
OVERALL DESIGN STATUS
- Roadway - 75%
- Structures – 40%
- Maintenance of Traffic (MOT) – 45%
MAJOR DESIGN SUBMITTALS TO DATE:
SLIDE 4
4
CONSTRUCTION MILESTONES
N Improve operations on NB I-95 by extending auxiliary lane Open Communal Areas under I-395/Complete Project
SLIDE 5 * This schedule does not reflect days added to the contract for holidays, weather days or special events
5
- Installation of new drainage (Phase 1 - completed)
- Construction of foundations for new overhead sign structures This work will require
continuous weekend lane closures starting at 11 p.m. on Friday until 5:30 a.m. on Monday (Ongoing)
- Construct median barrier wall (Ongoing)
- Begin concrete pavement replacement (June)
UPCOMING CONSTRUCTION ACTIVITIES THREE MONTH LOOK AHEAD
SLIDE 6
* This schedule does not reflect days added to the contract for holidays, weather days or special events
6
I-95 SIGN STRUCTURE DRILLED SHAFT OPERATIONS
SLIDE 7
* This schedule does not reflect days added to the contract for holidays, weather days or special events
7
I-95 SIGN STRUCTURE DRILLED SHAFT OPERATIONS
SLIDE 8
* This schedule does not reflect days added to the contract for holidays, weather days or special events
8
Preparations for foundation work on northbound I-95 bridge approaching ramp to I-195 (ongoing)
SLIDE 9
* This schedule does not reflect days added to the contract for holidays, weather days or special events
9
Trestle Bridge Construction
SLIDE 10 * This schedule does not reflect days added to the contract for holidays, weather days or special events
10
- Nighttime eastbound lane closures for soil boring operations (Ongoing)
- Installation of ITS devices for the Smart Workzone Management System (Ongoing)
- Nighttime single and double lane closures on SR 836 (Ongoing)
UPCOMING CONSTRUCTION ACTIVITIES THREE MONTH LOOK AHEAD
SLIDE 11
11
SR 836 PHASE 1
N
LEGEND
Median Work Zone
Eastbound and westbound SR 836 travel lanes have been shifted to the right and a work zone has been set up in the median
SLIDE 12
- Install temporary barrier wall from approximately NW 18 Avenue to west of the Miami
River to set up a work zone in the middle (mid-April)
12 TBW TBW Remove existing barrier wall
SR 836 PHASE 1 – STEP 1A
- Temporary barrier wall (TBW) installed from east of the toll gantry to west of the Miami
River
- Removal of existing median barrier wall for the first eight spans (Ongoing)
- Nighttime closures of NW 17 Avenue will be implemented when there are demolition
activities overhead (May)
WESTBOUND SR 836 EASTBOUND SR 836
SLIDE 13
* This schedule does not reflect days added to the contract for holidays, weather days or special events
13
SR 836 BARRIER WALL DEMOLITION
SLIDE 14 14 TBW TBW Closure Pour
SR 836 PHASE 1 – STEP 1A
- After median concrete barrier wall is removed the contractor will perform a concrete
closure pour to join the two bridges (May/June) WESTBOUND SR 836 EASTBOUND SR 836
SLIDE 15
* This schedule does not reflect days added to the contract for holidays, weather days or special events
15
SR 836 CLOSURE POUR
SLIDE 16
16
SR 836 PHASE 1 – STEP 1
Widening of SR 836 to the south to create future eastbound lanes Future widening for westbound SR 836
Shift eastbound SR 836 traffic to the median to begin widening to the south (June) WESTBOUND SR 836 EASTBOUND SR 836
SLIDE 17 SR 836 UPCOMING CONSTRUCTION ACTIVITIES
17
- Utility relocations (Ongoing)
- Widening activity on NE 13 Street between Biscayne Boulevard and NE 2 Avenue
(June/July)
- Bridge foundation work for I-395 collector-distributor bridges (June/July)
- Permanent closure of NE 12 Street between Biscayne Boulevard and NE 2 Avenue;
Traffic to be routed to NE 13 Street (July/August) UPCOMING CONSTRUCTION ACTIVITIES THREE MONTH LOOK AHEAD
SLIDE 18
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
18
Bridge foundation work for westbound Signature Bridge (October)
UPCOMING CONSTRUCTION ACTIVITIES THREE MONTH LOOK AHEAD
SLIDE 19
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
19
SLIDE 20 MAINTENANCE OF TRAFFIC (MOT)/HOURS
I-395 SPECIFIC
Mainline Nightly Closures
- 10 pm to 5:30 am Sunday thru Thursday
- 1 am to 7 am Saturday and Sunday
SR 836 SPECIFIC
Mainline Nightly Closures
- 8 pm to 5:30 am Sunday thru Thursday
- 8:30 pm to 9 am Friday
- 8:30 pm to 11 am Saturday
I-95 SPECIFIC
Mainline Nightly Closures
- 9 pm to 5:30 am Sunday thru Thursday
RAMPS
- 10 pm to 6:30 am Sunday thru Thursday
- 11 pm to 7 am Friday and Saturday
SPECIAL NOTES:
- Special events will be taken into account when scheduling closures
- Hours noted above are for single lane closures, multi-lane closures will occur later
- Weekend lane closures will be permitted on I-95 from 11 p.m. on Friday to 5:30 a.m. on Monday
- The contract documents allows for weekend closures on certain ramps
20
SLIDE 21
- Provide drivers with real-time
travel information;
- Encourage motorists to take
alternate routes;
- Clear incidents more quickly,
thereby reducing secondary incidents; and
- Make work zones safer for
highway workers and motorists. Smart Work Zone Management System (SWZMS) - The project will implement a SWZMS that will utilize Intelligent Transportation System (ITS) Devices such as traffic cameras, data collection devices and portable message signs to:
TRAFFIC MANAGEMENT SYSTEM
21
SLIDE 22 22
COMMUNITY OUTREACH
PROJECT WEBSITE
- www.i-395miami.com
- Sign-up for project alerts/updates
Lane Closure information Upcoming construction activities Presentations
OUTREACH OFFICE IN THE OVERTOWN COMMUNITY
- 1035 NW 3 Avenue, Miami, Florida 33136
STAKEHOLDER MEETINGS
- Ongoing individual stakeholder meetings and presentations
- Next stakeholder meeting – May 20
SLIDE 23
786-280-0983 OGonzalez@mrgmiami.com Contact: Oscar Gonzalez
www.i-395miami.com
THANK YOU!