Municipal Collection System &Wastewater Treatment Plant Town of Woodhull Agenda Introduction Project History & Project Status Project Review Construction Schedule & Overview Property Disturbance &


slide-1
SLIDE 1

Municipal Collection System &Wastewater Treatment Plant

Town of Woodhull

slide-2
SLIDE 2

Agenda

◼

Introduction

◼

Project History & Project Status

◼

Project Review

◼

Construction Schedule & Overview

◼

Property Disturbance & Restoration

◼

Wastewater Service & Connection

◼

Comments & Questions

slide-3
SLIDE 3

Introduction

Town of Woodhull

◼

Scott Grant, Town Supervisor

◼

Twig Terwilliger, Town of Woodhull

Hunt Engineers, Architects, Land Surveyors & Landscape Architects, DPC

◼

Christopher L. Wood, Project Manager

◼

Charles Franzese, Construction Administrator

◼

Aaron Vergason, Construction Manager/Inspector

◼

Rick Pope, King Consulting Engineers, Construction Inspector

Vacri Construction Corporation

◼

Matthew Thomas, Project Manager

◼

Andrew Breznay, Resident Superintendent

slide-4
SLIDE 4

Project History & Status

◼

2008 Board Conceptualized Project & Completed Feasibility Study

◼

2010 Submitted for Original Funding

◼

2012 Received Initial Funding Offer

◼

2012 Town Board Acceptance of Project

◼

2012 Sewer District Formation

◼

2013 Project Funding Obtained

❑

NYS Environmental Facilities Corporation

◼

2014 Original Engineering Design & Securing Easements

◼

2016-2017 Additional Funding Submitted & Secured

❑

NYS WQIA & CDBG

◼

2018 Updated Engineering Design/Bidding

◼

October 2018 Contract Awards

◼

April 2019 Start of Construction

slide-5
SLIDE 5

Service Area

slide-6
SLIDE 6

Construction Contracts

Multi-Prime Contracts for Project

◼

Contract #1A: General Construction Treatment Facility

❑

Contractor: Vacri Construction Corporation

◼

Contract #1B: Electrical Treatment Facility

❑

Contractor: M.W. Control Services, Inc

◼

Contract #1C: Mechanical/HVAC Treatment Facility

❑

Contractor: Kimble Inc.

◼

Contract #1D: Plumbing Treatment Facility

❑

Contractor: Kimble Inc.

◼

Contract #2: Municipal Collection System

❑

Contractor: Vacri Construction Corporation

slide-7
SLIDE 7

Construction Schedule & Operation

◼

Typical Hours of Operation

❑

8-10 hours per day, 5 days per week; 7:00 am to 3:30 pm

◼

April 2019 - Start of Construction

◼

May 2019 – August 2019 – Treatment Plant Construction

◼

April 2019 – November 2019 Collection System Construction

◼

August 2019 - Treatment Plant Commissioning/Operational

◼

August 2019 – November 2019 – Sewer Lateral Installation

◼

November 2019 – General Restoration

◼

December 2019 - March 2019 - Winter Shutdown

◼

April 2020 – Public Meeting (Restoration Concerns)

◼

April 2020 – June 2020 - Final Restoration

slide-8
SLIDE 8

Property Disturbance and Restoration

◼ Contractor shall work with landowner to clear path for

sewer lateral piping and septic tank decomissioning. Contractor to remove fencing, clear trees, etc. Fencing shall be reset

◼ Town, Contractor & Engineer understand the sensitivity

  • f construction on private property and its impact.

◼

A 20 ft. Construction Easement has been obtained

◼

Contractor shall complete activities within construction easement. If contractor needs to access areas outside of easement, owner will be contacted for approval.

◼

Contractor will not utilize private utilities

◼

Private Utilities will be protected if locations are known

slide-9
SLIDE 9

Property Disturbance and Restoration

◼ Contractor will complete general restoration of sewer laterals

as work is completed.

❑

General restoration shall consist of backfilling trench, and general grading to allow property owner to access all areas of yard.

◼ Contractor shall re-enter private parcels to complete

restoration and “punch list” items after natural settlement has

  • ccurred and to place final seed, mulch and/or plant

shrubbery/trees as part of project.

slide-10
SLIDE 10

Property Disturbance and Restoration

◼ Town has developed a protocol to address construction

related issues if they should arise.

◼

Submit concern via email

◼

WoodhullSewer@gmail.com

◼

Contact Construction Manager/Inspector

◼

Aaron Vergason, HUNT-EAS: (607) 481-3937

◼

Rick Pope, King Consulting Engineers: (716) 800-9721

◼

Visit/Call Town Hall, to add concern to project log book

◼ It is Important that your concerns/issues are brought to our

attention immediately not after construction is complete.

◼ It should be noted that the entire route will be videotaped

before and after construction to document site conditions

◼ Prior to closeout of construction the Town will conduct a

Public Meeting to confirm all concerns have been addressed.