NIUMINCO GROUP LIMITED ANNUAL GENERAL MEETING 30 NOVEMBER 2015 Important Information This presentation is not a prospectus nor an offer of securities for subscription or sale in any jurisdiction nor a securities recommendation. The information


slide-1
SLIDE 1

NIUMINCO GROUP LIMITED

ANNUAL GENERAL MEETING 30 NOVEMBER 2015

slide-2
SLIDE 2

Important Information

This presentation is not a prospectus nor an offer of securities for subscription or sale in any jurisdiction nor a securities recommendation. The information in this presentation is an overview and does not contain all information necessary for investment decisions. In making investment decisions, investors should rely on their own examination of Niuminco Group Limited and consult with their own legal, tax, business and/or financial advisers in connection with any acquisition of securities. The information contained in this presentation has been prepared in good faith by Niuminco Group Limited. However, no representation or warranty, express or implied, is made as to the completeness or adequacy of any statements, estimates, opinions or other information contained in this presentation. To the maximum extent permitted by law, Niuminco Group Limited, its directors, officers, employees and agents disclaim liability for any loss

  • r damage which may be suffered by any person through the use of, or reliance on, anything contained in or omitted from this presentation.

Certain information in this presentation refers to the intentions of Niuminco Group Limited, but these are not intended to be forecasts, forward looking statements, or statements about future matters for the purposes of the Corporations Act (Cth, Australia) or any other applicable law. The occurrence of events in the future are subject to risks, uncertainties and other factors that may cause Niuminco Group Limited’s actual results, performance or achievements to differ from those referred to in this presentation to occur as contemplated. The presentation contains only a synopsis of more detailed information to be published in relation to the matters described in this document and accordingly no reliance may be placed for any purpose whatsoever on the sufficiency or completeness of such information and to do so could potentially expose you to a significant risk of losing all of the property invested by you or incurring by you of additional liability. Recipients of this presentation should conduct their own investigation, evaluation and analysis of the business, data and property described in this document. In particular, any estimates or projections or opinions contained herein necessarily involve significant elements of subjective judgment, analysis and assumptions and you should satisfy yourself in relation to such matters. The information in this report that relates to exploration results is based on Information reviewed by Ian Plimer (BSc [Hons], PhD) who is a Fellow of the Australasian Institute of Mining and Metallurgy. Professor Plimer is a director of Niuminco Group Limited and has sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the activity he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore

  • Reserves. He consents to the inclusion in the report of the matters based on this information in the form and context in which it appears.
slide-3
SLIDE 3

CORPORATE OVERVIEW

Board of Directors:

  • Prof. Ian Plimer – Independent Chairman

Tracey Lake – Managing Director Matthew Roberts – Independent Director Neill Arthur – Independent Director Capital Structure: ASX Code: NIU POMSoX Code: NIU Website: www.niuminco.com.au Shares on issue 1,413,306,999 No outstanding options

slide-4
SLIDE 4

FINANCIAL YEAR 2015 - REVIEW

  • Loss of AUD$197,041 before depreciation & impairment.
  • Successful scale-up of mining & gold production at Edie Creek –

acquisition of 2nd excavator, bulldozer & 2 additional rod mills/barrels.

  • 4th quarter, machinery downtime, water inundation & lower grade
  • re.
  • 36,473g (1,173 oz) gold & 30,716g (988 oz) silver produced from

1526t at avg grade of 23.9g/t.

  • Addition of 1800mm x 900mm ball mill to processing circuit in QTR4.
  • Successful Wardens’ hearings held in April at Bolobip and May River

ELAs.

  • Acquisition of drill rigs and commenced drilling at Edie Creek with
  • wn rigs and crew.
  • Capital raising completed in May in difficult environment.
slide-5
SLIDE 5

OPERATING IN WORLD CLASS GEOLOGICAL PROVINCES

Papua New Guinea Tasmania

  • Edie Creek Mine - producing gold & silver.
  • May River - major copper gold porphyry and

epithermal anomalies. Adjoins Frieda River deposit.

  • Bolobip – 60km east of Ok Tedi, a major, drill

ready, copper gold porphyry target.

  • Aberfoyle tin and tungsten–

includes Royal George, Great Pyramid and Lutwyche deposits.

  • Old Oonah mine tin/silver deposit.
slide-6
SLIDE 6

EDIE CREEK – AN OPERATING MINE

Significant upside – currently mining only 3.2 tonnes and processing 5.6 tonnes of ore per day – with extensive infrastructure in place

slide-7
SLIDE 7

EDIE CREEK Epithermal Gold & Silver

Identified bulk tonnage targets

  • High grade Au-Ag

veins.

  • Lower grade bulk

tonnage – a number

  • f bodies with

substantial economic potential identified.

  • Drilling program

expanded.

  • Measured scale-up
  • f pilot mining &

processing continuing.

slide-8
SLIDE 8

DRILLING – Edie Creek

  • Still relatively unexplored:
  • only 38 drill holes for 6118m since

drilling commenced in 1988.

  • Extensions of known vein & lode

systems.

  • Bulk tonnage targets.
  • New exploration drilling.

DDH - EDD018

slide-9
SLIDE 9

DRILLING – Edie Creek

slide-10
SLIDE 10

DRILLING – Edie Creek

Drill holes EDD017 & EDD018

slide-11
SLIDE 11

PILOT MINING – Edie Creek

  • Developing 4 semi-circular

small pits over existing, known vein/lode systems, to

  • Extend current mining of medium

to high grade vein/lode systems

slide-12
SLIDE 12

PILOT MINING – Edie Creek

Plan of Alpha East – Edie Lode Extension Pit

slide-13
SLIDE 13

EDIE CREEK PRODUCTION

Jan 15 Feb Mar Apr May Jun Jul Aug Sep Oct Mined Ore 3.55 3.36 2.99 2.16 1.83 2.62 3.49 4.03 3.76 4.33 Processed Ore 6.15 6.51 5.97 3.98 2.51 4.66 6.45 6.62 6.91 6.85 Grade 19.4 31.36 16.73 10.51 17.98 17.60 7.76 8.89 10.07 6.79 0.0 5.0 10.0 15.0 20.0 25.0 30.0 35.0 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 G r a d e A v T

  • n

n e s P e r D a y

Av Tonnes per Day of Mined & Processed Ore, and Grade

slide-14
SLIDE 14

PROCESSING – Edie Creek Now

Ball mill & amalgam barrels

slide-15
SLIDE 15

PROCESSING – near term

slide-16
SLIDE 16

PROCESSING – the future

slide-17
SLIDE 17

EDIE CREEK PRODUCTION

0.00 1000.00 2000.00 3000.00 4000.00 5000.00 6000.00 7000.00 50 100 150 200 250 Jul 14 Aug Sep Oct Nov Dec Jan 15 Feb Mar Apr May Jun Jul Aug Sep Oct Au (g) Ore (t) Month

Gold produced and ore processed by month

Proc'ed Ore (kg&t) Au (g)

The challenge to increase production given the lower grade ore from 6.5 tonnes per day to 20 tonnes per day

Breakeven – PNG Operations

slide-18
SLIDE 18

0.00 2000.00 4000.00 6000.00 8000.00 10000.00 12000.00 14000.00 200,000 400,000 600,000 800,000 1,000,000 1,200,000 1,400,000 March 14 Qtr June 14 Qtr Sep 14 Qtr Dec 14 Qtr Mar 15 Qtr Jun 15 Qtr Sep 15 Qtr Au (g) Sales in PGK Quarter

Edie Creek - Quarterly Gold Production & Sales

Au & Ag Sales (K) Au (g)

EDIE CREEK PRODUCTION

slide-19
SLIDE 19

MAY RIVER - HOTMIN BASE

  • Niuminco’s base

camp acts as a regional exploration base at Hotmin.

  • Ideal locality in

centre of May River Exploration Licence.

  • Existing airstrip, and

major supplies brought in by low- cost river transport.

  • A major airborne

geophysical survey completed.

  • Airborne VTEM and

ZTEM, covering North & South May River completed.

slide-20
SLIDE 20

MAY RIVER – Warden’s hearing

slide-21
SLIDE 21

Frieda River 2bnt Resource

MAY RIVER – ADJOINS FRIEDA RIVER

SKIRASIA DRILLING: 06SK98 109m @ 1.53g/t Au 11SK98 54m @ 1.83g/t Au 93SK001 96m @ 0.89g/t Au UFOU PROSPECTS: 009UF97 11m @ 10.6% Cu, 1.98g/t Au 010UF97 19m @ 11.47% Cu, 2.17g/t Au

slide-22
SLIDE 22

MAY RIVER-structural interpretation

  • Frieda River/May River area contains a number of circular type structures - 1km to 20km

diameter.

  • Some may relate to regional caldera collapse structures and some collapses above

porphyry and/or exposed intrusive bodies or diatreme breccia bodies.

  • Horse-Ivaal to Nena trend coincides with NE rim of inner structure, Iku to Skirasia trend

coincides with SW rim of outer structure.

slide-23
SLIDE 23

BOLOBIP BASE CAMP

A MAJOR COPPER GOLD PORPHYRY TARGET 60KM EAST OF OK TEDI MINE

slide-24
SLIDE 24

BOLOBIP – drill targets

  • A multi-phase intrusive complex. 3 drill targets ready to drill.
  • Latest data shows coherent 1km diameter copper and gold anomaly.
  • Classic geochemical signature of a leached cap above a mineralised copper-gold porphyry
  • system. Extensive surface gold mineralisation in trench channel samples (CRA).
slide-25
SLIDE 25

Focus to remain on the advanced exploration assets:

  • The Aberfoyle Tin & Tungsten Project;

Comprising the Aberfoyle/Lutwyche/Storey’s Creek/Royal George/Great Pyramid tin and tungsten deposits.

  • current JORC 2012 Inferred Mineral Resources for the Royal

George and Great Pyramid deposits.

  • Drilled Oonah during the year - re-assessment of future

exploration.

TASMANIAN PROJECTS

slide-26
SLIDE 26

ABERFOYLE – TIN, TUNGSTEN

  • Potential underpins

TNT’s valuation

  • Development
  • pportunity
  • Potential for combined
  • pen-cut and

underground mine feeding low CAPEX gravity separation plant

  • Extensive historical

data

slide-27
SLIDE 27

GREAT PYRAMID – TIN

  • Inferred Mineral

Resource of 5.2m tonnes @ 0.2% Sn.

  • Shallow, near surface

deposit with low stripping ratio.

  • Excellent

infrastructure and access to site.

  • Low CAPEX as

planned operation is a satellite mine to Aberfoyle.

slide-28
SLIDE 28

ROYAL GEORGE - TIN

  • Inferred Mineral Resource of 800,000

tonnes at 0.33% tin for 2640 tonnes of contained tin using a 0.2% cut-off.

  • Planned development satellite mine to

Aberfoyle deposit.

slide-29
SLIDE 29

2016 – STRATEGY GOING FORWARD

  • Measured scale-up of mining & production at EDIE CREEK, through completion of

ball mill circuit; and

  • Development of 4 existing, known vein/lode systems, to achieve
  • Consistent monthly ore processing & gold production circa 5000g (160 oz),

Thereby allowing the Group to:

  • Continue low cost exploration & extension drilling at EDIE CREEK using own rigs

& crew.

  • Complete low cost drilling of 3 targets at BOLOBIP using own rig & crew.
  • Confirm drill targets & commence exploration drilling at SOUTH MAY RIVER.
slide-30
SLIDE 30

THANK YOU