NPCC VISIT THE POWER SYSTEM OPERATOR OF PAKISTAN National Power - - PowerPoint PPT Presentation
NPCC VISIT THE POWER SYSTEM OPERATOR OF PAKISTAN National Power - - PowerPoint PPT Presentation
SAARC TRAINING FOR PROFESSIONALS OF AFGHANISTANS POWER REGULATORY SYSTEM NPCC VISIT THE POWER SYSTEM OPERATOR OF PAKISTAN National Power Control Centre Presented by: Salman Gul Deputy Manager NPCC National Transmission and Despatch
National Transmission and Despatch Company Ltd.
THE POWER SYSTEM OPERATOR OF PAKISTAN
National Power Control Centre
Presented by:
Salman Gul
Deputy Manager NPCC
INTRODUCTION TO NPCC
National
Power Control Center (NPCC) is part
- f
National Transmission and Despatch Company (NTDC) which is a corporate entity unbundled from WAPDA power wing
NTDC
constructs,
- perates,
maintains primary transmission network (i-e 500,220 kV transmission lines & 500/220 kV grid stations), provides wheeling facility to CPPA-G for purchase of power from generators and selling to DISCOs
DISCOs construct, maintain secondary transmission network (i-e
132,66 kV transmission lines & 132/11 kV grid stations) and 11/0.4 kV distribution system
NPCC is responsible for operation, monitoring of generation , both
primary and secondary transmission system and coordination with all Power sector stake holders (i-e MOE, NTDC head and field offices, DISCOs, GENCOs, CPPA-G & IPPs
MD NTDC DMD (P&E) General Manager (SO) Chief Engineer (Op’n Planning) Manager PPC Chief Engineer (Network Op’n) Manager Power Control Manager RCC-N Manager RCC-S Manager Database
NPCC-Employees Yardstick Total Employees : 389
SYSTEM OPERATION HIERARCHY
- Generation Control
- Switching & Operating
Control of 500 & 220 kV Network Switching & Operation of 132 & 66 kV Southern Network
RCCS
(Regional Control Centre South) Jamshoro
Switching & Operation of 132 & 66 kV Northern Network
RCCN
(Regional Control Centre North) Islamabad
NCC
(National Control Centre)
OBJECTIVES OF NPCC
➢ Reliability & Security of power system
- Smooth Supply
- Minimum Interruptions
➢
Quality of Electric Power Supply
- Standard Voltage and Frequency
➢ Safety
- Personnel.
- Equipment.
➢ Economy
- Minimum Generation Cost
- Minimum Losses
MAJOR FUNCTIONS OF NPCC
- 1. National Power Control Centre, commonly known as
NPCC, is the nerve centre of Power Sector. Entire power generation and its transmission to the load centres is controlled and coordinated from its National and Regional Control Centres. 2. Maintaining balance between Supply & Demand. 3. Frequency , voltage control and equipment loading within permissible limits.
- 4. Maintaining security & stability of network.
MAJOR FUNCTIONS OF NPCC
- 6. Month-wise & Annual Energy Estimation.
- 7. Economic Dispatch.
- 8. Switching operations of Power Network.
- 9. Scheduling of maintenance shut-downs on power-
plants & Transmission network elements. 10.Short to medium term operational planning.
- 11. Advance notifications to thermal plants regarding
energy (Year Ahead, Quarter Ahead, Week Ahead and Day Ahead).
- 12. Collection of system data and preparation of reports
ADMINISTRATIVE FUNCTION
NPCC is headed by General Manager (System Operation)
in main NPCC Building Islamabad.
GM
(SO) is assisted by Chief Engineer (Network Operation) & Chief Engineer (Network Planning).
GM(SO) reports and coordinates with all Stakeholders
regarding Power system.
NPCC is a control and command body and for smooth
- peration of system, pass-on instructions to GENCOS,
IPPs, DISCOs and Hydro Stations from its Control rooms which function round the clock in 3 shifts with Shift Engineers on duty.
SYSTEM OPERATION & CONTROL
NPCC CONTROL ROOM
PRESENT OPERATIONAL STRATEGY
System Security and Reliability are issues of top priority
- nature. This is a technical urgency recognized by utilities
all over the world and may demand out of merit operation
- f some of the generating units in the system.
The provision of spinning reserve is equal to the 1/3rd of
the one biggest generator capacity in system according to grid code.
500 and 220 KV transmission lines/ transformers are
- perated with single contingency compliance.
Thermal Generators are dispatched in order of economic
merit order considering security and stability of system.
Hydel, Nuclear, REs (Wind, Solar) are operated as must
run
Security Constrained Economic Dispatch
Merit Order Plant Avail.
Congestion and Losses Fuel Avail. & Contracts Ramping Rates Startup / down Decision Stability, Reserves Etc…
GENERATION PLANNING & DESPATCH
Procedure and steps.
Demand forecasting/estimation on historical trends Generation forecasting/estimation keeping in view:
➢ Irrigation indents of Hydel stations ➢ Schedule outages ➢ Forced outages ➢ Weather/ Season. ➢ Special Events. ➢ Constraints if any
Dispatch of available thermal generation as per merit order.
OPERATIONAL CONSIDERATIONS FOR DISPATCH (PLANNED)
System Stability. Transmission/ Transformation constraints. Reactive power support for regulating system voltages. Planned and scheduled shutdowns on a)
Transmission Lines
b)
Transformers.
c)
Generating Plants.
Limitations on No. of starts of steam turbines. Testing of generating Plants.
OPERATIONAL CONSIDERATIONS FOR DISPATCH (UN-PLANNED)
Change in Water indents. Change in Gas quota allocations. Load restrictions on generating plants. Tripping of equipment/ Major Outages. Difference in Forecasted and actual load due to
abrupt weather change.
Reactive
power support for regulating system voltages.
NEPRA GRID CODE
NEPRA GRID CODE
Operation of power system regulated
under NEPRA’s Grid Code
OC-1 : General operating principles OC-2 : Demand Forecast
Input from all stakeholders for different time
horizons consolidated by NPCC
OC-3 : Demand Management
NEPRA GRID CODE
OC-4: Operational Planning
Network
- peration
and
- utage
planning/ coordination
Generation dispatch and outage coordination Insufficient power operating margin Frequency and voltage control and operating
margins
NEPRA PERFORMANCE LIMITS
Frequency Frequency Sensitive Mode (Normal Range)
49.8-50.2 Hz
Contingency Frequency Band (Load Shedding Threshold)
49.4-50.5 Hz
Voltage N-0 Contingency
N-1 Contingency
+8 % and -5 %
± 10 %
TRANSMISSION OPERATION & CONTROL
Operational objectives of NPCC are:
- Keeping balance between demand and supply all
the time
- Maintaining stable frequency
- Maintaining system security and reliability
- Keeping stable voltages over primary network
- Monitoring of transmission & transformer
parameters
SWITCHING OPERATIONS
NPCC performs switching operation on transmission network in following scenarios:
- Planned shutdowns for maintenance, cleaning and
washing activities
- Emergent shutdowns in case of abnormal situations.
- Transmission lines and transformers tripping.
- 132 kV switching for optimal configuration of radial
network
GENERATION MIX
GENERATION SOURCES
ABSTRACT OF POWER PLANTS
Generation Type
INSTALLED CAP AS PER LICENCE (MW) DERATED CAPACITY (MW) NO OF UNITS
TOTAL WAPDA HYDEL (22)
9,387 9,387 97
IPP HYDEL (5)
382 379 18
TOTAL HYDEL (27)
9,770 9,767 115
GENCO-I (3)
1,174 860 14
GENCO-II (3)
2,457 1,552 17
GENCO-III (4)
2,051 1,765 17
TOTAL GENCO (10)
5,682 4,177 48
IPP-THERMAL (37)
17,166 15,883 210
NUCLEAR (4)
1,345 1,246 4
SOLAR (4)
400 400 4
WIND (24)
1,235 1,235 718
TOTAL VRE'S (28)
1,635 1,635 722
BAGASSE (9)
363 353 13 TOTAL PLANTS (115) 35,961 33,060 1,112
GENERATION SOURCES (Derated Capacity)
Type Derated Percentage Share MW %age Total Hydel (Wapda + IPPs)
9,767 29.5%
Gencos Fossil Fuel
4,177 12.6%
IPPs Fossil Fuel
15,883 48.0%
Bagasse
353 1.1%
Nuclear
1,246 3.8%
Solar
400 1.2%
Wind
1,235 3.7%
Total
33,060 100.0%
BREAKUP OF MAX RECORDED GENERATION DURING PEAK HOURS
22,601 MW on 04 Sept 2019 Wapda-Hydel 7,937 Gencos 2,290 IPPs 12,374 Total 22,601
23,056 MW on 04 July 2019 @ 14:18 Hours
ABSOLUTE MAX RECORDED GENERATION DURING 24 HOURS
LOAD MANAGEMENT
GENERATION / DEMAND BALANCE
SYSTEM FREQUENCY = 50 HZ
GENERATION
DEM EMAND
The primary function of NPCC is to keep balance between demand and supply & to ensure system security and
- reliability. In balanced condition system frequency is 50 Hz.
GENERATION / DEMAND BALANCE
SYSTEM FREQUENCY < 50 HZ DEM DEMAND AND
GENERATION
When demand exceeds generation, frequency depreciates below 50 Hz and in order to maintain balance between demand and generation, load management has to be carried out.
GENERATION DEMAND BALANCE
Load is continuously varying in time and so the generation has to be varied in order to keep frequency in permissible limits
Variation in generation
- Hydel (Fastest ramping rates)
- Thermal
- Steam Turbines
- Gas Turbines
- DG Sets
GENERATION DEMAND BALANCE
In case of deficit in generation capacity, balance between demand and generation has to be maintained through load management
Therefore a multi tier strategy has been adopted for this balance through load management
Scheduled load management
System security load management
Emergency (Forced) Load Management
36
SCHEDULED LOAD MANAGEMENT
Scheduled load management is carried out by DISCO’s, keeping in view the following factors.
Load demand of respective DISCO. Generation share allocated to DISCO by NPCC. Constraints like voltage drop, transmission and
transformer loading including 11 kV & below system.
37
SYSTEM SECURITY LOAD MANAGEMENT
➢ Under Voltage, Under Frequency & Cross Trip
Protection schemes have been installed for System Security Load Management
EMERGENCY LOAD MANAGEMENT
Emergency load management (Forced LS) is carried out by NPCC by opening 132kV transmission lines in case
- f extreme system emergencies.
Examples are:
1.
Un-foreseen generating unit outages
2.
Non implementation of schedule load management by DISCOs
3.
Rupturing of gas lines
4.
Non availability of fuel
5.
Sabotage activities on transmission lines
6.
Transmission and transformation problems
MERIT ORDER
MERIT ORDER APPROVAL COMMITTEE
Power Plants are operated on the basis of Despatch Merit
Order which is approved by a committee of the following members.
General Manager (SO) NPCC, Convener. General Manager (PSP) NTDC, Member. Chief Technical Officer CPPA-G, Member. Chief Financial Officer CPPA-G, Member. Chief Technical Officer GENCO, Member.
Standard Operating Procedure SOP exists for the process of
preparing and revision of merit order for operation of power plants.
PROCEDURE OF MERIT ORDER FORMATION
➢Procedure
1) Chief Technical Officer CPPA-G will intimate the revised
applicable fuel prices and variable O&M Cost fortnightly in respect of Gencos and IPPs Plants comprising of the following components: i) Fuel Price, ii) Calorific value of fuel, iii) Net Heat Rate, iv) Variable O&M cost, v) Index Premium, vi) Ratio of fuel mix gas and furnace oil, vii) Environment Consideration, viii) Utilization of local gas and RLNG. ix) International contract by GoP for purchase of RLNG. 2) On receipt of information from CTO CPPA-G, office of GM (SO) NPCC shall consolidate/ prepare the revised merit order and put up immediately to all merit
- rder
committee members for final approval.
IMPLEMENTATION OF MERIT ORDER
As per Clause SDC 1.4.3.2 of NEPRA Grid Code, NPCC
always operates the plants without any discrimination. Cheaper plants take the lead in despatching. In prevailing situation of shortfall of power in the country, most of the time in the year, all available plants have to be operated and therefore question of any discrimination of despatch does not arise.
However during short period of lean demand ,Merit order is
strictly followed by NPCC keeping in view the technical constraints of Gencos along with voltage transmission issues if any.
Plants under annual maintenance outages according to
planned programs and hydel generation drops during lean period of system demand.
OPERATION PLANNING
OPERATION PLANNING
Pre Dispatch Functions
Annual Production Plan Calculation of future fuel requirements Year/Quarter/Month/Week Ahead Planning
Post Dispatch Functions
Event/NPMV Verification Liquidated Damages Operating Committees