MESYUARAT PANEL PERUNDINGAN TENAGA
By
- Mr. Gurcharan Singh
Head (GSO)
PERUNDINGAN TENAGA By Mr. Gurcharan Singh Head (GSO) 10 th JUNE - - PowerPoint PPT Presentation
MESYUARAT PANEL PERUNDINGAN TENAGA By Mr. Gurcharan Singh Head (GSO) 10 th JUNE 2014 SYSTEM HIGHLIGHTS GENERATION 21,509 MW INSTALLED CAPACITY PERLIS LANGKAWI Chuping N Kangar 11,222 MW (52.2%) Kuah TNB Kota Bharu Alor Kota
By
Head (GSO)
JOHOR PAHANG MELAKA NEGERI SEMBILAN SELANGOR PERAK KEDAH PULAU PINANG KELANTAN TERENGGANU PERLIS WILAYAH PERSEKUTUAN
LANGKAWIMELAKA BERSIA KENERING TEMENGOR KENYIR SG PIAH UPPER SG PIAH LOWER JOR WOH ODAK CHENDEROH PERGAU
N
Johor BahruPRAI GELUGOR SEGARI CONNAUGHT BRIDGE SERDANG KAPAR POWERTEK PD POWER GENTING SANYEN PORT DICKSON YTL PASIR GUDANG PAKA YTL
Ayer Tawar Batu Gajah Papan Kuala Kangsar Bukit Tambun Junjung Bukit Tengah Gurun Bedong Kota Setar Chuping Bukit Tarek KL (N) KL (E) Hicom G KL (S) Salak Tinggi Melaka Kg Awah Scudai Telok Kalong Tanah MerahJANAMANJUNG YAN
Yong Peng (N) Bukit Batu Sedili Lenggeng Yong Peng (E)3
GENERATION INSTALLED CAPACITY
TNB
IPP
MAXIMUM DEMAND (29/05/14)
RESERVE CAPACITY MARGIN
HIGHEST ENERGY DEMAND (25/6/2013)
SUBSTATION
CIRCUIT KILOMETRES
MVA INSTALLED CAPACITY
2014 17,152 MW 2015 17,697 MW 2016 18,282 MW 2017 18 ,880 MW
2018 19,492 MW
17,152MW
17,697MW 18,282MW 18,880MW 19,492MW
12,000 13,000 14,000 15,000 16,000 17,000 Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug MW
Monthly Peak Demand, MW
FY 08/09 FY 09/10 FY10/11 FY11/12 FY12/13 FY13/14
Financial Year Highest MD (MW) 08/09 14,245 09/10 15,072 10/11 15,476 11/12 15,826 12/13 16,562 13/14 16,583
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% FY0203 FY0304 FY0405 FY0506 FY0607 FY0708 FY0809 FY0910 FY1011 FY1112 FY1213 FY1314
Generation Mix For Peninsula Malaysia
COAL GAS HYDRO OIL DISTILLATE
Malaysia - Coal and Gas
from 75% in 2003 to 47% in 2013.
to 45% in 2013.
percentage has dropped due to major rectification work by stations for tube leak problems.
fuels during gas curtailments and coal unit forced
43 42 39 36 36 41 46 53 57 59 12 8 3 3 1 5 4 4 4 4
10 20 30 40 50 60 70
2014 2015 2016 2017 2018 Percentage Generation Mix by Feul
Gas Coal LNG Hydro
pushes Coal to 59% in 2018.
and hydro at 4%.
mix going forward due to its’ competitive pricing and availability readiness.
Gas and LNG is differentiated by price and quantum.
2 4 6 8 10 12 14 16 18 20
20 14 17.93 13.67 7.32 9.34 6.56 1.02 0.82 1.01 1.03 0.44
for system performance and reliability.
severity of each system disturbance relative to the size
ratio of unsupplied energy during an outage to the energy that would be supplied during one minute, if the supplied energy was at its peak value.
TNB managed to reduce the transmission system minutes from 20min in 2002 to 0.44min in 2013.
0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00 TRANSCO Phillipines ELECTRANET Australia ESKOM South Africa RTE France TNB Malaysia - 2013
12.23 8.30 4.73 2.30 0.44
Minutes
For 2013, TNB’s performance was better than KEPCO and TEPCO, two major utility in Asia.
KEPCO: 25.106 minutes TEPCO: 9 minutes
JOHOR PAHANG MELAKA NEGERI SEMBILAN SELANGOR PERAK KEDAH PULAU PINANG KELANTAN TERENGGANU PERLIS WILAYAH PERSEKUTUAN
LANGKAWIMELAKA BERSIA KENERING TEMENGOR KENYIR SG PIAH UPPER SG PIAH LOWER JOR WOH ODAK CHENDEROH PERGAU
Johor BahruPRAI GELUGOR SEGARI CONNAUGHT BRIDGE SERDANG KAPAR POWERTEK PD POWER GENTING SANYEN PORT DICKSON YTL PASIR GUDANG PAKA YTL
Ayer Tawar Batu Gajah Papan Kuala Kangsar Bukit Tambun Junjung Bukit Tengah Gurun Bedong Kota Setar Chuping Bukit Tarek KL (E) Hicom G KL (S) Salak Tinggi Melaka Kg Awah Scudai Telok Kalong Tanah MerahJANAMANJUNG YAN
Yong Peng (N) Bukit Batu Sedili Lenggeng Yong Peng (E)Prai (TNB) 2 x 535 MW CCGT (Jan 2016) Connaught Bridge (TNB) 1 x 350 MW CCGT (Sep 2015) Janamanjung (TNB) Unit 4: 1 x 1000 MW Coal (Mar 2015) Unit 5: 1x1000 MW Coal (Oct 2017) Tg Bin (IPP) Unit 4: 1 x 1000 MW Coal (Mar 2016) PCP, Pengerang (IPP) 400 MW Import (Jul 2017) Hulu Terengganu (TNB) 250 MW Hydro (Sep 2015) Ulu Jelai (TNB) 372MW Hydro (2018) Chenderoh (TNB) 12MW Hydro (Dec 2015) Tembat (TNB) 15MW Hydro
1MDB (IPP) Unit : 2 x 1000 MW Coal (2019)
GURUN (E) JUNJUNG AYER TAWAR JANAMANJUNG BKT TAREK KAPAR LENGGENG OLAK LEMPIT JIMAH YONG PENG (E) BKT BATU TG BIN PASIR GUDANG
500kV line 500kV line but energized at 275kV
BENTONG (S) ULU JELAI
TAPAH HULU TERENGGANU NEW PRAI Kuala Ketil
– TAPAH & LENGGENG – YONG PENG(E) (2019)
(2015)
(2015)
Reduced rainfall at hydro catchments
0% 10% 20% 30% Jan-13 Apr-13 Jul-13 Oct-13 Jan-14 Apr-14
Generator Outages 2013 - 2014
Unplanned Deration Planned
(plan and forced) averages at 17% for last 2 years.
29%, on 22 Jan 2014.
reserve margin now.
to drop to 25%
1000 2000 3000 4000 Jan-13 Apr-13 Jul-13 Oct-13 Jan-14 Apr-14 MW
Generator on Forced Outages 2013-2014
reach up to 3800MW on certain days.
2,000 4,000 6,000 8,000 Jan-13 Apr-13 Jul-13 Oct-13 Jan-14 Apr-14
MW 900 MW
1800 MW
Yellow Warning
Orange Warning
Red Warning
2300 MW Actual OR Minimum Operating Reserve OR target was reduced to 1800MW due to:-
237 239 241 243 245 247 249 1-Sep 1-Dec 1-Mar 1-Jun
TMGR LAKE LEVEL
'1112 current level '1213
135 137 139 141 143 145 147 1-Sep 1-Dec 1-Mar 1-Jun
KNYR LAKE LEVEL
'1112 Current Level '1213
lowest for the last 14 years.
catchments area are below average.
Kenyir and Temenggor revised due to impounding work for Hulu Trengganu project and the anticipated El-Nino impact.
be carefully utilized to ensure full capacity throughout the year and 2015.
ensured available to meet the relevant agencies minimum discharge requirements.
essential for the plant operation.
penting’, thus water supply will be given top priority by water suppliers.
established mitigation actions if water supply is disrupted.
Selangor.
Kulim Lumut Kuala Berang Temerloh Bentong Gua Musang Kuala Lipis Jerantut Muadzam Shah Mentakab Kuala Pilah Segamat Mersing Kluang Kuah
Dungun Taiping Teluk Intan Kuala Selangor Kuala Kubu Baru Banting Gemas Muar Batu Pahat Pontian Kechil Seri Iskandar Kampar Melaka Seremban Georgetown Kota Bharu Kuala Terengganu Ipoh Kuantan Shah Alam Kangar
JOHOR PAHANG MELAKA NEGERI SEMBILAN SELANGOR PERAK KEDAH PULAU PINANG KELANTAN TERENGGANU PERLIS WILAYAH PERSEKUTUAN
LANGKAWI
PAHLAWAN
Pasir Gudang
BERSIA KENERING TEMENGOR KENYIR SG PIAH UPPER SG PIAH LOWER JOR WOH ODAK CHENDEROH PERGAU
Johor Bahru
PRAI SEGARI CONNAUGHT BRIDGE SERDANG KAPAR POWERTEK PD POWER GENTING SANYEN TJPS YTL PASIR GUDANG PAKA YTL
Ayer Tawar Batu Gajah Papan Kuala Kangsar Bukit Tambun Junjung Gurun Bedong Kota Setar Chuping Bukit Tarek KL (N) KL (E) Hicom G KL (S) Salak Tinggi Melaka Kg Awah Skudai Telok Kalong Tanah Merah Yong Peng (N) Butterworth Bukit Tengah
GELUGOR JANAMANJUNG TTPC MELAKA
Gelang Patah Alor Setar
7498 MW
MAXIMUM DEMAND (28/05/14)
CENTRAL AREA MAX. DEMAND
JMJG500 BTRK500 U1 U3 U2 ATWR275 ATWR500 U4
L1 L2
Split JMJG500 and ATWR500 with either 1400MW or 1700MW direct to BTRK
L1 L2
Point A
Operating Code No. 4 (OC4) governs the procedures to be followed by the GSO and Users to facilitate Demand Control
in the event that
insufficient generating capacity
is available to meet forecast or real-time Demand the possibility of frequency excursions
given in the Planning Code.
25
26
12000 13000 14000 15000 16000 17000 18000 19000 1-May 2-May 3-May 4-May 5-May 6-May 7-May 8-May 9-May 10-May 11-May 12-May MW
System Availability vs Maximum Demand
Genenator Availability Maximum Demand
JMJG U1 PLPS BLK JMAH U1 JMJG U2 JMJG U3 SRDG GT1 TJGS ST1C KLPP GT11 PDPS GT2 PKLG U2
resorted to load shed to protect the grid system.
0800 0900 1000 1100 1200 1300 1400 1500 1600 1700
9:00 - 17:00
Steel Mills were requested to stop arcing in order to reduce demand.
0700 0600
@ 0524hrs
TJGS Blk 1 (240MW) tripped due to faulty control valve.
7th May 2014 morning, generation availability was already low due to previous day forced outage of JMJG U2 and U3. @ 0900hrs
started IMPORT from Singapore & Thailand.
@ 1238hrs
PKLG U2 (145MW) tripped due to cooling water pump failure.
@ 1450hrs
PKLG U1 (285MW) tripped due to cooling water pump failure.
@ 1345hrs
RED warning
was issued.
@ 1411hrs
ROTA was initiated and followed by EMLS which amounting to a total of 470MW load interruption.
15:35 - 17:20
Restoration of supply after PKLG U2 was back online @1521hrs. Red Warning was cancelled @1720hrs with Orange Warning reinstated.