Piner er S Stad adium F Fiel eld Lights Project Status Update - - PowerPoint PPT Presentation
Piner er S Stad adium F Fiel eld Lights Project Status Update - - PowerPoint PPT Presentation
Piner er S Stad adium F Fiel eld Lights Project Status Update Backgr kgrou ound This project consists of: Stadium Lighting PA system and speakers Sound wall Required by Environmental Impact Report (EIR) Site
Backgr kgrou
- und
- This project consists of:
- Stadium Lighting
- PA system and speakers
- Sound wall – Required by Environmental Impact Report (EIR)
- Site improvements:
- Site Paving (ADA Requirements) and Landscaping
- The project is partially Owner Furnished-Contractor Installed, which means that the District will
direct purchase the lighting and appurtenant equipment and a contractor will install it.
- The balance of the work; site work and landscaping, PA/speaker system and concrete sound wall
will be included in the bidding contractor’s scope of work.
Statu tus a s as of 5/ 5/10 10/1 /17
- The Musco Lighting for this project was board approved.
- The construction documents are 80% complete.
- DSA submission scheduled for May 24, 2017
- Tentative date range for DSA approval is July 12 – August 16.
- Bidding schedule is as follows;
- 1st Advertisement
June 6
- 2nd Advertisement
June 13
- Pre-Bid Job Walk
June 15
- Contractor Q&A/Addenda
June 15 – 20
- Bids Due
June 27
Lightin ing (Example le)
Pre reca cast st C Concrete Fe Fence
- Required by Environmental Impact Report
- Used to deflect sound from neighborhood
homes
- Average wall height 12’
- Meets California Environmental Quality Act
(CEQA) requirements
BASE SCOPE: 10-13 FT HIGH FENCE LOCATION ADJACENT TO TRACK & FOOTBALL FIELD
Prec ecas ast C Concrete F e Fence ( e (Exam ample) e)
Samples – For Illustrative Purposes
Mileston
- nes
es
Completion of Construction Documents May 23 DSA Submission May 24 Bidding Process June 6 – 22 Estimated DSA Approval July 12 – August 16 Board Approval for Contract Award TBD after DSA Approval Construction Timeframe 2-3 Months