SLIDE 1 December 23, 2019
1
Pittsburgh Parking Authority 9th and Penn Avenue Replacement Garage Planning Commission Design Review Process New Construction December 23, 2019
Pittsburgh Parking Authority 9 th and Penn Avenue Replacement Garage - - PowerPoint PPT Presentation
Pittsburgh Parking Authority 9 th and Penn Avenue Replacement Garage - - PowerPoint PPT Presentation
December 23, 2019 Pittsburgh Parking Authority 9 th and Penn Avenue Replacement Garage Planning Commission Design Review Process New Construction December 23, 2019 1 LOCATION MAP December 23, 2019 2 INTRODUCTION December 23, 2019
SLIDE 2 December 23, 2019
LOCATION MAP
2
SLIDE 3 December 23, 2019
INTRODUCTION
- Location
- 136 9th Street, Pittsburgh, PA
- Zoning District: GT-C (Golden Triangle – C)
- Size
- Demolition of existing 586 space parking structure
- Build a 692 space facility
- Operations
- Functional and efficient for ease of operations
- Durable cast in place p/t structure with extended life
- Community
- Revitalization and building block for future development
- Architecturally sensitive, and aesthetically enhanced
- Safe pedestrian connections to destinations
- Creation of urban open space (10%)
- Public art requirement (1%)
- Feasibility of re-purposing- ground tier
SLIDE 4 December 23, 2019
SITE PLAN – EXISTING PPAP OWNERSHIP
4
SLIDE 5 December 23, 2019
EXISTING PPAP OWNERSHIP AND DEMOLITION
5
SLIDE 6 December 23, 2019
CONDITIONS PRIOR TO DEMOLITION
SLIDE 7 December 23, 2019
EXISTING PPAP OWNERSHIP AND DEMOLITION
7
SLIDE 8 December 23, 2019
KEY DESIGN AND SITE CONSIDERATIONS
- User groups
- Daily Commuters
- Theatre District Patrons
- North Shore Stadium Events
- Architecture
- Open per code, and natural ventilated structure
- Horizontal lines and screening applications
- Recognition of proposed adjacent uses (hotel, condo)
- Traffic
- Traffic Study
- Primary entry/exits on 9th Street, overflow off of 8th Street
- Close coordination with the Cultural Trust
- Buildings owned by the Cultural Trust
- Maintaining the 3 buildings at corner of 9th and Penn Ave.
- Maintain the Goodyear building to the northwest of garage
- Coordination with demolition of the Duff’s building
- Property line consideration
- Sustainable
- ParkSmart Gold certified / Sustainable strategies
- Green Roof / City Park
SLIDE 9 December 23, 2019
SURROUNDING CONTEXT
9
Intersection of 9th Street and Penn Avenue Benedum Center / Umbrella Sky Exhibit
SLIDE 10 December 23, 2019
SURROUNDING CONTEXT
10
SLIDE 11 December 23, 2019
PERSPECTIVE RENDERINGS / PPAP Existing Parking Structures
11
SLIDE 12 December 23, 2019
RELATIONSHIP TO MASTER PLAN
12
PITTSBURGH CULTURAL TRUST MASTER PLAN
SLIDE 13 December 23, 2019
RELATIONSHIP TO MASTER PLAN
13
SLIDE 14 December 23, 2019
PERSPECTIVE RENDERINGS: 9th Street from Penn Avenue
14
Glass guardrail pedestrian barrier Cast-In-Place Concrete Perforated metal panel; panels project at varying depth; multi-color Curtainwall Decorative / Architectural Fencing
SLIDE 15 December 23, 2019
PERSPECTIVE RENDERINGS: 8th Street from Penn Avenue
15
Cast-In-Place Concrete Glass guardrail pedestrian barrier Perforated metal panel; panels project at same depth; one color Curtainwall
SLIDE 16 December 23, 2019
PERSPECTIVE RENDERINGS: 9th Street from Fort Duquesne
16
Glass guardrail pedestrian barrier Cast-In-Place Concrete Perforated metal panel; panels project at varying depth; multi-color Curtainwall Decorative / Architectural Fencing
SLIDE 17 December 23, 2019
PERSPECTIVE RENDERINGS: 9th Street from Penn Avenue (night)
17
Glass guardrail pedestrian barrier Cast-In-Place Concrete Perforated metal panel; panels project at varying depth; multi-color Curtainwall Decorative / Architectural Fencing
SLIDE 18 December 23, 2019
AERIAL RENDERINGS: 9th Street from Fort Duquesne
18
Paver area; temporary movie area Tall grasses Children’s playground; sport turf Artwork / sculpture Dog park Glass guardrail pedestrian barrier
SLIDE 19 December 23, 2019
WALL PANEL DETAIL
19
Perforated metal panels in 6 shades
- f grey, projecting
SLIDE 20 December 23, 2019
SITE PLAN
20
SLIDE 21 December 23, 2019
SITE PLAN
21
SLIDE 22 December 23, 2019
GROUND TIER PLAN
22
SLIDE 23 December 23, 2019
GROUND TIER PLAN
23
SLIDE 24 December 23, 2019
SECOND TIER PLAN
24
SLIDE 25 December 23, 2019
TYPICAL TIER PLAN
25
SLIDE 26 December 23, 2019
ROOF LEVEL PLAN – GREEN ROOF
26
SLIDE 27 P E N N A V E N U E
→
)
U B
UP SPEED RAMP UP P L P L P L P L P L P L P L P L P L P L P L P L P L P R O P O S E D P A R K I N G GARAGE URBAN OPEN SPACE AND P E D E S T R I A N A C C E S S EASEMENT #2 ACCESS DRIVE E A S E M E N T # 1 SITE DEVELOPMENT PLAN LD-5 NOTES: 1. SOIL CLASSIFICATION; URBAN LAND (UB) - 0 TO 3 PERCENT SLOPES, PAVEMENT, BUILDINGS AND OTHER ARTIFICIALLY COVERED AREAS. NOTE: FOR LEGEND OF EXISTING FEATURES SEE SHEET LD-2; NOTES, LEGEND AND ABBREVIATIONS PITTSBURGH PARKING AUTHORITY 9TH AND PENN PARKING GARAGE CITY OF PITTSBURGH ALLEGHENY COUNTY PAN W CONSULTING ENGINEERS, INC.
151 RENO AVENUE NEW CUMBERLAND, PA 17070 (717) 441-2216 FAX (717) 695-7449 www.navarrowright.com N AVARRO & W RIGHTDRAFT
Goodyear Service Center- No Access
- No Access
DRAFT - Site Logistics Plan
Developed by Massaro 12/02/2019