Quarterly Commission Update 1/14/2020
Powering our way of life.
Power Production Quarterly Commission Update 1/14/2020 Powering our - - PowerPoint PPT Presentation
Power Production Quarterly Commission Update 1/14/2020 Powering our way of life. Department Purpose and Goal Purpose: Provide safe, secure, economical, reliable and compliant power generation under the Priest Rapid Project Federal Energy
Quarterly Commission Update 1/14/2020
Powering our way of life.
Purpose: Provide safe, secure, economical, reliable and compliant power generation under the Priest Rapid Project Federal Energy Regulatory Commission (FERC) License Project No. 2114 while supporting the Wanapum relationship. Goal: Execute the aforementioned tasks while championing a culture of safety and operational excellence with continuous focus on the guiding values of safety, innovation, service, teamwork, respect, integrity, and heritage.
Project
10 20 30 40 50 60 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Job Site Reviews
70% 75% 80% 85% 90% 95% 100% 105% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Safety Meeting Attendance
Target Actual
behavior/conditions, suggestions for areas of improvement
60 65 70 75 80 85 90 95 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Project Availability
PR Actual Wan Actual Project Actual Target
head vibration
P01, P07 Exciter fires
2 4 6 8 10 12 14 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Forced Outage Percentage
PR Actual Wan Actual Project Actual Target
Capital O&M
Budget $25,609,386 Directs $23,189,755 Actual $10,567,433 $15,433,495 Remain $15,041,953 $7,756,260 Budget $4,226,729 Labor $22,147,961 Actual $4,460,891 $19,874,946 Remain $234,162 $2,273,051 Budget $29,836,115 Total $45,337,716 Actual $15,028,324 $35,308,441 Remain
$14,807,791 $10,029,275
Schedule Adherence
Challenges
into corrective actions
unexpected
Maintenance Health (PR)
context for schedule adherence – a more complete picture 2020 Plans
practices to Wanapum & Maintenance Center
Maximo Update
Capital Project Update
Strategic Deployment: 2020 Goals
initiatives
commitment
Strategic Deployment: 2020 Goals
Goals established
Operations: Move craft work into Maximo
Personnel
Wanapum upgrade.
2020 Q1 Forecast
mobilization
Powering our way of life.
Grant PUD Commission Meeting – January 14, 2020
Powering our way of life.
recreation facilities, and provides company-wide real estate and geographic information system (GIS) services in alignment with Grant PUD’s safety, financial, and compliance goals.
FERC approval of Recreation Resources Management Plan
Rock 115kV, fiber build-out, office/storage space, etc.
Priest Rapids Right Embankment mapping, Wholesale Fiber mapping and analysis for grant applications, Fish & Wildlife mapping for publication, etc.
approved
management of peak weekends, record crowds
2019 Spotlight:
Columbia Cliffs compliance
encroachments removed since October
joint land-use authorization in development
pending FERC approval
classification
2019 Budget Actuals as of 11/30/2019 Budget Remaining % of Budget Spent Q4 YEP % Budget to YEP CAP $37,500 $531,081 ($493,581) 1416.22% $580,866 1548.98% O&M $1,321,606 $837,091 $484,515 63.34% $1,177,426 89.09% Labor $1,136,018 $1,044,408 $947,818 91.94% $1,136,109 100.01% TOTAL $2,495,124 $2,412,580 $938,752 96.69% $2,894,401 116.00%
Planned Projects & Work Activities
Production/Power Delivery projects, property leases
Mat, Fiber Expansion, Power Delivery projects
permit
updates
initiatives
work orders for rec sites
construction projects
Buckshot rebuild
dredging and erosion control
Boat Launch float replacement
trailer replacement
100%
(Shoreline Mgmt. Plan)
none known/anticipated
GCPUD Enterprise Risk
Q1 2019 Update
Budget / Staffing
GCPUD ERM: Staffing Changes
Enterprise Risk Manager (1)
– Transitions to role in January from Wholesale Mkt Supply – Dual support role on special projects
– Departure in December
Risk Analyst (2)
– Moving to EPMO in January
GCPUD ERM: Budget Nov
KEY DETAILS The Risk Department budget is dominated by insurance premiums. Based on Nov 2019 Actuals
Budget Actuals Variance Fav/(Unfav) Enterprise Risk 57,592 14,016 43,576 Insurance Risk 2,048,425 1,782,520 265,905 Sub - Total 2,106,017 1,796,536 309,481 Budget Actuals Variance Fav/(Unfav) Enterprise Risk 148,765 134,314 14,451 Insurance Risk 203,364 188,486 14,878 Sub - Total 352,129 322,800 29,329 Total 2,458,146 2,119,336 338,810 Labor O&M Directs
Current Business
GCPUD ERM: Current Business
Annual Insurance Renewal
is being scheduled sometime in January.
submitted to lead underwriter this month.
GCPUD ERM: Current Business
Central Ephrata Substation Claim
Middle Office Control Design
Business Support
GCPUD ERM: Business Support
Wholesale Model Review
Reporting
Forward Price Curve Review
Energy Risk Policy Update
GCPUD ERM: Business Support
Rate 17
Slice Strategy Support
KEY DETAILS Commercial Support is a key function of GCPUD’s Risk business model.
grantpud.org
Powering our way of life.
Gene Austin
Compliance Manager
Reliability Compliance Program The Year in Review - 2019 The Year Ahead - 2020
The Year in Review – 2019
2019 Objectives − Restore Confidence and Effectiveness − Establish RC Program Foundation − Validate District Compliance Posture
The Year in Review – 2019
Foundational Accomplishments: − Assessed Program; Planned Improvements − Defined Reliability Organizational Structure − Rebuilt how we Manage Compliance Information − Restored Compliance Tools to Track and Notify − Clarified Roles and Responsibilities − Trained/ Developed RC Staff − Revamped the NERC-CIP Compliance Program − Fortified Regulator Relationships − Restored Confidence in RC Workgroup
March 28, 2019
Engineering – PP, PD Operations – PP, PD Craft & Technical Shops
CIP Standard Owners/ SMEs CIP Program Lead O&P Standard Owners/ SMEs Chief Compliance Officer/ CFO Reliability Council CIP Sr. Manager/ COO Compliance Manager/ PCC
* Position required by Regulator
*/
Cyber Security Physical Security Network Operations System Support; EMS GMS EACM PACS HelpDesk HR, Training Procurement
GCPD Reliability Council
The Reliability Council provides executive leadership, direction,
accountability, and oversight for Reliability Compliance Program.
The Council establishes the expectations and governs the
GCPD Reliability Council
…provides executive leadership, direction, accountability, and oversight for Reliability Compliance Program…
Reliability Council
− Chief Compliance Officer*/ CFO − CIP Sr. Manager*/ COO − Chief Customer Officer − Power Production, Managing Director − Power Delivery, Managing Director − Chief Technology Officer − Primary Compliance Contact* (Chair)
Members
− Jeff Bishop − Rich Wallen − Dave Churchman − Ty Ehrman − Jeff Grizzel − Derin Bluhm − Gene Austin
* Position required by Regulator
Standards & Requirements
O&P Reliability Standards 70
Requirements 924
CIP Standards 12
Requirements 67
2019 Emphasis to Assure Compliance
Potential Non-Compliance Violations
Self-Reported PNCs are:
˗ 1 of 8 means of Violation Discovery ˗ Least ‘Aggravated’ form of Discovery ˗ Builds Credibility with Regulator
Open PNC’s – 13
˗ ( 2) Audit Findings – 2017 ˗ ( 1) Self-Report – 2018 ˗ (10) Self-Report – 2019 ˗ ( 2) Identified and under RC review
10
‘Simplify, Standardize, and Single Source’
11
CIP Responsibilities – who does what?
12
R4.1 – A Process to Authorize Access (electronic and Physical) based on need: −Electronic access; −Unescorted Physical Access into PSPs −Access to BES Cyber System Information R4.2 – Verify at least once each calendar quarter that individuals with active electronic access or unescorted physical access have authorization records
CIP-004 “Cyber Security — Personnel & Training”
PURPOSE: To minimize the risk of impacting the Reliability of the Bulk Electric System, from individuals with access to Cyber Systems, through Personnel Risk Assessment, Training, and Security Awareness…
13
Reliability Compliance Program The Year Ahead - 2020
Routine Compliance Activities Continued RC Program Enhancements
AUDIT Readiness
2020 Triennial NERC Audit
Audit Schedule:
Commenced 1/7/2020
evidence/ Data Requests
start of the Audit
inspection of facilities – Aug. 21st
September 2020 Determining the Audit Scope
Audit Readiness Schedule
9/1/2019 8/31/2020 10/1/2019 11/1/2019 12/1/2019 1/1/2020 2/1/2020 3/1/2020 4/1/2020 5/1/2020 6/1/2020 7/1/2020 8/1/2020
3/2/2020 2019 Self-Certification 8/10/2020 - 8/21/2020
Triennial NERC Audit
1/1/2020 Low Impact BES Cyber Systems Compliance CIP-003-7 1/6/2020 - 2/29/2020 Self-Cert Preparation 9/1/2019 - 12/31/2019 CIP Procedure Rewrite & Other Program Enhancements 1/7/2020 - 7/17/2020 NERC Audit Readiness 7/17/2020 Submit Audit Docs 7/1/2020 Supply Chain Management CIP-013-1 3/5/2020 Inherent Risk Assessment 1/7/2020 Audit Kickoff Mtg 1/27/2020 - 8/21/2020
Compliance Assessment and Audit Support GDS Associates
5/1/2020 Audit Notice
Reliability Compliance
Budget to Actual
Through 11/30/2019