Presentation to: Little Missouri Scenic River Commission Sept 1, - - PowerPoint PPT Presentation

presentation to little missouri scenic river commission
SMART_READER_LITE
LIVE PREVIEW

Presentation to: Little Missouri Scenic River Commission Sept 1, - - PowerPoint PPT Presentation

Presentation to: Little Missouri Scenic River Commission Sept 1, 2020 Presented by Dan Schneider, PE NDDOT Project AC-NH-SOIB-7- 085(109)125 STRUCTURE REPLACEMENT, WILDLIFE CROSSING STRUCTURE, GRADING, AGGREGATE BASE, HMA, GUARDRAIL &


slide-1
SLIDE 1

Presentation to: Little Missouri Scenic River Commission Sept 1, 2020

Presented by Dan Schneider, PE

slide-2
SLIDE 2

NDDOT Project AC-NH-SOIB-7- 085(109)125

STRUCTURE REPLACEMENT, WILDLIFE CROSSING STRUCTURE, GRADING, AGGREGATE BASE, HMA, GUARDRAIL & INCIDENTALS

slide-3
SLIDE 3

PROJECT OVERVIEW

  • Location: US 85, Long X Bridge, Between Grassy Butte and Watford

City

  • NDDOT District: Williston
  • Design: NDDOT
  • Contract Date: June 10, 2019
  • Start Date: July 29, 2019
  • Completion Date: July 15, 2021
  • Original Contract Amount: $33,971,510.00
  • Contractor: Ames Construction, INC Burnsville, MN
  • Construction Inspection team: AECOM
slide-4
SLIDE 4

Sequencing

  • Widen roadway, begin construction of Long X Bridge, and construct

temporary bypass at wildlife crossing structure

  • Place traffic on temporary bypass and construct east portion of

wildlife crossing structure. Bridge construction continues.

  • Construct roadway over east portion of the wildlife crossing structure

and construct west portion of wildlife crossing structure

  • Complete construction of long X Bridge and route traffic to east half
  • Remove existing bridge, salvaging the south truss.
  • Complete roadway and route traffic to newly constructed bridge and

roadway

slide-5
SLIDE 5

Plans and Cross-sections

slide-6
SLIDE 6
slide-7
SLIDE 7

Existing Structure

slide-8
SLIDE 8

Environmental Commitments

  • Paleontologist requirements
  • Theodore Roosevelt National Park provisions
  • Grouse lek surveys and provisions
  • SWPPP
  • Eagle and Raptor nesting surveys and provisions
  • Big horn sheep lambing provisions
  • USFS provisions
  • Biologist requirements
  • Asbestos removal
  • Sensitive plant species watch
slide-9
SLIDE 9

Environmental Commitments (2)

  • Noxious weed survey
  • Equipment hygiene
  • Fire prevention provisions
  • Erionite disposal
  • Visual screening
  • Aquatic nuisance provisions
  • Cultural resource preservation
  • Causeway construction and minimum river opening
  • Migratory bird provisions
slide-10
SLIDE 10

Paleontologist Findings

slide-11
SLIDE 11

Drilled shafts at abutment 1

slide-12
SLIDE 12

Reinforcing steel cage Abutment 1

slide-13
SLIDE 13

Ground Anchors Abutment 1

slide-14
SLIDE 14

Removing Ground Anchor Casing

slide-15
SLIDE 15

Piling

slide-16
SLIDE 16

Cofferdam Construction

slide-17
SLIDE 17

Reinforcing steel

slide-18
SLIDE 18

Placing Concrete

slide-19
SLIDE 19

Pier 5 with Form Liner

slide-20
SLIDE 20

Substructure Construction Piers 3 and 4

slide-21
SLIDE 21

Architectural Finish

slide-22
SLIDE 22

Prestressed Concrete I Beams

slide-23
SLIDE 23

Setting Beams over Little Missouri River

slide-24
SLIDE 24

Erosion control

slide-25
SLIDE 25

Phase 1 Wildlife Crossing

slide-26
SLIDE 26

Phase 2 Wildlife Crossing

slide-27
SLIDE 27

Completed Wildlife Crossing – Looking East

slide-28
SLIDE 28

Deck Placement

slide-29
SLIDE 29

Artist Rendition

slide-30
SLIDE 30

Conclusion

  • Project progressing well
  • Completion scheduled for July 2021
  • Questions