Pressure Zone 3 Expansion Project Update - Gregory Hill Pump - - PowerPoint PPT Presentation

pressure zone 3 expansion project update gregory hill
SMART_READER_LITE
LIVE PREVIEW

Pressure Zone 3 Expansion Project Update - Gregory Hill Pump - - PowerPoint PPT Presentation

Pressure Zone 3 Expansion Project Update - Gregory Hill Pump Station & Tanks Westminster City Council Meeting July 10, 2017 Discussion Outline Review the Pressure Zone 3 Project 1. Review Gregory Hill Project 2. Show Renderings 3.


slide-1
SLIDE 1

Pressure Zone 3 Expansion Project Update

  • Gregory Hill Pump Station & Tanks

Westminster City Council Meeting July 10, 2017

slide-2
SLIDE 2

Discussion Outline

1.

Review the Pressure Zone 3 Project

2.

Review Gregory Hill Project

3.

Show Renderings

4.

Discuss Proposed Schedule

5.

Questions and Discussion

slide-3
SLIDE 3

PZ3 Program Is The Latest Series of System Improvement Projects

1.

Correct Large Areas of Long- Standing Low Pressure

2.

Increase Water Storage

3.

Connect Existing Storage to More Customers

4.

Increase Redundancy to the Existing Pump Stations

5.

Replace Aging Infrastructure

Zone 3 and Expansion Area

slide-4
SLIDE 4

20”BFV 12”BFV

The Zone 3 Expansion Scope Includes 7 System Improvements

  • 1. Demo Sunset Ridge Tank
  • 2. 104th Transmission Main
  • 3. 88th Transmission Main
  • 4. Gregory Hill Area Pipelines
  • 5. GH Site PS & Tanks
  • 6. New Elevated Tank
  • 7. Surge Protection Equipment
slide-5
SLIDE 5

Improvements Were Based

  • n Extensive Analysis

1.

+$500,000 Preliminary Design

2.

+40 Hydraulic Model Scenarios

3.

Cost-Benefit Analysis

4.

Aging Infrastructure Timing

5.

Current and Future Demands

6.

Project and Cost Phasing

7.

Decision Support Matrices of Multiple Non-Monetary Criteria

slide-6
SLIDE 6

Analysis Included Many Sites For Tanks and Different Layouts

CROWN POINT SCHOOL DMV ELEVATION 5525 (APPROX)

slide-7
SLIDE 7

The Gregory Hill Site is Best for the Pump Station and Tanks

Existing Gregory Hill Tanks & Pump Station Site Pillar of Fire

slide-8
SLIDE 8

The Gregory Hill Site was Selected for Many Reasons – Slide 1 of 2

  • 1. Compatibility with Existing System
  • Existing Ground Storage
  • Existing Elevated Storage
  • Existing Pump Stations
  • Hydraulic Proximity to Transmission Lines
  • Current and Future Water Demand Distribution
  • Geographic Diversity & Reliability
  • 2. Unique Necessary Elevation for Storage

Tanks

slide-9
SLIDE 9

The Gregory Hill Site was Selected for Many Reasons – Slide 2 of 2

  • 3. Unique Necessary Location for Pump Station

Network

  • 4. Existing Site with Adjacent Available Land
  • 5. Northridge & Wandering View Sites Already Have

Maximized Storage

  • 6. Highest Score of Ten Non-Monetary Factors
  • 7. Ability to Co-Address Aging Infrastructure
  • 8. Monetary Factors
slide-10
SLIDE 10

The Existing Site is Too Small and Must Expand East – Slide 1 of 2

slide-11
SLIDE 11

The Existing Site is Too Small and Must Expand East – Slide 2 of 2

slide-12
SLIDE 12

Project Includes Many Site Enhancements – Slide 1 of 2

slide-13
SLIDE 13

Project Includes Many Site Enhancements – Slide 2 of 2

slide-14
SLIDE 14

Views from Newton Street Will Change – Slide 1 of 2

slide-15
SLIDE 15

Views from Newton Street Will Change – Slide 2 of 2

slide-16
SLIDE 16

The New East Tank Aligns with Newton Street – Slide 1 of 2

slide-17
SLIDE 17

The New East Tank Aligns with Newton Street – Slide 2 of 2

slide-18
SLIDE 18

Setbacks to Property Line Will Increase - Slide 1 of 2

slide-19
SLIDE 19

Setbacks to Property Line Will Increase - Slide 2 of 2

slide-20
SLIDE 20

The Gregory Hill Project Is Awaiting Next Steps

  • 1. Bids Solicited - Currently Being Reviewed
  • 2. Options with Neighborhood Input
  • Site Access, Fencing, Landscaping, Other Related Ideas
  • 3. Target August City Council for Construction

Contracts

  • 4. 18-Month Construction
slide-21
SLIDE 21

Questions

Dan Strietelmeier, Project Manager 303-658-2179 or dstriete@cityofwestminster.us Stephen Grooters, Utilities Engineering Manager 303-658-2194 or sgrooters@cityofwestminster.us