Project Scope Recommendations April 12, 2016
1
Existing Site Arrangement
Project Scope Recommendations April 12, 2016 Existing Site - - PowerPoint PPT Presentation
Project Scope Recommendations April 12, 2016 Existing Site Arrangement 1 Ba c kg ro und: LRCC Replacement included in adopted FY2015-2024 CIP April 2015 early community visioning and survey feedback June-September, 2015 massing
1
Existing Site Arrangement
LRCC Replacement included in adopted FY2015-2024 CIP April 2015 early community visioning and survey feedback June-September, 2015 massing concepts and cost estimating July 2015 County Board direction to explore including APS Pre-K November 2015 joint AC/APS work session review of two massing concepts
2
3
Lubber Run Visioning Session
Fall/Winter 2015 Massing Concepts
Ensure preservation of mature and cherished trees Concerns about retaining open/green space
Building size Hardscape Parking County staff Lack of DPR preschool
Gym is needed
4
5
Exercise & Fitness equipment Swimming pool Indoor sports Gyms Nature Center
Swimming pool Exercise & Fitness equipment Nature Center Community Center Gyms
6
7
Walter Reed Center
8
Gym at ground level Construction above impractical with
Gym on upper levels creates noise
Arlington Mill Center Langston Center
9
Zoning Ordinance: 480 parking spaces Recommended with Use Permit: 150
Surface lot for 150 vehicles: 48,000 sf Alternate of surface drop off and 150 underground
Paved area reduced to 1,000 sf drive aisle 150 underground spaces @ $60,000 ea. = $9.0 M
Maggie Daley Park, Chicago
10
FY 2015 – FY 2024 CIP – 37,500 sf with no gym nor improvements to outdoor amenities (2014 $) $28M Concept study estimates: Building Gymnasium S/Total $23.5 M $6.8 M $30.3 M Outdoor Amenities $2.9 M Underground Parking @ $60 K/space, 150 spaces $9.0 M Total Estimate 2015 $ $42.2 M Escalated 2017 $ @ 3% per year $44.8M
Open Issues
11
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 BOARD GUIDANCE A/E RFP & SELECTION BOND REFERENDUM COMMUNITY PROCESS/CONCEPT DEVELOPMENT CMAR RFP AND SELECTION PFRC REVIEWS AND APPROVAL CONSTRUCTION DOCUMENTS & PERMITS CONSTRUCTION AUTHORIZATION CONSTRUCTION OCCUPANCY MILESTONES BOARD ACTION COMMUNITY ACTION PROCUREMENT DESIGN CONSTRUCTION 2020 2016 2017 2018 2019 ACTIVITY
Submit CIP request with underground parking Initiate RFP for designer in May, 2016 Engage community for concept and site development, including PFRC
Issue RFP for Construction Manager at Risk: Fall, 2016
Contractor selection based on prior experience and successful project deliveries On Board prior to final concept decision Contractor to participate in design completion to maintain total budget Construction awarded after negotiation of guaranteed maximum pricing
12
13
Klimmendaal, Netherlands