Purbrook Way Hulbert Road Junction – Phasing Drawings
Revision 2 Current at 31-03-2016
Purbrook Way Hulbert Road Junction Phasing Drawings Revision 2 - - PowerPoint PPT Presentation
Purbrook Way Hulbert Road Junction Phasing Drawings Revision 2 Current at 31-03-2016 From: Tuesday 29 th March To: Friday 1 st April Full Depth Road Construction SE Roundabout Part 2 of 2 Surface Water Drainage SE Rbt Part 2 of 2
Revision 2 Current at 31-03-2016
From: Tuesday 29th March To: Friday 1st April Full Depth Road Construction –
Surface Water Drainage
Splitter island and footway build
From: Monday 4th April To: Wednesday 6th April (end of day) 3 days
roundabout completed in one phase – same duration as half.
Asda exit lane reduced in width Two lines of traffic cannot safely join a roundabout with only 1 lane.
Full Depth Road Construction –
Plane out and Lay Tarmac
Surface Water Drainage
Splitter island and footway build
Extent of TM Extent of Surfacing
LEGEND
From: Thursday 7th April To: Friday 15th April
Kerbing
Splitter island works and footway build
Signage, Guardrail, Traffic Signals, Street Lighting, CCTV works
From: Monday 18th April To: Thursday 21st April 4 Nights
Surface Course
Asda exit lane reduced in width Single file, one direction traffic control in place
Over night closures with 4-Way Traffic Light System in place Roundabout returned to normal operation during the day Extent of TM Extent of Surfacing
LEGEND
Plane Out, Install Reinforcement Grid, lay Binder & Surface Course
Asda exit lane reduced in width Two lines of traffic cannot safely join a roundabout with only 1 lane.
From: Friday 22nd April To: Wednesday 27th April 4 Nights
Extent of TM Extent of Surfacing
LEGEND
From: Thursday 28th April To: Friday 6th May 6 Nights Note: Bank Holiday Monday 2nd May
Plane Out, Install Reinforcement Grid, lay Binder & Surface Course
Over night closures with 4-Way Traffic Light System in place Roundabout returned to normal operation during the day
Asda exit lane reduced in width Single file, one direction traffic control in place During this phase there will be the need to stop all traffic for 15-20mins to allow surfacing vehicles to lay entrance area. This will be controlled and co-ordinated with Asda and the public.
Extent of TM Extent of Surfacing
LEGEND
From: Monday 9th May To: Friday 13th May 5 Nights
Surface Course
Over night closures with 4-Way Traffic Light System in place Roundabout returned to normal operation during the day
Asda exit lane reduced in width Single file, one direction traffic control in place During this phase there will be the need to stop all traffic for 15-20mins to allow surfacing vehicles to lay entrance area. This will be controlled and co-ordinated with Asda and the public.
Extent of TM Extent of Surfacing
LEGEND
Asda exit lane reduced in width Works adjacent to Asda entrance/exit required, resulting in reduced width.
From: Monday 16th May To: Wednesday 18th May
Break out and build Asda Splitter island (including footway crossing and original kerbing)
Surface Course
Signage, Guardrail, Traffic Signals, Street Lighting, CCTV, Landscaping works
current design and programme. They are subject to change should unforeseen circumstances arise, design changes, weather etc.
to minimise the disruption to local stakeholders and travelling public.
require alteration on site to reflect Health, Safety and operational requirements.