Purbrook Way Hulbert Road Junction Phasing Drawings Revision 2 - - PowerPoint PPT Presentation

purbrook way hulbert road junction phasing drawings
SMART_READER_LITE
LIVE PREVIEW

Purbrook Way Hulbert Road Junction Phasing Drawings Revision 2 - - PowerPoint PPT Presentation

Purbrook Way Hulbert Road Junction Phasing Drawings Revision 2 Current at 31-03-2016 From: Tuesday 29 th March To: Friday 1 st April Full Depth Road Construction SE Roundabout Part 2 of 2 Surface Water Drainage SE Rbt Part 2 of 2


slide-1
SLIDE 1

Purbrook Way Hulbert Road Junction – Phasing Drawings

Revision 2 Current at 31-03-2016

slide-2
SLIDE 2

From: Tuesday 29th March To: Friday 1st April Full Depth Road Construction –

  • SE Roundabout Part 2 of 2

Surface Water Drainage

  • SE Rbt Part 2 of 2
  • HRS

Splitter island and footway build

  • PWW, PWE, HRN
slide-3
SLIDE 3

From: Monday 4th April To: Wednesday 6th April (end of day) 3 days

  • Traffic directed around B&Q roundabout
  • Surfacing works to west side of main

roundabout completed in one phase – same duration as half.

Asda exit lane reduced in width Two lines of traffic cannot safely join a roundabout with only 1 lane.

Full Depth Road Construction –

  • SE Rbt Part 2 of 2

Plane out and Lay Tarmac

  • SW Rbt Part 1 of 2

Surface Water Drainage

  • SE Rbt Part 2 of 2, PWW

Splitter island and footway build

  • PWW, PWE, HRS, HRN

Extent of TM Extent of Surfacing

LEGEND

slide-4
SLIDE 4

From: Thursday 7th April To: Friday 15th April

Kerbing

  • Asda entrance

Splitter island works and footway build

  • PWW, PWE, HRS, HRN, Roundabout

Signage, Guardrail, Traffic Signals, Street Lighting, CCTV works

  • Multiple areas
slide-5
SLIDE 5

From: Monday 18th April To: Thursday 21st April 4 Nights

Surface Course

  • HRN and Roundabout

Asda exit lane reduced in width Single file, one direction traffic control in place

Over night closures with 4-Way Traffic Light System in place Roundabout returned to normal operation during the day Extent of TM Extent of Surfacing

LEGEND

slide-6
SLIDE 6

Plane Out, Install Reinforcement Grid, lay Binder & Surface Course

  • Purbrook Way (East)

Asda exit lane reduced in width Two lines of traffic cannot safely join a roundabout with only 1 lane.

From: Friday 22nd April To: Wednesday 27th April 4 Nights

Extent of TM Extent of Surfacing

LEGEND

slide-7
SLIDE 7

From: Thursday 28th April To: Friday 6th May 6 Nights Note: Bank Holiday Monday 2nd May

Plane Out, Install Reinforcement Grid, lay Binder & Surface Course

  • Purbrook Way (West)

Over night closures with 4-Way Traffic Light System in place Roundabout returned to normal operation during the day

Asda exit lane reduced in width Single file, one direction traffic control in place During this phase there will be the need to stop all traffic for 15-20mins to allow surfacing vehicles to lay entrance area. This will be controlled and co-ordinated with Asda and the public.

Extent of TM Extent of Surfacing

LEGEND

slide-8
SLIDE 8

From: Monday 9th May To: Friday 13th May 5 Nights

Surface Course

  • Hulbert Road (South)

Over night closures with 4-Way Traffic Light System in place Roundabout returned to normal operation during the day

Asda exit lane reduced in width Single file, one direction traffic control in place During this phase there will be the need to stop all traffic for 15-20mins to allow surfacing vehicles to lay entrance area. This will be controlled and co-ordinated with Asda and the public.

Extent of TM Extent of Surfacing

LEGEND

slide-9
SLIDE 9

Asda exit lane reduced in width Works adjacent to Asda entrance/exit required, resulting in reduced width.

From: Monday 16th May To: Wednesday 18th May

  • 2 days Break out and kerbing
  • Clear for the weekend
  • 1 day (Wednesday 18th May) surfacing

Break out and build Asda Splitter island (including footway crossing and original kerbing)

  • Asda entrance/exit

Surface Course

  • Around Asda splitter island

Signage, Guardrail, Traffic Signals, Street Lighting, CCTV, Landscaping works

  • Multiple areas
slide-10
SLIDE 10

Notes

  • The dates and durations detailed are the current best forecast based on

current design and programme. They are subject to change should unforeseen circumstances arise, design changes, weather etc.

  • This phasing is different to that originally planned and has been produced

to minimise the disruption to local stakeholders and travelling public.

  • Traffic Management layouts will be assessed when installed and may

require alteration on site to reflect Health, Safety and operational requirements.