Purple Line Extension Community Webinar July 24, 2019 1 Agenda Section 1 Update Section 2 Update Section 3 Update Eat Shop Play Business Interruption Fund Questions


slide-1
SLIDE 1

Purple Line Extension

Community Webinar July 24, 2019

1

slide-2
SLIDE 2

Agenda

2

  • Section 1 Update
  • Section 2 Update
  • Section 3 Update
  • Eat Shop Play
  • Business Interruption Fund
  • Questions & Answers
slide-3
SLIDE 3

Purple Line Extension

Project Alignment

3

slide-4
SLIDE 4

Sections 1, 2 & 3 Status

4 *Subject to change. The PLE project team is working to deliver the project consistent with Measure M

Forecasted Schedule Section

Section 1 Section 2 Section 3

Length

3.92 Miles 2.59 Miles 2.56 Miles

New Stations

Wilshire/La Brea Wilshire/Fairfax Wilshire/La Cienega Wilshire/Rodeo Century City/ Constellation Westwood/UCLA Westwood/VA Hospital

Pre-Construction Activities

2014 – 2015 2016 – 2018 2018 – 2019

Construction

2015 – 2023 2018 – 2025 2019 – 2027

Operations

2023 2025 2027

slide-5
SLIDE 5

Purple Line Extension

Section 1 Alignment

5

slide-6
SLIDE 6

Purple Line Maintenance Facility

6

Maintenance Facility

  • Located in the Arts District, north of 6th St Bridge
  • 590 S Santa Fe Av

Current Work

  • Parking lot paved and striped
  • Sidewalks and landscaping installed
  • Furniture being placed and assembled
  • Artwork installed on west wall approximately mid-June
slide-7
SLIDE 7

Purple Line Maintenance Facility

7

Installing art work on the façade

  • f the building
slide-8
SLIDE 8

Wilshire/Western Connection Schedule

Schedule

8 *As of July 2019, subject to change

slide-9
SLIDE 9

TBMs Break Through

9

Soyeon and Elsie break through at Wilshire/Western

slide-10
SLIDE 10

TBM Transport

10

TBMs being disassembled for transport back to Wilshire/La Brea Station

slide-11
SLIDE 11

Wilshire/La Brea Station

11

slide-12
SLIDE 12

Wilshire/La Brea Station Box

12 12

Rendering shows length of the Wilshire/La Brea underground station box on Wilshire Bl from Orange Dr to Detroit St

slide-13
SLIDE 13

Wilshire/La Brea Station

Schedule

13 *As of July 2019, subject to change

slide-14
SLIDE 14

Wilshire/La Brea Station

Station Construction

Constructing the interior walls Assembling TBM ring on the west end

slide-15
SLIDE 15

Beginning July 2019, STS will restore bus pads at the following locations:

  • Wilshire Bl/Bronson Av
  • Wilshire Bl/Lorraine Bl
  • Wilshire Bl/McCadden Pl
  • Wilshire Bl/ Citrus Av
  • Wilshire Bl/Cloverdale Av
  • Wilshire Bl/McCarthy Vista
  • Wilshire Bl/San Vicente Bl

Example of a Bus Pad along Wilshire Bl

Upcoming Work

Bus Pads and Water Crossings

slide-16
SLIDE 16

Wilshire Bl/Sycamore Av Antenna

Antenna

  • Steel pole, slightly more than 62 feet above the concrete base
  • Less than 12 inches in diameter
  • Radio antenna must be in very close proximity (300 feet maximum) to the

underground station’s communications room (at the east end of the Wilshire/La Brea Station)

  • This eliminates the loss of signal strength.
  • Location provides connectivity to the various emergency response

agencies’ other local and mountain top radio transmitter/receiver sites

  • Location allows the Purple Line radio system to have the coverage it

requires for all users:

  • Metro Operations and Maintenance
  • Public safety (police, fire, Sheriff, and Transit Security) in the

underground stations and tunnels

slide-17
SLIDE 17

Wilshire Bl/Sycamore Av Antenna

Rendering of Antenna

slide-18
SLIDE 18

Wilshire/Fairfax Station

18

slide-19
SLIDE 19

Wilshire/Fairfax Station Box

19 19

Rendering shows length of the Wilshire/Fairfax underground station box on Wilshire Bl from west of Fairfax Av to just west of Ogden Dr

slide-20
SLIDE 20

Wilshire/Fairfax Station Schedule

*As of July 2019, subject to change 20

slide-21
SLIDE 21

Wilshire/Fairfax Station

Station Construction

Installing electrical conduit

slide-22
SLIDE 22

Orange Grove Ave. Closure

Start date September 2019*

  • STS is proposing a full

closure of Orange Grove Av just south of Wilshire Bl for the duration of the project

  • This closure will support the

excavation of appendage structures and successor activities

  • Outreachto the community and

the relevant city agencies has begun

*As of July 2019, subject to change

Closure area

slide-23
SLIDE 23

Wilshire/Fairfax Station

Concrete and Rebar – Ongoing 2019

  • Concrete and rebar (steel) work

anticipated to continue through 2019

  • Work will require worksite traffic

control on the south side of Wilshire Bl from Orange Grove Av to Ogden Dr

  • Off-peak work hours

(9am – 3:30pm; 8pm - 6am)

  • More details to be provided in future

construction notices and briefings

Concrete work shown from the street level at Wilshire/La Brea. Concrete is being pumped underground from the street level. Similar work will be done at the Wilshire/Fairfax Station.

23

slide-24
SLIDE 24

Wilshire/Crescent Heights

Tunnel Investigation, Ongoing through September 2019

24

Approximate work locations at Wilshire/Crescent Heights.

  • Additional investigation wells will

be installed throughout Summer 2019

  • Lane reductions on Wilshire Bl

are anticipated to continue in advance of the tunneling from the Wilshire/Fairfax station

  • Extended work hours may be

required as investigation continues

  • Additional details will be available

in future construction notices

slide-25
SLIDE 25

Directional Drilling

August 2019

  • Beginning August 2019,

STS will be investigating the locations of two abandoned

  • il wells
  • Work will be done at night,

8pm to 6am

  • Intermittent lane closures

along Wilshire Bl will be in place to support investigative drilling

Approximate work location at Wilshire Bl/ La Jolla Av

slide-26
SLIDE 26

Wilshire/La Cienega Station

26

slide-27
SLIDE 27

Wilshire/La Cienega Station Box

27 27

Rendering shows length of the La Cienega underground station box on Wilshire Bl from La Cienega Bl to Tower Dr

slide-28
SLIDE 28

Wilshire/La Cienega Station

*As of July 2019, subject to change 28

slide-29
SLIDE 29

Wilshire/Gale

Intermittent Daily Gale Closure – North of Wilshire Bl

  • Gale Dr will be intermittently

closed Monday to Saturday, 6am to 6pm

  • This closure is a public safety

measure due to high volumes of ingress/egress from the property

  • Access to N Gale Dr will be

maintained from San Vicente Bl

  • Hauling operation to occur until

10pm

29

Gale Dr from north of Wilshire Bl

slide-30
SLIDE 30

Wilshire/La Cienega

30

Removing stockpiled excavation material

slide-31
SLIDE 31

Wilshire/La Cienega – Upcoming Work

Instrumentation Work & Street Maintenance

When: Ongoing through 2019 Instrumentation work on Wilshire Bl and La Cienega Bl

  • Intermittent lane reductions on

Wilshire Bl, La Cienega Bl, and side streets during off-peak hours (non-rush hour) Street Maintenance, Dewatering Well Maintenance, and Utility Work on Wilshire Bl

  • Intermittent lane reductions on Wilshire Bl

and side streets during off-peak hours (non-rush hour)

31

Example of instrumentation drilling

slide-32
SLIDE 32

Wilshire/La Cienega – Upcoming Work

City of Los Angeles

When: Ongoing through 2019 Construction activities on Wilshire Bl between Fairfax Av and San Vicente Bl may require traffic control in the City of Beverly Hills. Work includes, but is not limited to:

  • Geotechnical instrumentation installation
  • Soil improvement
  • Magnetic surveying

Information on this work and the required traffic control will be available via construction notices.

32

slide-33
SLIDE 33

Station Naming Policy

33

Station Names will reflect the following principles:

  • Transit system context: names will reflect the property’s location, relative to the entire

transit system, and not duplicated elsewhere.

  • Property area: provide specific information about the property’s location relative to

the surrounding area.

  • Neighborhood identity: acknowledge the communities and neighborhoods serviced

by the station and stops.

  • Simplicity: names will be short, easily recognizable and fit for signage and mapping.
  • Character limit: preferred maximum of 24 characters to ensure ADA readability and fit

within signage system.

slide-34
SLIDE 34

Name your next Purple Line Stations

34

Metro staff originally developed a set of geographically-based names for the Section 1 Stations and are now seeking community input on those names. Submit your proposals at metro.net/purple

slide-35
SLIDE 35

Section 2

35 35

slide-36
SLIDE 36

Purple Line Extension

Section 2 Alignment

36

slide-37
SLIDE 37

Wilshire/Rodeo Station

slide-38
SLIDE 38

Section 2 Wilshire/Rodeo Station

slide-39
SLIDE 39

Wilshire/Rodeo Station Box

Station Box

39

Rendering shows length of the underground station box on Wilshire Bl from Cañon Dr to Beverly Dr

slide-40
SLIDE 40

Driveway Installation

Staging Yards

40

Where:

  • Wilshire/Reeves Yard: on Reeves Dr
  • N CañonYard: on N CañonDr and Wilshire Bl

Start Date: Mid-July 2019 Anticipated Completion: Early August Work Hours: Monday – Friday, 8am – 6pm Traffic Control:

  • Sidewalk closures adjacent to yards
  • Intermittent closure of curb lane on

westbound Wilshire Bl, northbound N CañonDr, and southbound Reeves Dr from 9am – 4pm

  • For your safety, do not use

streets as a walk way

slide-41
SLIDE 41
  • N. Cañon Staging Yard

Installation of Sound Wall

  • 20-foot sound wall around the staging yard will be installed to mitigate

noise to adjacent properties and public ROW

  • Start Date:Late June 2019
  • Completion Date:Mid-July 2019
  • Work Hours: Monday – Friday, 8am – 6pm

41 *Subject to change

Sound wall and driveway installation progress at N Cañon Yard

slide-42
SLIDE 42

42

Utility Work

*Subject to change

Example of sewer line replacement

  • Potholing work to identify existingutilities

below the street

  • Sewer and water line replacement and

relocation and storm drain lateral replacement Start Date: April 8, 2019 Duration: 6 months* Anticipated Completion: September 2019* Work Hours:

  • Weekdays:9am – 4pm and8:15pm – 7am
  • Weekends: 8am – 8pm

Traffic Control:

  • Lane and crosswalk closures as well as turn restrictions will be required for this work.
  • Two lanes in each direction will be maintained for weekdaywork on Wilshire Bl.
  • One lane in each direction will be maintained for weeknightwork on Wilshire Bl.
  • One lane in each direction for weekend work on Wilshire Bl.
slide-43
SLIDE 43

43

Geotechnical Instrumentation

Installation

Instruments will be installed within the station box area to monitor ground movement, settlement and other geological conditions. These installations will be within the public right of way and within privately owned properties. Start Date: June 24, 2019 Duration: Ongoing Work Hours:

  • Weekdays: 7am – 4pm
  • Weekends: 8am – 7pm (as needed)

Traffic Control

  • Intermittent lane, sidewalk, and crosswalk, parking meter closures will be required for

this work on Wilshire Bl, Beverly Dr, Reeves Dr, N Cañon Dr, S Cañon Dr, and alleys between Beverly Dr and Crescent Dr

  • Flaggers will be available at alleys
  • Two lanes in each direction will be maintained for day work on Wilshire Bl

Example of geotechnical instrument installation in Century City

slide-44
SLIDE 44
  • N. Cañon Drive Closure

Traffic Configuration – September 2019*

Sound wall with art on Cañon Dr side and public information graphics on Wilshire Bl side

  • Install before piling for a minimum of 2 years
  • New traffic signal at Clifton/ Crescent
  • Existing meters/valet spaces on Clifton Way

shift to the north

  • Maintain existing valet time periods
  • Relocate some meters on N Cañon Dr from

East to West side

Pedestrian walkway *Dates subject to change

slide-45
SLIDE 45

Pile Drilling Installation

45

Pile installation includes:

  • Drill rig to drill holes
  • Crane to lift piles into holes
  • Truck to backfill holes
  • All work occurs behind K-rail and/or

traffic closures within station box area, including both north alleys Schedule

  • Following utility relocation, anticipated to start

September 2019* on north side of Wilshire Bl

  • Weekend closures will occur at Wilshire/Beverly

Dr and Wilshire/S Cañon Dr Work Hours

  • 7 days a week
  • 8am – 9pm, drilling
  • 9pm – 11pm, non-drilling

Example of piling work in Century City

*Dates subject to change

slide-46
SLIDE 46

46

Pile Drilling Installation

Example of progress on Constellation Bl

slide-47
SLIDE 47

Wilshire Bl Piling Set-up

North Side Piling Set-up

47

Example of construction area with piling set-up on the north side of Wilshire Bl

slide-48
SLIDE 48

Wilshire Bl Piling Set-up

South Side Piling Set-up

48

Example of construction area with piling set-up on the south side of Wilshire Bl

slide-49
SLIDE 49

Pile Drilling Weekend Installation

49 *Dates subject to change

  • Work Hours: Saturday and Sunday (7am – 8pm) and (8pm – 10pm) for non-drilling and break-

down activities. Traffic control in place Friday, 8pm – Monday, 7am

  • Weekend piling at the following intersections: Beverly Dr and S Canon Dr

– 5 weekend closures for Wilshire/Beverly Dr intersection (Friday 8pm – Monday 7am), for piling and decking, collectively

  • NOTE: Each intersection may take several weekends to complete during north and south side

piling operations

Anticipated weekend closures for piling intersections and alleys

slide-50
SLIDE 50

Piling Plan

50

NORTH SIDE PILING:

  • Start Date: September 2019*
  • End Date: January 2020* (with work

during holiday moratorium)

  • Intersection Closures Required:
  • Wilshire/Beverly Dr

*Dates subject to change

SOUTH SIDE PILING:

  • Start Date: January 2020*
  • End Date: May 2020*
  • Intersection Closures Required:
  • Wilshire/Beverly Dr
  • Wilshire/Reeves Dr
  • Wilshire/S Cañon Dr

Piling will last approximately 4 months on each side

Utility Work Completion (September 2019) N Cañon Dr Wall Completion (September 2019) Piling North Side (September 2019 – January 2020) Piling South Side (January 2020 – May 2020) Decking (Beginning May 2020)

slide-51
SLIDE 51

Decking

Following Piling: Anticipated May 2020*

51

  • Construction of a concrete deck, curb-to-curb
  • n Wilshire Bl
  • Decking will serve as the temporary street

surface

  • Metro will work closely with first responders on

emergency access and safety Duration: Anticipated 13 weekends Work Hours: Full closures Friday, 8pm through Monday, 7am Additional activities under decking closures:

  • Ground improvements, piling, temporary civil

improvements, dewatering system installation and geotechnical instrumentation

Asphalt removal on Wilshire Bl near Detroit St Steel beams welding prior to concrete deck panel installation

*Dates subject to change

slide-52
SLIDE 52

Century City/Constellation Station

52

slide-53
SLIDE 53

Century City/Constellation Station Box

53 53

Rendering shows length of the underground station box on Constellation Bl from Century Park East to Avenue of the Stars

slide-54
SLIDE 54

Century City/Constellation Station Schedule

54

*As of July 2019, subject to change.

slide-55
SLIDE 55

Century City/Constellation

AUR Schedule

55 *As of July 2019, subject to change

slide-56
SLIDE 56

Advance Utility Relocation

Schedule and Work Hours AT&T/DWP

AT&T and DWP (Power) will perform cable pulling activities through 2019

  • Work hours: Monday – Friday, 9am – 4pm and 11pm – 4am

Weekends as needed from 9am – 4pm

  • Work will occur on Constellation Bl east and west of Avenue of the Stars

56 *Dates subject to change

AUR, Constellation Bl west of Avenue of the Stars (before)

slide-57
SLIDE 57

Construction Staging Areas

1940, 1950, 2010 & 2040 Century Park East

Upcoming Activities:

  • Site grading
  • Installation of sound wall behind

AT&T building

  • Excavation within tunnel shaft

Work Hours: Monday – Friday, 6am – 5pm and 7pm – 5am

57 *Dates subject to change

slide-58
SLIDE 58

58

Constellation Bl Full Closure Extension through December 2019

  • No Public Access for Tenants through Driveway
  • Limited Access for: Large Trucks, Deliveries, Construction, Trash, FedEx/UPS
  • Flaggers will be present for access

9-Month Closure Began September 2018

slide-59
SLIDE 59

Excavation began: February 4, 2019

  • Launch Box Dimensions: 250’ L x 65’ W x 90’ D
  • Progress Update:
  • Excavated 48' underground and will continue

until reaching a depth of approximately 100'

  • Hanging utilities completed
  • Continuing installation of infrastructure for

TBMs

  • Following the launch of the TBMs, decking will

serve as temporary roadway surface for the public

  • The sidewalk on the north side of Constellation Bl

will remain open

59

Launch Box Excavation

Overview

*Dates subject to change

Launch box with completed decking

slide-60
SLIDE 60

Constellation Bl Launch Box

Excavation Progress

60

Excavation within Constellation Bl launch box

slide-61
SLIDE 61

Monitoring and Coordination

  • COLA/Metro/ TPOG will monitor traffic
  • Turn lanes will remain open for use (except for full

street closure on weekends)

  • Access to driveways & entrances will be maintained

(except for weekends)

  • Access for Emergency Vehicles & First Responders will

be maintained

61

slide-62
SLIDE 62

Launch of Tunnel Boring Machines

  • Harriet and Ruth will dig the twin

tunnels for Section 2

  • Anticipated Launch:

Late Summer 2019

  • Excavation Duration: 2 years
  • Extraction Location: Wilshire Bl/

La Cienega Bl

62

slide-63
SLIDE 63

West Closure of Constellation Bl

  • Constellation Bl closure will be extended west of the

launch box to Solar Way

  • Coordinating directly with Westfield Mall, Century

Plaza Hotel, and Constellation Park projects

  • Anticipated Start Date: Early 2020
  • Activities to Occur:
  • Piling
  • Decking
  • Excavation

63

slide-64
SLIDE 64

Santa Monica Bl Bus Layover

64

Start Date: October 2018 Anticipated Completion Date: July 2019 Work Hours: Monday – Friday, 6am – 2:30pm and 7pm – 6am Traffic Control:

  • Intermittent lane closures on Santa Monica Bl during non-peak hours Metro

bus lines 4, 704, 16, 316 will continue to be detoured until completion of bus layover work

Median bus layover work in progress

*Dates subject to change

slide-65
SLIDE 65

Section 3

65

slide-66
SLIDE 66

Purple Line Extension

Section 3 Alignment

66

slide-67
SLIDE 67

67

Section 3 Tentative Schedule

Shaft

*Dates are preliminary and subject to change

slide-68
SLIDE 68

68

Westwood/UCLA

Station Rendering

68

slide-69
SLIDE 69

69 69

Westwood/UCLA Station Outline

69

slide-70
SLIDE 70

70

Northeast Full Entrance – Chase Bank

Proposed Full Entrance Inside Chase Bank

slide-71
SLIDE 71

Westwood/UCLA

Schedule – Key Dates*

71

VA Medical Center Historic District

*Dates are approximate and subject to change.

Activity Forecast Start Forecast Finish Advance Utility Relocation (AUR) Spring 2018 Spring 2020 End-wall piling at UCLA Station Spring 2020 Fall 2020 City sewer/storm drain relocation Fall 2020 Spring 2021 Station piling and decking Spring 2021 Spring 2022

slide-72
SLIDE 72

Advanced Utility Relocation (AUR)

Spring 2018 – Spring 2020

slide-73
SLIDE 73

End-Wall Piling

73 APPROXIMATE DURATION: 7 WEEKS HOURS: 24/7

slide-74
SLIDE 74

End-Wall Piling

74

slide-75
SLIDE 75

Westwood/VA Hospital

Current Station Rendering

75

slide-76
SLIDE 76

76

3-D Rendering Westwood/VA Station

View from Bonsall Ave - North to South

slide-77
SLIDE 77

77

Passenger Pick-up/Drop-off

Current Design

  • Short term passenger drop-off and pick up (15-30 minutes max)
  • Designed to minimize traffic congestion while maintaining

pedestrian and commuter access

slide-78
SLIDE 78

Westwood/VA Hospital Station Box

78 78

Rendering shows length of the underground station box on Wilshire Bl and Bonsall Av

slide-79
SLIDE 79

Westwood/VA Hospital

Schedule of upcoming work

79

VA Medical Center Historic District

*Dates are approximate and subject to change.

Activity Forecast Start Forecast Finish Subsurface Geotechnical Investigations June 2019 August 2019 Preconstruction Survey/ Monitoring June 2019 December 2022 SCE Duct bank on Ohio Av July 2019 March 2020 SCE Duct bank on Federal Av July 2019 March 2020 SCE Duct bank on Wilshire Bl August 2019 March 2020 Construction Staging Yard October 2019 December 2019

slide-80
SLIDE 80

Pedestrian and Vehicular Access to Bonsall Av Maintained

80 STAGE 1 STAGE 2

TRAFFIC CONTROL DEVICES TRAFFIC CONTROL DEVICES CONCRETE BARRIER (K-RAIL) CONCRETE BARRIER (RAIL) PILE CORRIDOR PILE CORRIDOR SIDEWALK CLOSED SIDEWALK OPEN SIDEWALK OPEN SIDEWALK CLOSED 12’ 12’ 12’ 12’ WORK AREA WORK AREA

* Subject to change

slide-81
SLIDE 81

81

VA Construction Vehicles

Stage 1 – Major Truck Trips

End wall Piling = 13 trucks/day Spring - Summer 2020 Instrumentation Summer 2019 – Spring 2020 Shaft Excavation = 50 trucks/day Summer 2019 – Spring 2020 Instrumentation Summer 2019 – Spring 2020

* Subject to change

slide-82
SLIDE 82

Station/TBM Power Connection

Upcoming SCE Underground Electrical Work

82 SCE Work Path

  • Work anticipated to begin on Ohio Av, at

Purdue with intermittent parking restrictions and traffic detours expected

  • Intermittent left turn restrictions will be

enforced with Traffic Control Officers

  • Potential for two stages to occur

simultaneously

  • Upgrade will provide power necessary

for construction and tunneling activities and operations of the future Westwood/VA Hospital Station

slide-83
SLIDE 83

SCE Proposed Schedule Options for Ohio Av

83

Option Work Hours (Productive Hours) Duration of work on Ohio Current Plan: Non-Peak 9am to 3:30pm 7 months Option 2: Night Work 9pm to 6am 5 months Option 3: AM Peak 6am to 4pm 4 months Option 4: All of the above

  • Non peak
  • Night work
  • AM Peak

9am to 3:30pm 3 months 6am to 4pm 9pm to 6am

Benefits of more work hours:

  • Shorter construction schedule
  • Less impact to community
slide-84
SLIDE 84

Metro Services for Veterans

Metro’s Veterans Hiring Initiative Program

  • 6% Annual Veteran Hiring Initiative
  • Currently exceeding goal at 7%
  • Support and promote economic development for veterans
  • Attract qualified talent and their spouses for the many positions & apply

transferrable skills to Industry

  • Leverage those skills, knowledge, & attributes to showcase military experience
  • Educate Veteran Community of Broad/Diverse Opportunities
  • Advocate for Veteran Employees & Jobseekers

Application for Discounted TAP Cards for Service Connected Veterans Translation of Military Experience into Civilian Job Skills

slide-85
SLIDE 85

85

3875 Wilshire Bl, Suite 1401 Los Angeles, CA 90010 (562)547-8978

slide-86
SLIDE 86

86

5115 Wilshire Bl, Los Angeles, CA 90036 (877) 224-0954

slide-87
SLIDE 87

225 N Canon Dr Beverly Hills, CA 90210 (310) 860-7800

87

slide-88
SLIDE 88

88

Century Plaza Towers 2049 Century Park East Century City, CA 90067 (310)592-0464

slide-89
SLIDE 89

Helping local businesses as we build. Purple Line Extension Update

slide-90
SLIDE 90

BIF Information and Eligibility

> Financial assistance to small “mom and pop” businesses with 25

  • r fewer full-time employees directly impacted by Metro Rail

construction along three project areas > Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements > Grant amount determined by loss of business revenue related to period of construction disruption > Businesses are eligible for up to $50,000 per impact year

slide-91
SLIDE 91

BIF Information and Eligibility

> To date, 936 grants have been awarded with a total value of more than $22.4 million along all three project areas > Crenshaw/LAX Transit Project > Regional Connector, Little Tokyo area > Purple Line Extension Section 1 and Section 2 > February 2019 Metro’s Board of Directors authorized the expansion of the BIF to Section 3 of the Purple Line Extension

slide-92
SLIDE 92

BIF Grant Award Update

> Purple Line Extension Section 1 (as of 7/12/19) > BIF Grants Awarded: 198 > BIF Grant Amount Awarded: $5,142,660.09 > Number of small businesses awarded: 76 > BIF Business Advisor: Brian Lazo > Pacific Coast Regional Small Business Development Corporation (PCR) > 213.739.2999

slide-93
SLIDE 93

BIF Grant Award Update

> Purple Line Extension Section 2 (as of 7/12/19) > BIF Grants Awarded: 50 > BIF Grant Amount Awarded: $1,393,595.28 > Number of small businesses awarded: 30 > BIF Business Advisor: Darrell Smith > Pacific Coast Regional Small Business Development Corporation (PCR) > 213.739.2999

slide-94
SLIDE 94

BIF Grant Award Update

> Purple Line Extension, Section 3 > BIF Business Advisor: Darrell Smith > Pacific Coast Regional Small Business Development Corporation (PCR) > Phone: 213.739.2999

94

Approved by the Metro Board

slide-95
SLIDE 95

La Cienega and Rodeo Stations Wednesday, August 7, 2019 12pm – 1pm

Link to the online meeting: Webex Access Code: 804 613 256 | Password: Purple Join by phone: 1-650-479-3207 (toll-free)

95

Lunch with Us: Public Webinar

Beverly Hills

slide-96
SLIDE 96

Updates on La Cienega and Rodeo Stations Wednesday, August 7, 2019 6:30pm – 8pm Beverly Hills City Hall 2nd Floor Municipal Gallery 445 N Rexford Dr Beverly Hills, CA 90210 *On-site parking free after 5pm

96

Next Community Meeting

Beverly Hills

slide-97
SLIDE 97

Section 2: Construction Community Meeting Thursday, August 15, 2019 6:30pm – 8pm

Century Plaza Towers 2029 Century Park East Los Angeles, CA 90067 Concourse Level D, Room A

*Parking will be validated

97

Next Community Meeting

Section 2

slide-98
SLIDE 98

Section 3: Pre-Construction Community Meeting Thursday, September 19 6:30pm – 8pm Belmont Village Senior Living 10475 Wilshire Bl Los Angeles, CA 90024 Free on-site parking available

98

Next Community Meeting

Section 3

slide-99
SLIDE 99

Section 1: Construction Community Meeting Thursday, October 17, 2019 6:30pm – 7:30pm

Cathedral Catholic School (Tentatively) 755 S Cochran Av, Los Angeles, CA 90036

99

Next Community Meeting

Section 1

slide-100
SLIDE 100

Stay in Touch