Purple Line Extension
Community Webinar July 24, 2019
1
Purple Line Extension Community Webinar - - PowerPoint PPT Presentation
Purple Line Extension Community Webinar July 24, 2019 1 Agenda Section 1 Update Section 2 Update Section 3 Update Eat Shop Play Business Interruption Fund Questions
Community Webinar July 24, 2019
1
2
Project Alignment
3
4 *Subject to change. The PLE project team is working to deliver the project consistent with Measure M
Forecasted Schedule Section
Section 1 Section 2 Section 3
Length
3.92 Miles 2.59 Miles 2.56 Miles
New Stations
Wilshire/La Brea Wilshire/Fairfax Wilshire/La Cienega Wilshire/Rodeo Century City/ Constellation Westwood/UCLA Westwood/VA Hospital
Pre-Construction Activities
2014 – 2015 2016 – 2018 2018 – 2019
Construction
2015 – 2023 2018 – 2025 2019 – 2027
Operations
2023 2025 2027
Section 1 Alignment
5
6
Maintenance Facility
Current Work
7
Installing art work on the façade
Schedule
8 *As of July 2019, subject to change
9
Soyeon and Elsie break through at Wilshire/Western
10
TBMs being disassembled for transport back to Wilshire/La Brea Station
11
12 12
Rendering shows length of the Wilshire/La Brea underground station box on Wilshire Bl from Orange Dr to Detroit St
Schedule
13 *As of July 2019, subject to change
Station Construction
Constructing the interior walls Assembling TBM ring on the west end
Beginning July 2019, STS will restore bus pads at the following locations:
Example of a Bus Pad along Wilshire Bl
Bus Pads and Water Crossings
Antenna
underground station’s communications room (at the east end of the Wilshire/La Brea Station)
agencies’ other local and mountain top radio transmitter/receiver sites
requires for all users:
underground stations and tunnels
Rendering of Antenna
18
19 19
Rendering shows length of the Wilshire/Fairfax underground station box on Wilshire Bl from west of Fairfax Av to just west of Ogden Dr
*As of July 2019, subject to change 20
Station Construction
Installing electrical conduit
Start date September 2019*
closure of Orange Grove Av just south of Wilshire Bl for the duration of the project
excavation of appendage structures and successor activities
the relevant city agencies has begun
*As of July 2019, subject to change
Closure area
Concrete and Rebar – Ongoing 2019
anticipated to continue through 2019
control on the south side of Wilshire Bl from Orange Grove Av to Ogden Dr
(9am – 3:30pm; 8pm - 6am)
construction notices and briefings
Concrete work shown from the street level at Wilshire/La Brea. Concrete is being pumped underground from the street level. Similar work will be done at the Wilshire/Fairfax Station.
23
Tunnel Investigation, Ongoing through September 2019
24
Approximate work locations at Wilshire/Crescent Heights.
be installed throughout Summer 2019
are anticipated to continue in advance of the tunneling from the Wilshire/Fairfax station
required as investigation continues
in future construction notices
August 2019
STS will be investigating the locations of two abandoned
8pm to 6am
along Wilshire Bl will be in place to support investigative drilling
Approximate work location at Wilshire Bl/ La Jolla Av
26
27 27
Rendering shows length of the La Cienega underground station box on Wilshire Bl from La Cienega Bl to Tower Dr
*As of July 2019, subject to change 28
Intermittent Daily Gale Closure – North of Wilshire Bl
closed Monday to Saturday, 6am to 6pm
measure due to high volumes of ingress/egress from the property
maintained from San Vicente Bl
10pm
29
Gale Dr from north of Wilshire Bl
30
Removing stockpiled excavation material
Instrumentation Work & Street Maintenance
When: Ongoing through 2019 Instrumentation work on Wilshire Bl and La Cienega Bl
Wilshire Bl, La Cienega Bl, and side streets during off-peak hours (non-rush hour) Street Maintenance, Dewatering Well Maintenance, and Utility Work on Wilshire Bl
and side streets during off-peak hours (non-rush hour)
31
Example of instrumentation drilling
City of Los Angeles
When: Ongoing through 2019 Construction activities on Wilshire Bl between Fairfax Av and San Vicente Bl may require traffic control in the City of Beverly Hills. Work includes, but is not limited to:
Information on this work and the required traffic control will be available via construction notices.
32
33
Station Names will reflect the following principles:
transit system, and not duplicated elsewhere.
the surrounding area.
by the station and stops.
within signage system.
34
Metro staff originally developed a set of geographically-based names for the Section 1 Stations and are now seeking community input on those names. Submit your proposals at metro.net/purple
35 35
Section 2 Alignment
36
Station Box
39
Rendering shows length of the underground station box on Wilshire Bl from Cañon Dr to Beverly Dr
Staging Yards
40
Where:
Start Date: Mid-July 2019 Anticipated Completion: Early August Work Hours: Monday – Friday, 8am – 6pm Traffic Control:
westbound Wilshire Bl, northbound N CañonDr, and southbound Reeves Dr from 9am – 4pm
streets as a walk way
Installation of Sound Wall
noise to adjacent properties and public ROW
41 *Subject to change
Sound wall and driveway installation progress at N Cañon Yard
42
*Subject to change
Example of sewer line replacement
below the street
relocation and storm drain lateral replacement Start Date: April 8, 2019 Duration: 6 months* Anticipated Completion: September 2019* Work Hours:
Traffic Control:
43
Installation
Instruments will be installed within the station box area to monitor ground movement, settlement and other geological conditions. These installations will be within the public right of way and within privately owned properties. Start Date: June 24, 2019 Duration: Ongoing Work Hours:
Traffic Control
this work on Wilshire Bl, Beverly Dr, Reeves Dr, N Cañon Dr, S Cañon Dr, and alleys between Beverly Dr and Crescent Dr
Example of geotechnical instrument installation in Century City
Traffic Configuration – September 2019*
Sound wall with art on Cañon Dr side and public information graphics on Wilshire Bl side
shift to the north
East to West side
Pedestrian walkway *Dates subject to change
45
Pile installation includes:
traffic closures within station box area, including both north alleys Schedule
September 2019* on north side of Wilshire Bl
Dr and Wilshire/S Cañon Dr Work Hours
Example of piling work in Century City
*Dates subject to change
46
Example of progress on Constellation Bl
North Side Piling Set-up
47
Example of construction area with piling set-up on the north side of Wilshire Bl
South Side Piling Set-up
48
Example of construction area with piling set-up on the south side of Wilshire Bl
49 *Dates subject to change
down activities. Traffic control in place Friday, 8pm – Monday, 7am
– 5 weekend closures for Wilshire/Beverly Dr intersection (Friday 8pm – Monday 7am), for piling and decking, collectively
piling operations
Anticipated weekend closures for piling intersections and alleys
50
NORTH SIDE PILING:
during holiday moratorium)
*Dates subject to change
SOUTH SIDE PILING:
Piling will last approximately 4 months on each side
Utility Work Completion (September 2019) N Cañon Dr Wall Completion (September 2019) Piling North Side (September 2019 – January 2020) Piling South Side (January 2020 – May 2020) Decking (Beginning May 2020)
Following Piling: Anticipated May 2020*
51
surface
emergency access and safety Duration: Anticipated 13 weekends Work Hours: Full closures Friday, 8pm through Monday, 7am Additional activities under decking closures:
improvements, dewatering system installation and geotechnical instrumentation
Asphalt removal on Wilshire Bl near Detroit St Steel beams welding prior to concrete deck panel installation
*Dates subject to change
52
53 53
Rendering shows length of the underground station box on Constellation Bl from Century Park East to Avenue of the Stars
54
*As of July 2019, subject to change.
AUR Schedule
55 *As of July 2019, subject to change
Schedule and Work Hours AT&T/DWP
AT&T and DWP (Power) will perform cable pulling activities through 2019
Weekends as needed from 9am – 4pm
56 *Dates subject to change
AUR, Constellation Bl west of Avenue of the Stars (before)
1940, 1950, 2010 & 2040 Century Park East
Upcoming Activities:
AT&T building
Work Hours: Monday – Friday, 6am – 5pm and 7pm – 5am
57 *Dates subject to change
58
9-Month Closure Began September 2018
Excavation began: February 4, 2019
until reaching a depth of approximately 100'
TBMs
serve as temporary roadway surface for the public
will remain open
59
Overview
*Dates subject to change
Launch box with completed decking
Excavation Progress
60
Excavation within Constellation Bl launch box
61
62
63
64
Start Date: October 2018 Anticipated Completion Date: July 2019 Work Hours: Monday – Friday, 6am – 2:30pm and 7pm – 6am Traffic Control:
bus lines 4, 704, 16, 316 will continue to be detoured until completion of bus layover work
Median bus layover work in progress
*Dates subject to change
65
Section 3 Alignment
66
67
Shaft
*Dates are preliminary and subject to change
68
Station Rendering
68
69 69
69
70
Proposed Full Entrance Inside Chase Bank
Schedule – Key Dates*
71
VA Medical Center Historic District
*Dates are approximate and subject to change.
Activity Forecast Start Forecast Finish Advance Utility Relocation (AUR) Spring 2018 Spring 2020 End-wall piling at UCLA Station Spring 2020 Fall 2020 City sewer/storm drain relocation Fall 2020 Spring 2021 Station piling and decking Spring 2021 Spring 2022
Spring 2018 – Spring 2020
73 APPROXIMATE DURATION: 7 WEEKS HOURS: 24/7
74
Current Station Rendering
75
76
View from Bonsall Ave - North to South
77
Current Design
pedestrian and commuter access
78 78
Rendering shows length of the underground station box on Wilshire Bl and Bonsall Av
Schedule of upcoming work
79
VA Medical Center Historic District
*Dates are approximate and subject to change.
Activity Forecast Start Forecast Finish Subsurface Geotechnical Investigations June 2019 August 2019 Preconstruction Survey/ Monitoring June 2019 December 2022 SCE Duct bank on Ohio Av July 2019 March 2020 SCE Duct bank on Federal Av July 2019 March 2020 SCE Duct bank on Wilshire Bl August 2019 March 2020 Construction Staging Yard October 2019 December 2019
80 STAGE 1 STAGE 2
TRAFFIC CONTROL DEVICES TRAFFIC CONTROL DEVICES CONCRETE BARRIER (K-RAIL) CONCRETE BARRIER (RAIL) PILE CORRIDOR PILE CORRIDOR SIDEWALK CLOSED SIDEWALK OPEN SIDEWALK OPEN SIDEWALK CLOSED 12’ 12’ 12’ 12’ WORK AREA WORK AREA
* Subject to change
81
VA Construction Vehicles
End wall Piling = 13 trucks/day Spring - Summer 2020 Instrumentation Summer 2019 – Spring 2020 Shaft Excavation = 50 trucks/day Summer 2019 – Spring 2020 Instrumentation Summer 2019 – Spring 2020
* Subject to change
Upcoming SCE Underground Electrical Work
82 SCE Work Path
Purdue with intermittent parking restrictions and traffic detours expected
enforced with Traffic Control Officers
simultaneously
for construction and tunneling activities and operations of the future Westwood/VA Hospital Station
83
Option Work Hours (Productive Hours) Duration of work on Ohio Current Plan: Non-Peak 9am to 3:30pm 7 months Option 2: Night Work 9pm to 6am 5 months Option 3: AM Peak 6am to 4pm 4 months Option 4: All of the above
9am to 3:30pm 3 months 6am to 4pm 9pm to 6am
Benefits of more work hours:
Metro’s Veterans Hiring Initiative Program
transferrable skills to Industry
Application for Discounted TAP Cards for Service Connected Veterans Translation of Military Experience into Civilian Job Skills
85
3875 Wilshire Bl, Suite 1401 Los Angeles, CA 90010 (562)547-8978
86
5115 Wilshire Bl, Los Angeles, CA 90036 (877) 224-0954
225 N Canon Dr Beverly Hills, CA 90210 (310) 860-7800
87
88
Century Plaza Towers 2049 Century Park East Century City, CA 90067 (310)592-0464
Helping local businesses as we build. Purple Line Extension Update
> Financial assistance to small “mom and pop” businesses with 25
construction along three project areas > Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements > Grant amount determined by loss of business revenue related to period of construction disruption > Businesses are eligible for up to $50,000 per impact year
> To date, 936 grants have been awarded with a total value of more than $22.4 million along all three project areas > Crenshaw/LAX Transit Project > Regional Connector, Little Tokyo area > Purple Line Extension Section 1 and Section 2 > February 2019 Metro’s Board of Directors authorized the expansion of the BIF to Section 3 of the Purple Line Extension
> Purple Line Extension Section 1 (as of 7/12/19) > BIF Grants Awarded: 198 > BIF Grant Amount Awarded: $5,142,660.09 > Number of small businesses awarded: 76 > BIF Business Advisor: Brian Lazo > Pacific Coast Regional Small Business Development Corporation (PCR) > 213.739.2999
> Purple Line Extension Section 2 (as of 7/12/19) > BIF Grants Awarded: 50 > BIF Grant Amount Awarded: $1,393,595.28 > Number of small businesses awarded: 30 > BIF Business Advisor: Darrell Smith > Pacific Coast Regional Small Business Development Corporation (PCR) > 213.739.2999
> Purple Line Extension, Section 3 > BIF Business Advisor: Darrell Smith > Pacific Coast Regional Small Business Development Corporation (PCR) > Phone: 213.739.2999
94
Link to the online meeting: Webex Access Code: 804 613 256 | Password: Purple Join by phone: 1-650-479-3207 (toll-free)
95
Beverly Hills
96
Beverly Hills
*Parking will be validated
97
Section 2
98
Section 3
99
Section 1
100