Quick planning using "S" curves and cost based durations - - PowerPoint PPT Presentation

quick planning using s curves
SMART_READER_LITE
LIVE PREVIEW

Quick planning using "S" curves and cost based durations - - PowerPoint PPT Presentation

Quick planning using "S" curves and cost based durations Fernando Valderrama, Presto Rafael Guadalupe, UPM Objective Fully automated model for quick planning based on the project cost estimate Total duration Allocation of


slide-1
SLIDE 1

Quick planning using "S" curves and cost based durations

Fernando Valderrama, Presto Rafael Guadalupe, UPM

slide-2
SLIDE 2

Objective

2

Fully automated model for quick planning based on the project cost estimate

  • Total duration
  • Allocation of cost over time
  • Defining and sequencing activities
  • Activities duration
  • Number of crews
slide-3
SLIDE 3

Estimating total duration

3

Relationship between cost and time (BCIS, 2009) Use Duration (weeks) General 22.4 x LOG (€) - 91 Collective housing 33 x LOG (€) - 146 Single family 31 x LOG (€) - 131

slide-4
SLIDE 4

Allocation of cost over time

Expenses by periods (Lara and Dinsmore)

4

slide-5
SLIDE 5

Defining and sequencing activities

5

Activities sequencing and cost allocation based on “S” curve (Presto)

slide-6
SLIDE 6

Activities duration

6

Activity duration = (Activity cost / Total cost) ^ (1 - V) x Total duration Based on

  • Proportionality between activity (resources) cost and

duration and total (resources) cost and duration

  • Estimation of the number of simultaneous activities
  • Correction for activity size
  • A simultaneity coefficient V (0 = serial, 1 = parallel)

is inserted to adapt to different situations

slide-7
SLIDE 7

Final result

7

  • No. of crews = Time based duration / Cost based duration

Presto

slide-8
SLIDE 8

Planned vs. calculated durations

8

Commercial center Activities at division level, V = 0,6

slide-9
SLIDE 9

Planned vs. calculated durations

9

Residential building Activities at work unit level, V = 0,4

slide-10
SLIDE 10

Future work

10

  • Refine and validate the model for different

project types and sizes

slide-11
SLIDE 11

Conclusions

11

Starting from an estimate, the methodology is completely automatic, with the following decision points:

  • Applying the BCIS expression
  • Checking the sequential order
  • Selecting the right “S” curve for the project
  • Deciding the simultaneity coefficient
slide-12
SLIDE 12

Thank you