Reserve and Resource and LOM Update MARCH 21, 2014 Forward Looking - - PowerPoint PPT Presentation

reserve and resource and lom update
SMART_READER_LITE
LIVE PREVIEW

Reserve and Resource and LOM Update MARCH 21, 2014 Forward Looking - - PowerPoint PPT Presentation

Reserve and Resource and LOM Update MARCH 21, 2014 Forward Looking STATEMENTS Certain information included in this news release constitutes 'forward-looking statements' within the meaning of the 'safe harbor' provisions of the United States


slide-1
SLIDE 1

Reserve and Resource and LOM Update

MARCH 21, 2014

slide-2
SLIDE 2

1

Forward Looking

STATEMENTS

Certain information included in this news release constitutes 'forward-looking statements' within the meaning of the 'safe harbor' provisions of the United States Private Securities Litigation Reform Act of 1995 and Canadian securities laws. The words 'expect', 'believe', 'will', ‘target’, ‘forecast’, ‘anticipate’, ‘plan’, 'guidance', and similar expressions identify forward- looking statements. Such statements include, without limitation, any information as to our future financial or operating performance, including: the Company's forward looking production guidance, projected capital expenditures, operating cost estimates, project timelines, mining and milling rates, projected grades, mill recoveries, and other statements that express management's expectations or estimates of future performance. Forward-looking statements are necessarily based upon a number of factors and assumptions that, while considered reasonable by management, are inherently subject to significant business, economic and competitive uncertainties and

  • contingencies. The factors and assumptions contained in this news release, which may prove to be incorrect, include, but

are not limited to: that metal prices will be consistent with the Company's expectations, that the exchange rate between the Canadian dollar and the United States dollar will be consistent with the Company's expectations, that there will be no significant disruptions or delays affecting operations or development projects, including the LDI mine expansion, that production and cash cost per ounce will meet expectations, that prices for key mining and construction supplies, including labour and transportation costs, will remain consistent with the Company's expectations, and that the Company's current estimates of mineral reserves and resources are accurate. The forward-looking statements are not guarantees of future performance. The Company cautions the reader that such forward-looking statements involve known and unknown risks that may cause the actual results to be materially different from those expressed or implied by the forward-looking statements. Such risks include, but are not limited to: the possibility that metal prices, foreign exchange rates, operating costs, production or cash cost per ounce may differ from management's expectations, inherent risks associated with mining and processing, the risk that the Lac des Iles mine may not perform as planned and that the Offset Zone and other properties may not be successfully developed, the possibility of construction and commissioning delays, the possibility of project cost overruns, uncertainty of mineral reserves and resources, and uncertainty of the ability of the Company to obtain financing. For more details on the factors, assumptions and risks see the Company's most recent Form 40-F/Annual Information Form on file with the U.S. Securities and Exchange Commission and Canadian provincial securities regulatory authorities. The Company disclaims any obligation to update or revise any forward-looking statements, whether as a result of new information, events or otherwise, except as expressly required by

  • law. Readers are cautioned not to put undue reliance on these forward-looking statements.

All dollar amounts in Canadian currency unless otherwise stated, all references to production refer to payable production, and all reference to tonnes refer to metric tonnes.

slide-3
SLIDE 3

2

2014

  • Total R+R of 5.2M ounces of contained Pd, an increase of 24% above Jan. 2013

technical report

  • Underground reserve accounts for 9.2M tonnes at diluted grade of 3.9 g/t Pd
  • Total reserve increased by 140,000 oz of contained Pd to 1.3M oz
  • Total resources increased by 860,000 oz of contained Pd to total of 3.9M oz
  • Current mine life extended by one year to 2019
  • Annual production will peak at more than 200,000 oz
  • Total mined reserve of 1.1M payable Pd oz, an increase of 34% from 2013
  • Management focus on advancing work to potentially extend LOM through

successful conversion of resources into reserves

RESERVE AND RESOURCE HIGHLIGHTS

slide-4
SLIDE 4

3

2014

  • Palladium production and operating costs ahead of guidance in January and

February

  • Several large stopes in production cycle and significant broken ore inventory
  • Tonnage mined per plan and grade above guidance
  • Mill recoveries ahead of plan year to date
  • Short-term ore handling solutions in place, on track for permanent measures in H2

2014

  • Making progress towards goal of higher mine production rates and lower unit

costs by year end

YEAR TO DATE OPERATIONS UPDATE

slide-5
SLIDE 5

4

2014

  • The January 2013 Technical Report considered the mining of the LDI offset zone only
  • the 2014 report has been an extensive and all encompassing review of all geological

information and mineral inventory at the LDI site and included:

  • New geological block models rigorously tested for potential economic extraction

to support inclusion as resources, completed by LDI resource geologists with review by Tetra Tech

  • A mine plan, at a PFS level, completed by Tetra Tech with review and input from

LDI to convert resources to reserves – The main changes in the mining plan are:

  • The Offset zone reserve is now down to 1065 L from 990 L previously
  • Remnant material in the Roby zone including higher grade sill pillars and large

lower grade bulk stopes

  • Inclusion of the low grade stockpile on surface
  • A final salvage mining of the pit

LIFE OF MINE OVERVIEW

slide-6
SLIDE 6

5

2014

  • Life of Mine is end of 2018 for underground and 2019 with Open Pit
  • Underground mine increases to 5000 tpd and total payable Pd increases to
  • approx. 200,000 oz per year up from 140,000 in the 2013 report.
  • 1.1 million Payable ounces of Pd produced an increase of 140,000 ounces from

2013, despite mining depletion.

  • Annual mill throughput, including low grade blended material is expected to be

2.6M tonnes.

  • A large open stope blast hole method with waste for fill remains the mining

method as has been successfully done at LDI for several years.

  • Total site capital of $143M

LIFE OF MINE HIGHLIGHTS

slide-7
SLIDE 7

6

LIFE OF MINE

ECONOMIC SUMMARY

Lac Des Iles LOM Economics Current Prices (US$770 Pd) Study Prices (US$700 Pd) Gross Revenue $1,400 M $1,220 M Operating Margin $476 M $336 M Post Tax Cash Flow $362 M $195 M NPV @ 5% $324 M $173 M Cash Cost US$/oz $421 $441

  • Mine economics are most affected by:
  • Foreign exchange rate
  • Palladium price
slide-8
SLIDE 8

7

CAPITAL REQUIREMENTS FOR 2014

  • Underground development
  • Ventilation system upgrade at depth
  • TMF expansion to meet LOM requirements
  • Normal equipment fleet replacement, surface and

underground

slide-9
SLIDE 9

8

LDI OPTIMIZATION OPPORTUNITIES

  • Longer mill runs with additional RGO (low grade

stockpile)

  • Mining of Tailings

– Requires engineering and technical solutions and capital

  • investment. Studies to be completed.
  • Future Mining of the low grade footwall resource

– May be economic at higher production rates and metal prices – All infrastructure in place to mine the higher grade HW zone.

  • Deepen the shaft to exploit resources at depth

– Requires additional drilling and resource conversion – Potential for higher mining volumes at lower unit costs

slide-10
SLIDE 10

9

PLAN FOR THE PHASE 2 PROJECT

  • Advancing the Phase 2 Shaft Deepening project in a

structured and rigorous process is critical:

– Best business case for NAP, with higher production at lower cost – Realizing the potential of one of the best Palladium projects – Building value for shareholders

  • Scoping studies for shaft deepening and TMF to be

completed by mid year

  • Enhanced diamond drilling program approved pending

financing

  • A PFS level study to start by year-end
slide-11
SLIDE 11

10

2014 RESERVE AND RESOURCE ESTIMATES

Net Change in Total Reserves and Resources in Terms of Contained Palladium

Contained Pd (M oz) Increase Category Current R&R Previous R&R Pd (M oz) (%) M&IND Resources 3.86 3.00 0.86 28 P&P Reserves 1.34 1.20 0.14 12 Reserves and Resources* 5.20 4.20 1.00 24

*Excludes Inferred Resources ** Numbers may differ than those in the press release due to rounding

slide-12
SLIDE 12

11

2014 RESERVE AND RESOURCE ESTIMATES

Summary of the 2014 Resource and Reserve Estimate for the Lac des Iles Mine Property

Source Zone Category Tonnes (000’s) Pd (g/t) Pd (k oz contained)

Near Surface All 2P Reserves 5,885 1.03 195 Near Surface All Resources 26,030 1.44 1,205 Underground Hangingwall 2P Reserves 9,161 3.89 1,146 Underground Hangingwall Resources* 5,651 4.25 773 Underground Footwall 2P Reserves nil

  • Underground

Footwall Resources 26,322 2.24 1,894 Underground Roby & Offset Inferred 15,720 2.77 1,400 TOTALS All Sources Reserves & Resources* 73,050 2.22 5,213

slide-13
SLIDE 13

12

CHANGES TO LDI RESERVE AND RESOURCE ESTIMATES: INTRODUCING HANGINGWALL AND FOOTWALL ZONES

  • A new resource and reserve

classification has been adopted

  • Roby and Offset zones are now

subdivided into separate hangingwall and footwall zones

  • Previously the footwall and

hangingwall resources were combined

  • Adding 26 million tonnes of M&IND

resources grading ~2.2 g/t from the two underground footwall zones

Cross Section, Looking North

slide-14
SLIDE 14

13

Comparison of 2012 and 2014 MR&MR:

Offset Zone measured and indicated resources at a 2.5 g/t Pd Cut-Off

Longitudinal sections, Offset Zone, looking west. For 2012 R&R estimate, only material above a 2.5 g/t Pd cut-off grade was captured. This year, both hangingwall and footwall zones have been defined.

Shaft pillar

2012 Resources

Shaft pillar New stopes added to LOM plan

  • n the 1065 level

2014 Resources 1000 m Level

Resource Zone Colour 2014 Hangingwall 2014 Footwall 2012 Global

500 m Level

slide-15
SLIDE 15

14

Comparison of 2012 and 2014 MR&MR:

Roby Zone 2P Reserves Added

Longitudinal section, northern Roby Zone, looking northwest. For 2014, the Roby 6 Block, two sill pillars and material from the bottom of the current resource shell have been added to the LOM plan. All of these new reserves (shown in red) report to the Roby underground hangingwall zone.

Offset Fault Plane

SW NE

Roby Lower Stope (650 L) Roby 6 Block (525 to 585 L) Roby Upper Sill Pillar (345 L) Roby Lower Sill Pillar (585 L) Roby Zone 1 g/t Pd resource shell

slide-16
SLIDE 16

15

Comparison of 2012 and 2014 MR&MR:

Roby Zone Remaining Reserves and Resources

Representative cross section of the Roby Zone, looking north. For 2014, 500 k oz of contained Pd in 6.5 M tonnes of Measured and Indicated Resources have been added from the Roby footwall

  • zone. In addition, and outside of this resources, a small reserve (pit salvage) was added from the

bottom/west part of the pit.

Roby Pit W E

Roby Footwall Zone Resource Shell Roby Hangingwall Zone Resource Shell (mined out)

Undeveloped sill pillar (345 level) – now in reserve Pit salvage reserve

slide-17
SLIDE 17

16

Comparison of 2012 and 2014 MR&MR:

Roby Open Pit Expansion Resources Including Pit Salvage Reserves

Schematic north-looking oblique section for the Roby Zone showing the position of the newly added Roby pit expansion resources. These total 16 M tonnes (800 k oz Pd) of Measured and Indicated Resources and could potentially be developed near the end of mining in the Offset Zone deposit.

OBLIQUE SECTION – LOOKING NORTHEAST

Roby open pit expansion resources within new 1 g/t Pd grade shell SW Part South Part

slide-18
SLIDE 18

17

Comparison of 2012 and 2014 MR&MR

Near surface M&IND resources beyond Roby Zone open pit resources

Plan view map showing location of additional near-surface resources. Sheriff Zone M&IND Resources: 1.76 Mt @ 2.1 g/t Pd NVT Rim Resources: 0.45 Mt @ 2.0 g/t Pd Sheriff Zone and North VT Rim Zone resources were initially reported in September, 2013. The Sheriff Zone resources extend to depths

  • f between 200m (north part) to 300m (south

part) below surface. The North VT Rim resources extend to depths of ~100m below surface and the zone is open to depth and along strike to the east.

Note the resource limits shown represent the full extent of each zone projected vertically to surface and that the actual resource shell, especially in the case of the Sheriff Zone, exhibits variable widths at different depths.

North VT Rim West Sheriff Zone

N

Roby Pit North VT Rim Zone Sheriff Zone

slide-19
SLIDE 19

18

CLOSING HIGHLIGHTS

  • Stabilized existing LDI operations
  • Extended life of mine plan for LDI
  • Grown total reserves and resources
  • Identified longer-term growth opportunities for evaluation

later in 2014

slide-20
SLIDE 20

Q & A

slide-21
SLIDE 21

For more information, please visit www.nap.com

  • r contact Investor Relations at IR@nap.com