Southeast Connector Project
- Oct. 31, 2019
Southeast Connector Project
Texas Transportation Commission
- Oct. 31, 2019
Southeast Connector Project Texas Transportation Commission - - PowerPoint PPT Presentation
Southeast Connector Project Texas Transportation Commission Southeast Connector Project Oct. 31, 2019 Oct. 31, 2019 Minute Order authorization Sum ummary o y of Commission a n acti tion: Authorize TxDOT to issue a request for
Southeast Connector Project
Texas Transportation Commission
Southeast Connector Project
Minute Order authorization
Sum ummary o y of Commission a n acti tion:
construct and maintain the Southeast Connector Project, consisting of non-tolled improvements along I-20 from Forest Hill Drive to Park Springs Boulevard, I-820 from I-20 to Brentwood Stair Road and US 287 from Bishop Street to Sublett Road in Tarrant County.
2
Southeast Connector Project
Purpose
Texas (#s 44 and 81) connect to the project corridor
Park Springs Boulevard; I-820 from I-20 to Brentwood Stair Road; US 287 from Bishop Street to Sublett Road
– Operational efficiency. – Long term congestion management. – Safety and mobility improvements.
3
Southeast Connector Project
– Construction of one additional general purpose lane (GPL), plus four-lane collector distributors, in each direction. – Reconstruction and realignment of existing GPLs, frontage roads, on- and off-ramps and an interchange.
Overview
4
Additional capacity shown with red arrows. I-20
Southeast Connector Project
Overview
5
Additional capacity shown with red arrows.
– Construction of two additional general purpose lanes (GPL) in each direction. – Construction of one additional frontage road lane in each direction. – Reconstruction and realignment of existing GPLs, frontage roads, I-20 / I-820 interchange, on- and off-ramps and an interchange.
I-820
Southeast Connector Project
Overview
6
– 1 additional general purpose lane (GPL) in each direction. – Reconstruction and realignment of existing GPLs, frontage roads,
Additional capacity shown with red arrows. US 287
Southeast Connector Project
Alternative delivery support tool
7
– Used to determine best delivery method:
– Tool considers TxDOT’s goals and specific project characteristics.
– Tool indicates design-build as most appropriate delivery method with a score
Southeast Connector Project
Design-build anticipated timeline
8
Milestone Date Commission action to issue RFQ
Issue RFQ
Qualifications statements due
Commission action to issue RFP Spring 2020 Proposals due Winter 2021 Commission action for conditional award Winter 2021 Contract execution Spring 2021 Construction completion Late 2026