Southeast Connector Project

  • Oct. 31, 2019

Southeast Connector Project

Texas Transportation Commission

  • Oct. 31, 2019
slide-2
SLIDE 2

Southeast Connector Project

  • Oct. 31, 2019

Minute Order authorization

Sum ummary o y of Commission a n acti tion:

  • Authorize TxDOT to issue a request for qualifications (RFQ) to design,

construct and maintain the Southeast Connector Project, consisting of non-tolled improvements along I-20 from Forest Hill Drive to Park Springs Boulevard, I-820 from I-20 to Brentwood Stair Road and US 287 from Bishop Street to Sublett Road in Tarrant County.

2

slide-3
SLIDE 3

Southeast Connector Project

  • Oct. 31, 2019

Purpose

  • Two of the 100 most congested roadways in

Texas (#s 44 and 81) connect to the project corridor

  • Project limits: I-20 from Forest Hill Drive to

Park Springs Boulevard; I-820 from I-20 to Brentwood Stair Road; US 287 from Bishop Street to Sublett Road

  • Project purpose:

– Operational efficiency. – Long term congestion management. – Safety and mobility improvements.

3

slide-4
SLIDE 4

Southeast Connector Project

  • Oct. 31, 2019
  • Texas Clear Lanes project with an estimated design-build cost of $1.59B
  • Total length of 16.6 miles comprised of three roadways: I-20, I-820 and US 287
  • Project scope for I-20 from Forest Hill Drive to Park Springs Boulevard:

– Construction of one additional general purpose lane (GPL), plus four-lane collector distributors, in each direction. – Reconstruction and realignment of existing GPLs, frontage roads, on- and off-ramps and an interchange.

Overview

4

Additional capacity shown with red arrows. I-20

slide-5
SLIDE 5

Southeast Connector Project

  • Oct. 31, 2019

Overview

5

Additional capacity shown with red arrows.

  • Project scope for I-820 from I-20 to Brentwood Stair Road:

– Construction of two additional general purpose lanes (GPL) in each direction. – Construction of one additional frontage road lane in each direction. – Reconstruction and realignment of existing GPLs, frontage roads, I-20 / I-820 interchange, on- and off-ramps and an interchange.

I-820

slide-6
SLIDE 6

Southeast Connector Project

  • Oct. 31, 2019

Overview

6

  • Project scope for US 287 from Bishop Street to Sublett Road:

– 1 additional general purpose lane (GPL) in each direction. – Reconstruction and realignment of existing GPLs, frontage roads,

  • n- and off-ramps and an interchange.

Additional capacity shown with red arrows. US 287

slide-7
SLIDE 7

Southeast Connector Project

  • Oct. 31, 2019

Alternative delivery support tool

7

  • Decision support tool

– Used to determine best delivery method:

  • Design-bid-build
  • Design-build

– Tool considers TxDOT’s goals and specific project characteristics.

  • Results

– Tool indicates design-build as most appropriate delivery method with a score

  • f 0.88 (scale of -1.00 DBB to 1.00DB).
slide-8
SLIDE 8

Southeast Connector Project

  • Oct. 31, 2019

Design-build anticipated timeline

8

Milestone Date Commission action to issue RFQ

  • Oct. 2019

Issue RFQ

  • Dec. 2019

Qualifications statements due

  • Feb. 2020

Commission action to issue RFP Spring 2020 Proposals due Winter 2021 Commission action for conditional award Winter 2021 Contract execution Spring 2021 Construction completion Late 2026