Stakeholder Update Meeting February 10, 2020 This PowerPoint presentation was prepared by the Florida Department of Transportation (FDOT) staff and has been made available to the public as part of public records access. Any dissemination of this


slide-1
SLIDE 1

Stakeholder Update Meeting February 10, 2020

slide-2
SLIDE 2

2

This PowerPoint presentation was prepared by the Florida Department of Transportation (FDOT) staff and has been made available to the public as part of public records access. Any dissemination of this presentation by anyone or entity

  • ther than FDOT staff is not official. Any questions can be sent to FDOT-

D6PIO@dot.state.fl.us. This presentation may not be altered.

slide-3
SLIDE 3

* This schedule does not reflect days added to the contract for holidays, weather days or special events

3

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES Ongoing concrete pavement saw cutting in preparation for concrete replacement. TRAFFIC SHIFT: All travel lanes will be shifted to the right on southbound I-95 from SR 836 to NW 8 Street to allow the contractor to construct new bridge foundations (Tuesday, February 11)

slide-4
SLIDE 4

* This schedule does not reflect days added to the contract for holidays, weather days or special events

4

ONGOING LANE CLOSURES THREE MONTH LOOK AHEAD

ANTICIPATED NIGHTTIME LANE CLOSURES ON THE I-95 CORRIDOR:

  • Nighttime lane closures along I-95 between NW 8 Street and NW 29

Street

  • Continuous weekend lane closures for pavement work
  • Closure of I-95 entrance ramp at NW 8 Street
  • I-95 ramps to I-395 and SR 836
slide-5
SLIDE 5

* This schedule does not reflect days added to the contract for holidays, weather days or special events

5

Traffic on the SR 836 Miami River Bridge 5shifted to the outside in preparation for demolition activities in the median

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

slide-6
SLIDE 6

6

Ongoing bridge widening

  • n eastbound SR 836

from NW 17 Avenue to the Miami River UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

slide-7
SLIDE 7

Pouring concrete for the new bridge deck on SR 836

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

7

slide-8
SLIDE 8

8

Ongoing bridge widening on eastbound SR 836 from NW 12 Avenue to I-95 UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

slide-9
SLIDE 9

Supplemental parking for court facilities

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

9

slide-10
SLIDE 10

WEDNESDAY, FEBRUARY 12 THROUGH MONDAY, FEBRUARY 17 - NW 10 Avenue will be continuously closed from NW 13 Street to NW 14 Street starting at 10 a.m. on Wednesday, February 12 until 5:30 a.m.

  • n Monday, February 17.

The continuous closure will allow the contractor to safely drive concrete piles into the ground for new bridge foundations.

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

10

slide-11
SLIDE 11

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

11

ANTICIPATED NIGHTTIME LANE CLOSURES ON SR 836 CORRIDOR:

  • Single and double lane closures along eastbound and westbound SR 836
  • NW 17 Avenue under SR 836
  • SR 836 ramps to northbound and southbound I-95
  • Arterial roads under SR 836
  • NW 17 Avenue and NW 12 Avenue ramps to SR 836

ONGOING LANE CLOSURES THREE MONTH LOOK AHEAD

slide-12
SLIDE 12

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

12

1. Removal of median separator between the eastbound I-395 mainline and the westbound mainline (Ongoing) 2. Construction of westbound outside, local road lanes. Foundation work started at NE 2 Avenue and is moving towards the west (Ongoing) 3. Begin demolition of portions of existing eastbound I-395 to allow for the construction of new bridge foundations (February) UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

1 2 3

slide-13
SLIDE 13

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

13

I-395 steel sheet pile driving for Signature Bridge center pier

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

slide-14
SLIDE 14

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

14

I-395 bridge demolition

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

slide-15
SLIDE 15

* This schedule does not reflect days added to the contract for holidays, weather days or special events

15

  • Auger Cast Pile (ACP)

Operations for Segmental Bridges started in late December 2019

  • ACP Completed: 160/1948
  • I-395 Segmental ACP – 857
  • I-395 Signature ACP – 520
  • SR 836 Viaduct ACP - 571

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

slide-16
SLIDE 16

* This schedule does not reflect days added to the contract for holidays, weather days or special events

16

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES Shift traffic to the left on the westbound MacArthur Causeway approach to Biscayne Boulevard exit (February 17, 2020)

slide-17
SLIDE 17

* This schedule does not reflect days added to the contract for holidays, weather days or special events

17

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES Lane shift (to south side) on the westbound MacArthur Causeway ramp to Biscayne Boulevard to allow for clearing and grubbing

  • activities. This will allow for construction of

new retaining wall (February 17, 2020)

slide-18
SLIDE 18

* This schedule does not reflect days added to the contract for holidays, weather days or special events

18

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES Traffic shift on Biscayne Boulevard from NE 13 Street to NE 11 Terrace. Shift lanes to the outside. There will be three NB Lanes (two through lanes and one left turn lane onto NE 13 Street) and three SB Lanes (two through lanes and one left turn lane onto EB MacArthur Causeway) Close Bayshore loop ramp to EB MacArthur Causeway (March 2020)

1 1 2 2

slide-19
SLIDE 19

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

19

ANTICIPATED NIGHTTIME LANE CLOSURES ON I-395 CORRIDOR:

  • Lane closures along eastbound and westbound I-395
  • Lane closures along Biscayne Boulevard and other arterial roadways

adjacent to I-395

  • I-395 to I-95 ramp closures

ONGOING LANE CLOSURES THREE MONTH LOOK AHEAD

slide-20
SLIDE 20

20

COMMUNITY OUTREACH

PROJECT WEBSITE

  • www.i-395miami.com
  • Sign-up for project alerts/updates

Lane closure information Upcoming construction activities Presentations

  • Calendar of events

OUTREACH OFFICE IN THE OVERTOWN COMMUNITY

  • 1035 NW 3 Avenue, Miami, Florida 33136

STAKEHOLDER MEETINGS

  • Ongoing individual stakeholder meetings and presentations
  • Next stakeholder meeting – March 16, 2020
slide-21
SLIDE 21

786-280-0983 OGonzalez@mrgmiami.com Contact: Oscar Gonzalez

www.i-395miami.com

THANK YOU!