Surface Remediation Overview and Key Concerns Surface Remediation - PowerPoint PPT Presentation
Surface Remediation Overview and Key Concerns Surface Remediation Primary components Baker Creek Tailings and sludge ponds Pits Contaminated soil Buildings and roadways Others Site Overview Site Overview Site
Surface Remediation Overview and Key Concerns
Surface Remediation • Primary components – Baker Creek – Tailings and sludge ponds – Pits – Contaminated soil – Buildings and roadways – Others
Site Overview
Site Overview
Site Overview
Site Overview
Site Boundary
Baker Creek
Baker Creek
Baker Creek • Baker Creek flows through the site – Enters above Baker Pond and exits into Back Bay
Baker Creek • Both “natural” and “constructed” reaches
Baker Creek
Baker Creek
Baker Creek • Reach 4 flowed over arsenic stopes – Relocated and stabilized in 2006 4
Baker Creek • Problem sections of Baker Creek in flood – Narrow diversions above C1 pit and A2 pit 3 1 4
Baker Creek • High value habitat – Reach 4 – Grayling spawning – Reach 6 – Temperature and nutrients 3 1 4 6
Baker Creek • Other fish habitat and uses – Every reach is now known to support some fish uses 3 2 1 4 5 6
Baker Creek • Arsenic in sediments – Reach 2, 5, 6 – But other reaches also have areas of contaminated sediments 3 2 1 4 5 6
Baker Creek • Water quality – Arsenic in Baker Creek comes from water treatment plant – And from upstream 220 kg/yr 3 2 1 4 5 6 300 kg/yr
Baker Creek • Key Concerns – Physically impacted in mine area – Water quality – Sediment quality – Concerns for fish, muskrat and humans? – Disturbance from sediment remediation?
Tailings • South, Central & North Ponds • Northwest Pond
Tailings • Foreshore tailings • Offshore tailings
Tailings • North, Central & South Ponds – 7M tonnes tailings covering 51 ha – Sludge ponds
Tailings
Tailings
Tailings • Seven dams around Original Impoundments • Up to 20 m high • Inspected annually by geotechnical engineer
Tailings • Northwest Pond – 6.5M tonnes tailings covering 44 ha
Tailings
Tailings
Tailings • Six dams around Northwest Pond • 15-20 m high • Well engineered and constructed • Inspected annually by geotechnical engineer
Tailings • Tailings are fine silty powder • About 2,000-4,000 mg/kg arsenic
Tailings
Sludge Ponds • Settling pond and polishing pond – Water treatment residuals
Tailings & Sludge Ponds • Key concerns – Dust – Surface exposure of arsenic – Lack of vegetation – Seepage
Pits • Five major pits • A2, A1, C1, B2, B1
Pits
Pits • Five large pits and three small pits – Table of pits and volumes Existing Void Pit Volume 1 (m 3 ) Pit Plan Area (m 2 ) A1 757,000 48,000 A2 479,000 32,000 C1 372,000 31,000 B1 331,000 22,000 B2 203,000 20,000 B3 56,000 9,000 B4 10,000 4,000 Brock 10,000 2,000 TOTALS 2,218,000 158,000 1 Volume to spill point elevation
Pits • Key concerns – Safety • Steep pit walls are a potential hazard to people • Long-term stability of stopes directly below pits • Openings to surface – If Baker Creek channel issues not addressed • Flooding could allow water into pits and underground
Contaminated Soils
Contaminated Soils • Key concerns – Land use vs soil contamination levels – Soil quality • Human risk – Inhalation / ingestion – Arsenic uptake by vegetation • Wildlife – Disturbance related to soil remediation?
Buildings • Buildings – In general all buildings on the site will be cleaned and demolished – Five areas with different “issues”
Buildings • Townsite Area – City interested in four Townsite homes
Buildings • Townsite and A-Shaft – NWT Mine Heritage Society interested in Community Hall – A-Shaft is a safety hazard
Buildings • Mill Area – Significant arsenic and asbestos contamination – Requires careful sequence of hazardous material removal, demolition and disposal
Buildings
Buildings • Tailings Retreatment, Effluent Treatment, and Akaitcho Shaft – Some short-term uses – Then demolition and removal
Buildings • Key concerns – Many remaining buildings contain hazardous materials which could pose risks to workers and environment during demolition if not controlled – Decontamination will generate hazardous wastes requiring safe disposal (either on-site or special facility off-site) – Demolition will generate a large volume of non- hazardous waste requiring on-site disposal
Roadways
Roadways • Key concerns – Some road sections contaminated • Mine waste rock containing arsenic – Some roadways impede site drainage • Local flooding problems – Many roadways not required for future uses • Occupied land can be rehabilitated
Other • Remediation will create other surface components
Other • Arsenic trioxide management areas
Other • Water management system
Other • Soil borrow sources
Other • Landfill ???
Questions?
Recommend
More recommend
Explore More Topics
Stay informed with curated content and fresh updates.