SLIDE 1
TAXIWAY ALPHA REHAB CONSTRUCTION Shane A. Nixon. Airport Project - - PowerPoint PPT Presentation
TAXIWAY ALPHA REHAB CONSTRUCTION Shane A. Nixon. Airport Project - - PowerPoint PPT Presentation
TAXIWAY ALPHA REHAB CONSTRUCTION Shane A. Nixon. Airport Project Manager Limits of Construction Area A Limits of Construction Area A1-30 days Area A2-60 days Work within A1 and A2 may occur simultaneously All work within Twy
SLIDE 2
SLIDE 3
Area A Limits of Construction
- Area A1-30 days
- Area A2-60 days
- Work within A1
and A2 may occur simultaneously
- All work within Twy
E object free area/taxiway safety area shall be completed at night
SLIDE 4
Area B Limits of Construction
- Area B1-20 days
- Area B2-50 days
- Work within Area B1
and B2 may occur simultaneously
SLIDE 5
Crushing and removal
SLIDE 6
Scarifying and drying dirt
SLIDE 7
Undercut Area and Undercut Repair
SLIDE 8
Concrete Pavement Section and Shoulder Joint Detail
SLIDE 9
Concrete Treated Base (CTB) Placement
SLIDE 10
Trenching in Lighting Conduit, Installing Underdrain
SLIDE 11
Light Can Installation and Backfill
SLIDE 12
Concrete Joint and Elevation Plans
SLIDE 13
Reinforced Concrete Slabs
SLIDE 14
Production Concrete Pours
SLIDE 15
Concrete Production Pours
SLIDE 16
Production Concrete Pours
SLIDE 17
Saw Cutting Joints and Installing/Coring Taxiway Edge Lighting
SLIDE 18
Area A/B- Finished Product
SLIDE 19
Area C
- Area C -60 days
- 60-day closure of Twy
Romeo
- Twy Golf nightime
closure
- Work may be
performed currently with work in Area D
SLIDE 20
Area D
- Area D- 30 days
- 6” Mill and Pave Operation
SLIDE 21
Area C and Area D
SLIDE 22
Areas C and D Paving
SLIDE 23
Area C and D Paving
SLIDE 24
Area E
- All work within
Area E shall be completed between Friday at 2300 to Sunday at 1800.
- Work in Area E
must complete within 10 consecutive calendar days
SLIDE 25