TAXIWAY ALPHA REHAB CONSTRUCTION Shane A. Nixon. Airport Project - - PowerPoint PPT Presentation

taxiway alpha rehab construction
SMART_READER_LITE
LIVE PREVIEW

TAXIWAY ALPHA REHAB CONSTRUCTION Shane A. Nixon. Airport Project - - PowerPoint PPT Presentation

TAXIWAY ALPHA REHAB CONSTRUCTION Shane A. Nixon. Airport Project Manager Limits of Construction Area A Limits of Construction Area A1-30 days Area A2-60 days Work within A1 and A2 may occur simultaneously All work within Twy


slide-1
SLIDE 1

TAXIWAY ALPHA REHAB CONSTRUCTION

Shane A. Nixon. Airport Project Manager

slide-2
SLIDE 2

Limits of Construction

slide-3
SLIDE 3

Area A Limits of Construction

  • Area A1-30 days
  • Area A2-60 days
  • Work within A1

and A2 may occur simultaneously

  • All work within Twy

E object free area/taxiway safety area shall be completed at night

slide-4
SLIDE 4

Area B Limits of Construction

  • Area B1-20 days
  • Area B2-50 days
  • Work within Area B1

and B2 may occur simultaneously

slide-5
SLIDE 5

Crushing and removal

slide-6
SLIDE 6

Scarifying and drying dirt

slide-7
SLIDE 7

Undercut Area and Undercut Repair

slide-8
SLIDE 8

Concrete Pavement Section and Shoulder Joint Detail

slide-9
SLIDE 9

Concrete Treated Base (CTB) Placement

slide-10
SLIDE 10

Trenching in Lighting Conduit, Installing Underdrain

slide-11
SLIDE 11

Light Can Installation and Backfill

slide-12
SLIDE 12

Concrete Joint and Elevation Plans

slide-13
SLIDE 13

Reinforced Concrete Slabs

slide-14
SLIDE 14

Production Concrete Pours

slide-15
SLIDE 15

Concrete Production Pours

slide-16
SLIDE 16

Production Concrete Pours

slide-17
SLIDE 17

Saw Cutting Joints and Installing/Coring Taxiway Edge Lighting

slide-18
SLIDE 18

Area A/B- Finished Product

slide-19
SLIDE 19

Area C

  • Area C -60 days
  • 60-day closure of Twy

Romeo

  • Twy Golf nightime

closure

  • Work may be

performed currently with work in Area D

slide-20
SLIDE 20

Area D

  • Area D- 30 days
  • 6” Mill and Pave Operation
slide-21
SLIDE 21

Area C and Area D

slide-22
SLIDE 22

Areas C and D Paving

slide-23
SLIDE 23

Area C and D Paving

slide-24
SLIDE 24

Area E

  • All work within

Area E shall be completed between Friday at 2300 to Sunday at 1800.

  • Work in Area E

must complete within 10 consecutive calendar days

slide-25
SLIDE 25

CLT Airport: Building an Airport for the Future!