Updates on Camera & Ground Plane Monitoring System Heng-Ye Liao, Charles Cadeau, Francesco Pietropaolo, Stephen Pordes, Serhan Tufanli HV system consortium meeting 07/10/2018 Signal Readout Port Port Item Number 1 Ground plane


slide-1
SLIDE 1

Updates on Camera & Ground Plane Monitoring System

Heng-Ye Liao, Charles Cadeau, Francesco Pietropaolo, Stephen Pordes, Serhan Tufanli HV system consortium meeting 07/10/2018

slide-2
SLIDE 2

2

Signal Readout Port

Port Number Item 1 Ground plane readouts 2 Roof RTD 3

  • Bo’s Cam #3
  • Bo’s Red LEDs
  • Edgar’s LEDs

1 2 3 4 5 Level meter Port 10.2 6 7 8 9 10 11

Photo credit: Charles

BR BL

Beam plug P4 P6 P7 P5 P10(bot) P11 P8(top) P9(bot) P3(top) Red: Edgar’s cameras Green: Bo’s Arrow: Camera pointing position Note: Lost connection of P3

slide-3
SLIDE 3

3

Status of Camera System

  • Internet cables are made & routed
  • Dongle connectors are made
  • Internet cables and powers to dongles are connected
  • Physical addresses of Edgar's cameras had been registered
  • Cameras have been renamed as following:

NP04-CAM-0xx (Bo) xx=1-5 NP04-CAM-1yy (Edgar) yy=1-4 NP04-CAM-2zz (Acrylic) zz=1-3 → Each camera is accessible via VLC player

  • Central controlled software has been taken care of

→ George Salukvadze coordinates the accessibility for all the cameras He said he should have a central organized software by the end of this week.

Power cables for lightening Dongles

p.s. Dongle connector: power to camera+data transfer (Internet cable)

Internet cables

slide-4
SLIDE 4

4

Status of Ground Plane Monitoring System

  • Warm cable has been installed
  • Shielding box has arrived & has been mounted
  • Pomona box & DAQ are in the DCS rack
  • Cross-checked channel map

→ Signals & Grounds are inverted in the Pomona Box → Problem has been solved by inverting the signals & grounds inside the connector

  • Temporarily GP DAQ is almost ready

→ Sylvain Ravat is working on it.

  • Pulser measurement today/tomorrow

GP DAQ Pomona box p.s. Pomona box includes voltage vivider & protection circuit to GP DAQ

slide-5
SLIDE 5

5

Backup

slide-6
SLIDE 6

6

Port 10.2 Manhole Manhole Beam direction Bo’s LED Edgar’s LEDs

Light Position

p.s. Figure not drawn to scale