Visit to Project Allenby/Connaught by Bondholders 15 March 2011 - - PowerPoint PPT Presentation
Visit to Project Allenby/Connaught by Bondholders 15 March 2011 - - PowerPoint PPT Presentation
Visit to Project Allenby/Connaught by Bondholders 15 March 2011 Programme 10:30 Arrive at Wellington House, Aldershot 10:45 - 12:15 Project briefing & presentation 12:15 - 13:15 Walking Tour of St Omer Barracks 13:15 - 14:00 Q & A
2
Programme
Q & A session and lunch 13:15 - 14:00 Close/Return to Farnborough 14:00 Walking Tour of St Omer Barracks 12:15 - 13:15 Project briefing & presentation 10:45 - 12:15 Arrive at Wellington House, Aldershot 10:30
3
Strategic Importance to MoD
- The Project covers approximately 35% of Army UK Based Trained
Manpower (20% of total manpower)
- Salisbury Plain is the principle All Arms Manoeuvre Training Area in
UK
- The Project delivers two key objectives of the 1998 Strategic
Defence Review:
- Improving working and living accommodation
- Identified as a major factor in morale, effectiveness, recruiting and retention
- Providing accommodation for Units returning from Germany
and reorganising within UK
- 2nd Royal Tank Regiment in July 2007, a key deliverable which was met on time
- 5 major units moving onto Salisbury Plain (2,500 soldiers)
Source: MOD
4
- New Defence-wide organisation from April 2011
- Will include this contract, but detailed arrangements still to be determined
- Means contract will no longer be answerable to Land Forces
- Our joint intent is to ensure that well established working procedures are
maintained
- Detail of SDSR and its impact on the Project being considered
2010 Strategic Defence & Security Review
5
Shared Purpose and Vision
Purpose
Together, MoD and Aspire will manage and deliver a modern, flexible living and working environment for soldiers in the Aldershot and Salisbury Plain area that will support military fighting power, enhance Army recruitment and retention and provide long-term value for the MoD and for Aspire
Vision
We will improve the quality of life
- f soldiers by delivering best
in class service
6
History
- January 2002
Formed Aspire Joint Venture
- 2002-2003
Bidding
- July 2003
Selected as Preferred Bidder
- January 2004
Pre-Contract Activities Letter – mobilised
- April 2006
Financial Close
- July 2006
Service Commencement
- July 2007
2RTR delivered
- 2014
Funding availability period
- 2014
Construction complete
- 2016
Benchmarking/market testing
- 2041
End of contract
7
What is the Contract?
A 35 year contract to provide a service
8
Project Locations
9
- £8Bn [£11.9Bn] 35 year PFI contract with Aspire Defence.
- Construction Value £1.5Bn, Steady State Unitary Payment £240M pa
- Provides living & working accommodation to 18,700 military personnel, with
total dependency more that 21,000
- Originally 10 year, now 8 year construction phase. 375 new buildings and a
further 192 refurbished. 457 buildings demolished
- Previously 50+ support contracts. Aspire Defence Services
manage/operate service provision – 50% self delivered 50% sub- contracted
- Local Help Desks, available 24/7 365 days a year
Key Facts
10
Organisation and Structures
11
Contractual Framework
The Authority
Works Subcontract
Services( Sodexho ) Transport Management ( Lex ) Other Sub
- Works
Sub-subcontracts
Lifecycle Hard FMSoft FM
Utilities Infrastructure Service Subcontract Utilities Capital Upgrade Subcontract
Thames Water/EDF Energy MUJV
KBR
50% 50%
KBR Mowlem
50% 50% 12.5% 37.5% 100%
(ADSL)
MoD
Project Contract Services Subcontract
Living Services (Sodexo) Transport Management (Babcock Land) Corus
Major FM Sub-subcontracts
Lifecycle Hard FMSoft FM
Aspire Defence Services
Lifecycle Hard FM Utilities
MUJV (Veolia/UKPNS (Integrated Services & Works Utility)
KBR Carillion
50%
KBR Carillion Aspire Defence Finance
Aspire Defence Holdings
100%
(ADSL)
Soft FM
Aspire Defence Capital Works
Other Sub-subcontractors
Lenders
Collateral Deed
HSBC Infrastructure
5%
Carillion Innisfree KBR
45%
Hard FM/some Soft FM Accommodation
Aspire Defence Limited
12
ADL ADCW ADS
Working Relationships
13
Aspire Defence Capital Works
14
Construction Overview
- £1.5bn, 8 year construction programme
- Construction of:-
- large number low/medium rise
- not technically complex
- but geographically spread accommodation
- Management of Transition Programme key
low risk
15
Three Pricing Categories
- Firm, Fixed and Competed:
- Firm – £481m
- Fixed – uplifted for inflation/change in law – £296m
- Competed – subject to benchmarking or competition in
the market with agreed multiplier – £670m
- Appropriate allocation of risk over 8 year construction
period (2006 - 2014)
16
Demolished, 457 Refurbished/ Altered, 192 New Build, 375
Capital Works – number of units, by building type
17
Capital Works - building space by type and use
Dining 13% Technical 21% Other 5% Living 61%
18
Pre-Construction Progress to 31 January 2011
Scheme Design Reports
Remaining, 2 Completed, 512
Planning Consents
Required, 4 Granted, 366
Full Design
Assets to complete, 12 Assets Complete, 502
Procurement
Procured, 435 Remaining , 79
19
Construction Progress to 31 January 2011
20 40 60 80 100 120 140 160 180 Assets T i d w
- r
t h B u l f
- r
d P e r h a m D
- w
n L a r k h i l l W a r m i n s t e r A l d e r s h
- t
Remaining In Progress
Construction
In Progress 61 Remaining 106 AIS, 347
20
Construction Summary
- Construction not complex
- Lessons learned/continuous improvement
- Appropriate pricing risk – Firm, Fixed and
Competed
- Shorter programme
- On programme
- 65% complete
21
Aspire Defence Services
22
Hard and Soft FM Services
- £4.2bn over 35 years
- Management and administration
- Assets facilities maintenance
- Living accommodation services
- Transport services
- Stores services
- Office services
- Welfare services
- Support to security
23
Management & Administration Supply, Transport and Equipment Support Services Living Accommodation Services Office Services Welfare Services Support to Security Services Assets and Facilities Performance Monitoring QA Admin Helpdesk MIS HS&E HR Reporting Data Management Visitor Management Weapons & Ammunition Management Stores Fuel & Lubricants Laundry & Dry Cleaning Tailoring Shoe Repairs Travel Booking Fleet Management Logistics Vehicle Servicing Domestic Services Parking Space Management Mess Management Military Catering Bar Services Function Services Mailroom Archiving Admin and Clerical Typing PA Services Media Services Model Making Reprographics Leisure Services Civilian Catering Security Passes Reception Vetting Maintenance: M&E Building Fabric Grounds Ducting Civil Eng Furniture Fixtures & Fittings Estate Management Pest Control Utilities Maintenance & Management Cleaning Waste Management Window Cleaning
Services
Black – Self delivered Red – MUJV Green – Sodexo Blue – Babcock
24
Direct Delivery/Sub-Contract Revenue – averages over years 1- 10 at Financial Close prices
ADSL, £54m MUJV, £13m VT Land, £9m Sodexo, £28m
25
Service Delivery
- High customer satisfaction
- 24/7 Help Desks successful
- 100% of Retained Estate now in availability regime
- 4 year transitional period has now ended
- Minimal performance/availability deductions
- 0.06% of revenue since FC
- Changes in ownership in supply chain but no material impact
- IiP accreditation (top 3%)
26
Lifecycle
27
Lifecycle
- ProjCo budgetary risk, except for utilities
- Pre FC surveys and due diligence
- Cyril Sweet pricing model:-
- Gross Floor Area
- Cost /m2
- Age of building
- E C Harris opinion as to adequacy
28
New & Refurbished Buildings Retained Buildings FF&E External Areas Catering Equipment Total £613 million Real 2004
Lifecycle
29
Lifecycle
- Post FC
- Retained Estate (circa ⅓ of total)
- Extensive surveys
- 69 assets
- 16 space types
- Detailed pricing :-
- Individual quantities
- Cost per element
- Remaining life of each component
- Extrapolated
- Reconfirms adequacy of Retained Estate estimate
30
Lifecycle
200 400 600 800 1,000 1,200 1,400 2 6 2 8 2 1 2 1 2 2 1 4 2 1 6 2 1 8 2 2 2 2 2 2 2 4 2 2 6 2 2 8 2 3 2 3 2 2 3 4 2 3 6 2 3 8 2 4 year £M nominal Estimate Actual
31
Lifecycle – early years
20 40 60 80 100 120 140 2 6 2 7 2 8 2 9 2 1 2 1 1 2 1 2 2 1 3 2 1 4 2 1 5 2 1 6 year £M nominal Estimate Actual
32
Financial
33
Issuance Structure
The 2006 issuance for the financing of the project consisted of two fixed rate, wrapped, amortising Sterling debt tranches:-
8.5 years until amortisation commences Grace Period 34 years (1 year tail on the Project Agreement) Legal Maturity 25 years Weighted Average Life S&P: BBB Moody’s: Baa2 Underlying Rating Fixed Rate Sterling Type £ 1,463 million (plus additional £305 million of Variation Bonds) sold as:
- Series A (Ambac): £ 731 million
- Series B (MBIA): £ 731 million
Total Issuance
Debt Security Package
- Fixed and floating charges
- Security over project
accounts and contracts
- Assignment of insurance
policies
- Step-in rights
Debt Issuance
34
Bond Outstanding Principal and Amortisation Profile
The outstanding principal and the amortisation profile for the combined Series A and Series B bonds over time is shown below on an annual basis. Series A and Series B are repaid pro-rata
Outstanding Principal Amortisation Profiles
20 40 60 80 100 120 140 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026 2028 2030 2032 2034 2036 2038 2040 £ million 200 400 600 800 1,000 1,200 1,400 1,600 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026 2028 2030 2032 2034 2036 2038 2040 £ million
35
Uses of Funds (First 8 years) £m Sources of Funds (First 8 years) £m % External Funding
3,670 Total 278 Cash/Reserves 920 Hard & Soft Facilities Mgmt 593 72 133 129 52 Financing Fees and Interest Lifecycle Overheads, insurance and tax Direct funded Change Loan Stock Interest 1,493 Capital Expenditure
- 243
129 Additional Authority Funding Direct funded Change 100% 3,670 Total
- 173
Interest Income
- 1,542
Operating Revenues 7.6% 120 Shareholder Financing 92.4% 1,463 Fixed Rate Guaranteed Bonds
Source: Sept 2010 Operating Financial model
Sources and Anticipated Uses of Funds – first 8 years
36
Main cash out-flows over project life
50 100 150 200 250 300 350 400 450 500 550 600 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 Year ending December 31 £m Nominal Operating Costs Lifecycle Costs Corporation Tax Senior Debt Interest and Fees Senior Debt Repayment Payment to Authority Capital Expenditure
37
Senior Debt Cover Ratios
- FC Base case ADSCR min 1.32 (2014) average 1.39, BLCR min 1.46
- Current forecast ADSCR min 1.32 (2031) average 1.36, BLCR min 1.45
- Distribution lock-ups at ADSCR <1.12, BLCR <1.15
Semi-annual Senior Coverage Ratios
1.00 1.10 1.20 1.30 1.40 1.50 1.60 1.70 1.80 1.90 2.00 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 Apr 06 Model ADSCR Apr 06 Model BLCR Lock Up Point Sep 10 Model ADSCR Sep 10 Model BLCR
38
Credit Crisis
- Credit crisis impacted the Project:
- Primary Arrangements – GICs and Authorised Investments
- 6 significant GIC deposits at FC, balances reduce monthly
- Protective provisions called up; series of novations then collateralisations
- 5 of 6 exposures now fully repaid
- Final GIC is fully collateralised with gilts
- Secondary Arrangements – LCs
- LC issuer downgraded
- Alternative arrangements in place
39
GICs
200 400 600 800 1,000 1,200 A p r
- 6
J u n
- 6
A u g
- 6
O c t
- 6
D e c
- 6
F e b
- 7
A p r
- 7
J u n
- 7
A u g
- 7
O c t
- 7
D e c
- 7
F e b
- 8
A p r
- 8
J u n
- 8
A u g
- 8
O c t
- 8
D e c
- 8
F e b
- 9
A p r
- 9
J u n
- 9
A u g
- 9
O c t
- 9
D e c
- 9
F e b
- 1
A p r
- 1
J u n
- 1
A u g
- 1
O c t
- 1
D e c
- 1
F e b
- 1
1 A p r
- 1
1 J u n
- 1
1 A u g
- 1
1 O c t
- 1
1 £m
now
collateralisations novations
40
Summary
41
Project Summary
- Effective robust contract structure
- Successful service delivery from the start continues
- Construction programme delivering; 65% complete
- Effective management of changing requirements
- Strong partnering relationships
Cautionary Statement This presentation may contain indications of future developments and other forward looking statements that are subject to risk factors associated with, amongst other things, the economic and business circumstances occurring from time to time in the sector of the economy within which the company
- perates. These and other factors could adversely affect the Project companies’ results and prospects. Forward looking statements involve risks,
uncertainties and assumptions They relate to events and/or depend on circumstances in the future which could cause the results and outcomes to differ materially from those currently anticipated. No obligation is assumed to update any forward looking statements, whether as a result of new information, future events or otherwise.
42
St Omer Barracks
43