Water Information November 2013 Summary (linked) Overview of Town - - PowerPoint PPT Presentation
Water Information November 2013 Summary (linked) Overview of Town - - PowerPoint PPT Presentation
Water Information November 2013 Summary (linked) Overview of Town System Discolouration Problem (2 slides) Operating Requirements Approach Phase 1 Projects (5 Slides) Phase 2 Projects (2 Slides) Costs 2013 Water
Summary (linked)
- Overview of Town System
- Discolouration Problem (2 slides)
- Operating Requirements
- Approach
- Phase 1 Projects (5 Slides)
- Phase 2 Projects (2 Slides)
- Costs
- 2013 Water Rates (3 Slides)
- Project Descriptions
2 Summary Link
Overview Pictou’s Water Source
- Groundwater supply – not surface water
- Two Wellfields (Caribou and Pictou)
- 13 Wells – producing 1.7 million litres per day
- 9 Wells supply the Water Tower
3 Summary Link
Overview Pictou’s Water Source
4 Summary Link
The Discolouration Problem
- Naturally occurring manganese in raw water – the addition of
chlorine drops manganese out of solution (appears in solid form)
- Manganese then builds up in pipes and bottom of water tower
- A change in pressure (caused by line breaks etc)
stirs up deposits which then pass through the system as discoloured water
- Some areas of town worse than others:
– Dead ends lines have lower quality due to overnight settling – Certain areas of Town have multidirectional flow, depending on the time of day. The change in direction causes discoloration
5 Summary Link
Operating Requirements
- Governed by Nova Scotia Environment (NSE) and the
Nova Scotia Utility and Review Board (NSUARB)
- NSE required increase in chlorine (adds to discolouration
by pulling more manganese out of solution)
- NSE issues water withdraw permit based on sustainable
pumping yields (water is a Provincial resource)
- NSUARB sets rates based on capital projects & operating
costs
- The Town of Pictou’s Utility is currently one of the most
complex systems in the Province
6 Summary Link
Two Main Issues
- No. 1
System upgrades to ensure compliance with safe drinking water and other NSE regulations and permits continues. Referred to as Phase 1
- No. 2
Construction of a Central Treatment Plant to address water discolouration issues. Referred to as Phase 2
7 Summary Link
Phase 1: Capital Projects
1.1 Safe Drinking Water Regulations:
- NSE required testing and studies (complete)
- Engineering system designs (complete)
- Water Model created - pressure + disinfection residual
scenarios (complete with ongoing refinements)
- Installation of 3 new wells (complete)
- Installation of new transmission line to cluster wells
(complete)
- Installation of Ultra Violet disinfection (occurring now)
- Installation of Monitoring Equipment (occurring now)
- Provincial/Federal Infrastructure application pending
8 Summary Link
Phase 1: Capital Projects
9 Summary Link
Phase 1: Capital Projects
1.1 Safe Drinking Water Regulations:
10 Summary Link
Phase 1: Capital Projects
1.2 NSE Water Withdrawal Permit (Meters):
- Main purpose of meters is to ensure Utility stays below the NSE
permitted withdrawal amount (new construction, central filtration backwash requirements etc…)
- Meters are main tool available to reduce water consumption
(public education) and production (leak detection)
- Cost sharing has been obtained
- NSUARB approved installation (in 2005
and 2013)
- Flat billings will continue until
discolouration is addressed
- Neptune has begun to install meters on
an area by area basis
11 Summary Link
Phase 1: Capital Projects
1.3 Infrastructure Updates:
- New and replacement distribution lines:
– Portion of St. Andrews St (complete) – Irving St (complete) – Sinclair St (complete) – Portion of Palmerston St (complete) – Spruce St (complete) – Extension of Hector Ave (complete) – NSUARB 2013 rates includes $100k per yr – Engineering work complete on two Streets
- Standpipe Refurbishment:
– Outlet pipe extended upwards to lessen discolouration events (complete) – Major interior and exterior refit (work in progress)
12 Summary Link
Phase 2: Water Discolouration
Central Treatment Plant:
- Intent: Filter manganese out of raw water prior to
chlorination (no or little manganese left to drop out of solution – no manganese deposit in standpipe and lines – no water discolouration)
- Pre-design engineering report (completed)
- Piloting of treatment technologies at full scale (about to
start)
- Applications for Provincial and Federal infrastructure cost
sharing (pending release of applications)
13 Summary Link
Phase 2: Water Discolouration
14 Summary Link
Summary of Capital Costs
- Phase 1: (safe water & regulatory): $3.35 million
- Phase 2: (water discolouration):
$4.08 million TOTAL $7.43 million
15 Summary Link
2013 Water Rates
- NSUARB approved rate increases to fund:
– remaining costs of Phase 1 upgrades; and – costs associated with piloting of treatment technologies
- The NSUARB has approved flat rate billing until
water discolouration has been addressed
16 Summary Link
2013 Water Rates
- What is NOT included in the Town’s current rates:
– The vast majority of Phase 2 costs (water discolouration)
- Why not?
– The Town believes that in the absence of Provincial and Federal cost-sharing Phase 2 may not be affordable to water customers
17 Summary Link
Rate Hearing
- How will Phase 1 costs affect my water bill?
Flat rates (unmetered) will continue until discolouration has been addressed. Meter Size Current Size 2013 2014 2015 2016 2017 Unmetered 79.92 $ 119.45 $ 121.05 $ 121.63 $ 121.04 $ 5/8 149.99 $ 171.86 $ 175.88 $ 176.89 $ 175.87 $ 3/4 133.93 $ 158.05 $ 160.05 $ 160.78 $ 160.04 $ 1 212.30 $ 244.96 $ 248.07 $ 249.21 $ 248.06 $ 1.5 349.41 $ 411.11 $ 415.64 $ 417.30 $ 415.62 $ 2 590.79 $ 673.62 $ 681.63 $ 684.58 $ 681.60 $ 3 598.64 $ 719.07 $ 721.62 $ 722.56 $ 721.61 $ Year Ending
18 Summary Link
Additional Detail All Projects
Summary Link
Description of Individual Water Projects (Linked)
- Completed Projects
– Engineering – Well Clustering (transmission main) – Contact Pipes – New Wells – Infrastructure Replacement
- In Progress Projects
– Disinfection and Monitoring Upgrades – Water Tower Refurbishment – Residential Water Meters – Treatment Technology Piloting – Treatment Plant
20 Summary Link
Completed Projects
21 Summary Link
Engineering
Why
- Require professional design and costing advice (helps influence cost
sharing opportunities from other levels of government)
Description
- CBCL was hired to complete
– Assess water system – Suggest phase compliance/treatment work based on standards – Model the system – Provide guidance on all projects
Outcome
- A project list has been completed and divided into two phases:
– Phase 1 is compliance related – Phase 2 is treatment
- Achieve compliance with NSE standards
- Implement technology to improve water quality
22 Summary Link
Well Clustering
Why
- Create a centralized blend of water to send to a future treatment plant
Description
- Connected 9 of the Town’s 13 wells
- A blended water source reduces variability in its chemistry
Outcome
- All water produced along the northern/eastern boundary now supplies
the water tower and site of a future treatment plant
23 Summary Link
Contact Pipes
Why
- Regulations require water to be mixed with chlorine for a specific time
prior to entering the distribution system
Description
- Four wells currently feed directly into the distribution system.
- Large contact pipes were required at those sites
Outcome
- All sites have contact pipes installed and disinfected
- Disinfection requirements for chlorine achieved
Town chlorine dosing equipment 24 Summary Link
New Wells
Why
- Some wells were low in quality and yield
- Cheaper to decommission/built new wells than repair
Description
- Drilled two new wells
- Re-drilled one well
- Replaced three poor quality/low yield wells
Outcome
- Well #14 and #15 were built and commissioned
- Vance Well and #9 were decommissioned
- Footes Lane has been re-drilled 100 meters from its original location
- Town increased its production capacity by close to 100 gpm
25 Summary Link
Infrastructure Replacement
Why
- Several aged pipes and hydrants (early 1900 vintage)
- Some generations of pipes have been prone to breaks
- Hydrants need to be in working order
Description
- Replacing hydrants and pipes on a year by year basis
- Invested/ing about $110,000 per year
Outcome
- Several streets have had pipes replaced
(click here for street locations)
- Most Hydrants in the Town have been replaced
26 Summary Link
In Progress Projects
27 Summary Link
Disinfection and Monitoring Upgrades
Why
- Pre-existing system did not meet new NSE
requirements/regulations
- Needed to increase disinfection and monitoring of
raw water
Description
- Installation of new monitoring equipment for quality parameters
(computerized system)
- Installation of new UV disinfection lights
Outcome
- Installed all new equipment at 13 well sites and the water tower
- A computer system records all quality parameters and provides early
detection of changes
- UV lights provide the needed disinfection
Town of Pictou UV System (2013) 28 Summary Link
Water Tower Refurbishment
Why
- Built in 1982
- Requires cleaning, recoating and upgraded
corrosion control features
- New treatment to be built adjacent to water tower
(the project upgrades the tower prior to plant construction)
Description
- November 2013 - drained, cleaned, sand blasted, upgraded corrosion
control equipment and re-coated (interior)
- Spring 2014 - drained, sand blasted and re-coated (exterior)
- Updating to improve safety and access
Outcome
- The Tower will have an extended life of 15-20 years
- Improved physical appearance and safety
29 Summary Link
Residential Water Meters
Why
- Approaching maximum withdrawal limit regulated by the Province
- Need a method for identifying leaks (system and homes)
Description
- Exiting meters are being replaced with new technology
- Residential water meters are being installed
- Help improve leak detection
Outcome
- NSUARB has approved flat rate billing on residential meters until a
treatment plant is built
- Meters will notify users if they have a leak
- Allow Utility to account for all water used to determine system losses
- ALLOW THE TOWN TO STAY WITHIN SUSTAINABLE PUMPING LIMITS
30 Summary Link
Water Treatment Piloting
Why
- Need to identify which treatment technology best suits our water.
Description
- We have several sources of water, all high in manganese concentration
- Limited water available for a new central treatment system
maintenance (backwash water)
Outcome
- Identify the most effective and efficient technology for a treatment
plant
- Better understanding of maintenance costs and requirements
31 Summary Link
Water Treatment Plant
Why
- Water is extremely high in manganese concentration
- When interacting with chlorine it drops out of solution
- Causes major discolouration events and problems for all users
Description
- Will be built based on technology identified from the pilot
- Built at the water tower site (Oak Street) and treat 9 of 13 wells
- Water will be chlorinated after manganese is removed
Outcome
- Manganese will no longer enter the distribution system (clearer water)
- Existing manganese will eventually pass out of the system (over time)
- Greatly improve aesthetic water quality
32 Summary Link