What is a DDI Recommended Practices Traffic Operations Analysis - - PowerPoint PPT Presentation

what is a ddi
SMART_READER_LITE
LIVE PREVIEW

What is a DDI Recommended Practices Traffic Operations Analysis - - PowerPoint PPT Presentation

What is a DDI Recommended Practices Traffic Operations Analysis Geometric Design FHWA Review Conclusions & Lessons Learned Its not about you, its about the public Developed by Access Utah County (AUC), I-15


slide-1
SLIDE 1
slide-2
SLIDE 2

 What is a DDI  Recommended Practices

  • Traffic Operations Analysis
  • Geometric Design
  • FHWA Review

 Conclusions & Lessons Learned

slide-3
SLIDE 3

It’s not about you, it’s about the public

slide-4
SLIDE 4
slide-5
SLIDE 5
slide-6
SLIDE 6
slide-7
SLIDE 7
slide-8
SLIDE 8

 Developed by Access Utah County (AUC), I-15

CORE and the TOC

 Reviewed by UDOT Technical Committee  For DDI feasibility on other projects

slide-9
SLIDE 9
slide-10
SLIDE 10

Main goal is to reduce delay:

  • Accommodate the left turn movements
  • Reduce the number of signal phases

Only two signal phases are required, compared with 3 for a SPUI, or 4 with a diamond

slide-11
SLIDE 11

 Operational Failure when:

  • A + B > 1900 vph
slide-12
SLIDE 12

 Operational Failure when:

  • A + B > 1900 vph
  • A + C > 1900 vph
slide-13
SLIDE 13

 Operational Failure when:

  • A + B > 1900 vph
  • A + C > 1900 vph
  • B + C > 1900 vph
slide-14
SLIDE 14

 Operational Failure when:

  • A + B > 1900 vph
  • A + C > 1900 vph
  • B + C > 1900 vph
  • A + B + C > 2100 vph
slide-15
SLIDE 15

 Transition from LOS D

to LOS F is very short.

For this reason, UDOT defines LOS C as a minimum for acceptable operation.

 Operational Failure when:

  • A + B > 1900 vph
  • A + C > 1900 vph
  • B + C > 1900 vph
  • A + B + C > 2100 vph
slide-16
SLIDE 16

 Considerations:

  • Weaving and merging
  • Signal timing
  • Driver behavior
  • Intersection spacing

 Requires use of micro-simulation software

  • UDOT requires use of VISSIM (PTV America) for analysis
slide-17
SLIDE 17

 Considerations:

  • Traffic & Pedestrian Volumes
  • Multi-Lane Turning Movements
  • Merging & Weaving Operations within the

Interchange

  • Non-traditional Signal Warrant Analysis
slide-18
SLIDE 18
slide-19
SLIDE 19
slide-20
SLIDE 20
slide-21
SLIDE 21
slide-22
SLIDE 22

 Proximity of side streets, railroads, etc.  Accommodation of pedestrians  Existing geometric constraints in retrofit

projects

slide-23
SLIDE 23

 Ramp terminal separation distance  Crossover intersection layout and grading  Signing and Striping  Lane and Shoulder Widths  Glare Reduction  Roadway Cross-Section

slide-24
SLIDE 24

To provide for queue storage and weaving space, crossover intersections should be spaced

850’ apart, with adjacent

signalized intersections 1000’ from the crossover intersections.

Right-in/Right-out access points may be placed according to the UDOT Access Management rules.

Placement of accesses closer than 1000’ should be analyzed using VISSIM to determine potential operational effects.

slide-25
SLIDE 25
slide-26
SLIDE 26

 Design speed through the crossover is

reduced at least 10 mph, with a minimum speed through the curves of 25 mph.

 Utilize reverse curves without tangents to

minimize length of crossover zones.

slide-27
SLIDE 27
slide-28
SLIDE 28
slide-29
SLIDE 29

 Placement of glare screen

is specific to each DDI design, and may affect horizontal alignments.

 Line-of-sight calculations

should be used.

 Additional study required

to identify appropriate design parameters.

slide-30
SLIDE 30
slide-31
SLIDE 31

 Shoulder widths should NOT be reduced

across structure

 Lane widths should be at least 12 feet  Turning templates for side by side WB-67 or

  • ther appropriate design vehicle should be

applied

slide-32
SLIDE 32
slide-33
SLIDE 33
slide-34
SLIDE 34

 500 East, American Fork

  • Why a DDI
  • Crossover geometry & glare reduction
  • Side street & ramp terminal separation
slide-35
SLIDE 35
slide-36
SLIDE 36
slide-37
SLIDE 37
slide-38
SLIDE 38
slide-39
SLIDE 39

 SR-92, Lehi

  • Why a DDI
  • Crossover geometry & glare reduction
  • Side street & ramp terminal separation
slide-40
SLIDE 40
slide-41
SLIDE 41
slide-42
SLIDE 42
slide-43
SLIDE 43
slide-44
SLIDE 44
slide-45
SLIDE 45

 Access Justification Report (AJR)

  • Used by FHWA for all modifications to the interstate

system.

  • The AJR is not a substitute for the NEPA process, and the

NEPA process does not eliminate the need for a AJR document.

  • Addresses the eight “policy points” defined by FHWA as a

type of warrants process.

slide-46
SLIDE 46

ADVANTAGES

 Higher left-turn capacity  No exclusive left-turn lanes  Smaller structures  Two-phase signal provides

flexibility in timing

 Smaller ROW footprint at the

interchange

DISADVANTAGES

 Contrary to driver expectation  Operation sensitive to signal and

street spacing

 Rapid transition from LOS D to

LOS F

 ROW impacts at crossover

intersections

 Integration of pedestrian traffic

When compared with SPUI or Diamond interchanges:

slide-47
SLIDE 47

 Design/Build contractors may submit the DDI

interchange type as an alternate concept; RFP should be written to address the possibility.

 Operational analysis of a DDI requires specific

software and requires more review time.

 Retrofit of existing structures may extend the

  • perational life of the interchange for much less than

reconstruction.

slide-48
SLIDE 48

Thank you for your time.

slide-49
SLIDE 49