Winchester Municipal Utilities March 6, 2014 Introduction - - PowerPoint PPT Presentation
Winchester Municipal Utilities March 6, 2014 Introduction - - PowerPoint PPT Presentation
Winchester Municipal Utilities March 6, 2014 Introduction Basis for Design Capacity Raw Water Supply Raw & Finished Water Transmission Mains Hydraulic Analysis Water Treatment Plant Conclusions &
- Introduction
- Basis for Design Capacity
- Raw Water Supply
- Raw & Finished Water Transmission Mains
- Hydraulic Analysis
- Water Treatment Plant
- Conclusions & Recommendations
- Schedule
Introduction
Technical Memorandum #1 presents the following
results & recommendations:
Reviews past studies, including the 2009 Hazen &
Sawyer (H&S) Water System Planning Study (WSPS), and a series of technical memoranda prepared by Black & Veatch, Commonwealth Technology and Baldwin Engineering
Evaluates and recommends raw water supply
alternatives
Introduction
Technical Memorandum #1 presents the following
results & recommendations:
Evaluates and recommends raw water intake and pump
station improvements
Evaluates and recommends raw and finished water
transmission main improvements
Provides an updated opinion of probable construction
cost and schedule for the proposed water system improvements
Basis for Design Capacity
Scope of TM#1 did not include a detailed evaluation of
existing water demands
TM#2 prepared in 1997 evaluated population projections
and future demands through the year 2000
TM#4 projected water demands through 2020
H&S study reports actual water demands, “have not
achieved the projected demands from the 1997 TM”
Basis for Design Capacity
H& S study indicates ultimate design capacity of the
new WTP to be 12.0 mgd
Recorded maximum daily water demands have
exceeded 5.0 mgd since 2005
WMU has committed to provide additional water to
local industry in the amount of 1.0 mgd
Basis for Design Capacity
Bell recommends the first phase of construction
include a design capacity of 9.0 mgd
Allows for further residential & industrial growth Includes incremental increases of 3.0 mgd over 2 phases
which is more practical and economical
Current bidding climate and economy has resulted in a
flat line of recent bidding and bonding for treatment facilities
Kentucky River Pool 10
The Kentucky River is and
will remain the primary source of drinking water for WMU’s system
WMU is permitted by KY
DOW to withdraw 15.0 million gallons per day (mgd)
Carroll Ecton Reservoir
Currently supplemented by the Kentucky River Intake
Pump Station
Leaking impoundment structure
Amount of leakage unknown, estimated over 1.0 mgd Geotechnical & structural investigations required to
determine cause of leakage and required improvements
Continued recreational use:
Pumping to supplement water loss will be required Power costs estimated to be approximately $38,281 per year at
current rates
Carroll Ecton Reservoir
Continued use as backup water supply:
Water quality is acceptable during colder months Thermal stratification and oxygen depletion occur in
warmer months
Aeration & mixing
system would be recommended at an approximate cost
- f $500,000
Carroll Ecton Reservoir
Raw water is currently pumped through an 18-inch raw
water transmission main to maintain Reservoir levels
Existing transmission main would need to serve dual-
purpose
Water supply line transporting water from the Kentucky
River to the Reservoir
Reverse flow and transport water from the Reservoir to
the new WTP site
Carroll Ecton Reservoir
Item Description Estimated Cost Power Cost to Supply 1.0 mgd to Carroll Ecton Reservoir $38,281/Year Project Costs for Improvements to Maintain Backup Water Supply $2,188,000 Summary of Project Costs – Carroll Ecton Backup Water Supply
Raw Water Intake & Pump Station
Existing raw water intake structure was designed to
pump 15.0 mgd with four pumps in service
To reliably pump 9.9 mgd to the new WTP an
additional pump similar to the existing pumps needs to be installed
When demands require more than 9.9 mgd, a fourth
pump will need to be installed to maintain redundancy in the system
Raw Water Intake & Pump Station
Item Description Estimated Cost Installation of Vertical Turbine Pump & Appurtenances $600,000 Electrical, Control & HVAC Improvements $440,000 Project Development (25%) $260,000 TOTAL OPINION OF PROBABLE PROJECT COSTS $1,300,000 Summary of Project Costs – Raw Water Intake Improvements
*Project development costs are based on a percentage of construction costs.
Recommendations
We recommend the following raw water intake
improvements:
Install a third duty pump Install a second transformer Install a soft starter for Pump #3 Install a fused switch to power the future Pump #4
starter
Upgrade the HVAC systems Install a pump control valve in lieu of a VFD
Raw Water Transmission Main
Alternative Evaluation
Velocities (6.0 mgd, 30-inch, < 2 fps) O&M requirements Constructability Capitol cost Present worth
Recommendations
Construct 12,000 l.f. of 24-inch ductile iron pipe
Raw Water Transmission Main
Item Description Estimated Cost Installation of 12,000 l.f. of 24-Inch Ductile Iron Pipe $2,220,000 Project Development (25%) $550,000 TOTAL OPINION OF PROBABLE PROJECT COSTS $2,750,000 Power Costs $554,683/Year Salvage Value @ 50 Years $0 Present Worth $14,665,000 Summary of Project Costs – 24-Inch Ductile Iron Raw Waterline
*Project development costs are based on a percentage of construction costs.
Finished Water Transmission Main
Alternative Evaluation
Velocities (6.0 mgd, 30-inch, < 2 fps) O&M requirements Constructability Capitol cost Present worth
Recommendations
Construct approximately 36,000 l.f. of 24-inch ductile
iron pipe
Finished Water Transmission Main
Item Description Estimated Cost Installation of 36,000 l.f. of 24-Inch Ductile Iron Pipe $6,660,000 Project Development (25%) $1,665,000 TOTAL OPINION OF PROBABLE PROJECT COSTS $8,325,000 Power Costs $580,700/Year Salvage Value @ 50 Years $0 Present Worth $20,798,000 Summary of Project Costs – 24-Inch Ductile Iron Finished Waterline
*Project development costs are based on a percentage of construction costs.
Hydraulic Analysis
Location Raw Water Transmission Main Pressure (psi) at RWI 24-Inch 30-Inch 24 & 30-Inch RWI – Ex. WTP @ 6.6 mgd 175 N/A 171 RWI – New WTP @ 6.6 mgd 158 155 N/A RWI – New WTP @ 9.9 mgd 165 158 N/A Hydraulic Characteristics for Raw Water Pipeline Alternatives
Existing pressure at RWI 215 psi Flow control valves eliminate negative pressures Air release valves required Surge control valve at RWI to reduce pressure surges
Hydraulic Analysis
Location Finished Water Transmission Main Pressure (psi) at Bypass Connection
- Ex. 12” & 18”
- Ex. 18” &
New 24”
- Ex. 18” &
New 30”
- Ex. WTP @ 3.9 mgd
52 56 56
- Ex. WTP @ 6.0 mgd
N/A 67 68 New WTP @ 6.0 mgd N/A 67 68 New WTP @ 9.0 mgd N/A 95 95 Hydraulic Characteristics for Finished Water Pipeline Alternatives
Existing pressure at Bypass 52 psi
Recommendations
We recommend the following transmission main
improvements:
Division A – Raw Water Intake to New WTP Site
Install approximately 12,000 l.f. of 24-inch ductile iron transmission
main Division B – New WTP to Existing WTP
Install approximately 21,000 l.f. of 24-inch ductile iron transmission
main Division C – Existing WTP to Bypass
Install approximately 15,000 l.f. of 24-inch ductile iron transmission
main
Water Treatment Plant
Opinion of Probable Project Costs – New 9.0 mgd Winchester WTP
*Project development costs are based on a percentage of construction costs.
Item Description Estimated Cost Treatment Processes & Facilities $17,515,000 Site Work & Yard Piping $1,571,000 Electrical, Instrumentation & Controls $3,859,000 HVAC, Fire, Plumbing & Miscellaneous $915,000
TOTAL OPINION OF PROBABLE CONSTRUCTION COSTS
$23,860,000 Project Development (25%) $5,965,000 TOTAL OPINION OF PROBABLE PROJECT COSTS $29,825,000
Recommended Improvements
Item Description Estimated Cost
Raw Water Intake & Transmission Main Improvements $9,920,000 New 9.0 mgd Water Treatment Plant $23,860,000 TOTAL OPINION OF PROBABLE CONSTRUCTION COSTS $33,780,000 Work Orders No. 7 & 8 Engineering Fees* $875,000 Project Development Costs (25% of WTP) $5,965,000 TOTAL OPINION OF PROBABLE PROJECT COSTS $40,620,000 Opinion of Probable Project Costs – Recommended Improvements
*Fees associated with RWI & Transmission Mains.
Recommended Improvements
Opinion of Probable Project Costs Including Carroll
Ecton
$42,370,000
The estimated project development costs of $5,965,000
include the following associated with the WTP:
Construction contingency Allowances Engineering fees WMU costs
Schedule
Raw & Finished Water Transmission Main
Preliminary Design Phase
- Nov. 1, 2013 – Dec. 31, 2013
Submit Draft Technical Memorandum
February 3, 2014
Submit Encroachment Permits
February 3, 2014
Meeting with WMU to present Final TM
February 14, 2014
Submittal to KY Division of Water
February 28, 2014
TM Presentation to WMU Board
March 6, 2014
Submit Environmental Permits
March 7, 2014
Public meeting to obtain easements
March 28, 2014
Conduct Geotechnical Investigations
Start March, 2014
Final Design Phase
January 1 – June 14, 2014
Advertising / Bidding Phase
June 14 – July 8, 2014
Award Construction
August 1, 2014
Begin Construction
August 1, 2014
Substantial Completion
February 1, 2015
Schedule
Water Treatment Plant
Conceptual Design Meeting with KYDOW
August 1, 2014
Preliminary Design Phase
August 1, 2014 – January 31, 2015
Submit Preliminary Engineering Report
February 3, 2015
Meeting with WMU to present Final PER
February 14, 2015
Submit Environmental Permits
February 14, 2015
Submittal to KY Division of Water
February 14, 2015
Presentation to WMU Board
February 21, 2015
Final Design Phase
January 1 – May 15, 2015
Advertising / Bidding Phase
May 15 – June 15, 2015
Award Construction
July 1, 2015
Begin Construction
July 1, 2015